##Cover-do-not-delete. Cover page is required at any template as the first page.

##

MPT-Cell Deactivate
Implementation Solution for
NPT00080 Sector A(900MHz)

Prepared by: Sai Kaung Myat Htoo Date: 02.01.2023

Reviewed by: Ko Lin Ko Date: 02.01.2023

Approved by: Ko Than Htike Oo Date: 02.01.2023

Contents
1 Description of Change................................................................................................................3
1.1 Description of Site..............................................................................................................3

1.2 Purpose and Requirements.................................................................................................3

2 Preparations for Change..............................................................................................................4

2.1 Composition of Change Team and Responsibility of Team Members.............................4

2.1.1 Approval Team..............................................................................................................4

2.1.1 On-site Change Team............................................................................................4

2.2 Remote Access+ Platform and Software Preparation........................................................5

2.3 Check of Equipment Running............................................................................................5

3 Operation Steps for Change........................................................................................................7

3.1 Overall Description of Change Steps.................................................................................7

3.2 Operation Steps for Change...............................................................................................8

3.3 Test and Verification........................................................................................................10

3.4 Solution for Change back In the Case of Failure.............................................................10

3.4.1 Definition of Change Failure................................................................................10

3.4.2 Change back Steps..............................................................................................11

3.4.3 Changeback Risk Analysis..........................................................................................11

3.5 Change of Spare Parts and Emergency Workstation.......................................................11

4 Work After Change...................................................................................................................12

4.1 Observation......................................................................................................................12
1 Description of Change

1.1 Description of Site

Network topology diagram NPT00080

Block Sector A RRU


Key features and business
900 MHz service impact

Related business amount 900 MHz service impact

1.2 Purpose and Requirements

Change purpose* Cell Deactivate for troubleshooting

Change scope Cell deactivates at 900 MHz service impact

Change time* 03-Jan-2023 [09:00 to 11:00]

2 Preparations for Change

2.1 Composition of Change Team and Responsibility of Team Members

2.1.1 Approval Team

Name Responsibility Telephone No.

Pyae Min Naing Manager 09-423008507

2.1.1 On-site Change Team

Name Responsibility Telephone No.

Lin Ko Wireless Team 09423006394

Sai Kaung Myat Htoo Wireless Team 09423009079


Sai Khun Sai Wireless Team 09423009069

2.2 Remote Access+ Platform and Software Preparation

Type Content Owner

Remote access Remote access authorization: [Customer do not approve for remote

authorization access as per security rule]

Remote access test Remote access test: [NMS]

Platform, software and Clearly describe the needed tools software, material, backup

license communication, license, etc. and responsible owner

Site permission Yes

NE login permission U2020

Tools and Softwires NA

2.3 Change Risks and Countermeasures

Main Issues and Countermeas


No. Risk Category Possibility Impact
Risks Description ure

RRU hardware
Mobile service
1 Hardware Faulty/RRU down faulty/RRU Low 900MHz service will impact
down
Down.

3 Operation Steps for Change

3.1 Overall Description of Change Steps

No. Main steps Start time End time


1 Preparation before Operation 8:00 8:30

2 Log in and Information Backup 8:30 8:45

3 Service Confirmation 8:45 9:00

4 Change Procedure 9:00 9:30

5 Operation and Service Verification 9:30 10:00

6 Briefly Report After the Operation 10:00 10:15

7 Rollback Steps 10:15 10:30

8 Service verification 10:30 11:00

3.2 Operation Steps for Change

Implementatio
No. * Change Step* Operation* Time*
n Person*

1 Arrange onsite engineer Onsite support  Xxx(LSP Name)

1. Run MML command

"DSP BRD" to check

all of the board running

status Sai Kaung Myat

2 Health check ( 60mins before operation) 2. Check current alarm Htoo/ Sai Khun 7:00-7:15

in BTS sai

3. Check the current

KPI of BTS

Sai Kaung Myat

3 Login to LMT Login to U2020 Htoo/ Sai Khun 7:15-7:30

sai

Run the command


Sai Kaung Myat
Back up the DB, Performance files, SSL "BKP DB" to back up
4 Htoo/ Sai Khun 7:30-8:00
certificate and license data
sai
 from  U2020
Run the command DSP Sai Kaung Myat

5 Login to U2020 to check board status GLOCELL to check  Htoo/ Sai Khun 8:00-9:00

NodeB status sai

DEA GCELL: Sai Kaung Myat

6 Deactivate Cell Immediate cell shut Htoo/ Sai Khun 9:00-9:30

down sai

Wireless BO will check


Sai Kaung Myat
the board status by
7 Check the RRU status Htoo/ Sai Khun 9:30-10:00
"DSP BRD" command
sai
and alarms from U2020

Check KPI counter "CS

Traffic" and "PS Sai Kaung Myat

8  Verify the BTS status and alarm Traffic" if is normal Htoo/ Sai Khun 10:00-10:15

trend compare with sai

yesterday

Run the command


Sai Kaung Myat
"BKP DB" to back up
11 Verify the service Htoo/ Sai Khun 10:15-10:30
data
sai

Sai Kaung Myat


Briefly report after the
12 Backing up information Htoo/ Sai Khun 10:30-10:45
operation
sai

Sai Kaung Myat


Send Mail to MOC team and confirm service
Htoo/ Sai Khun 10:45-11:00
and alarm status
sai

3.3 Test and Verification

Change Validation
No. * Test Item* Operation Method* Owner* Time*

NA NA NA NA NA

3.4 Solution for Change back In the Case of Failure

3.4.1 Definition of Change Failure

Changeback time*/ The roll back decision is going to made by Pyae Min Naing

Changeback decision maker*

Rollback condition Hardware and software faulty issue

Change back condition Hardware and software faulty issue

3.4.2 Change back Steps

No.* Changeback Steps* Operation content* Onwer* Time*

Sai Kaung Myat


1 Activate cell Activate cell at xxx 10:15-10:30
Htoo/Sai Khun Sai

DSP BRD Sai Kaung Myat


2 Check RRU status 10:30-10:45
Htoo/Sai Khun Sai

Alarms monitor whether new Sai Kaung Myat


3 Check BTS sites status 10:45-11:00
alarms occur or not from U2020 Htoo/Sai Khun Sai

CS Traffic 

PS Traffic Sai Kaung Myat


4 CS and PS KPI analysis 11:00-12:00
Cell Availability Htoo/Sai Khun Sai

  
3.4.3 Change back Risk Analysis

Main Issues and Risks


No.* Possibility* Impact* Countermeasure*
Description*

900MHz service will


1 RRU hardware Faulty/RRU down Low 900MHz service will impact
impact

3.5 Change of Spare Parts and Emergency Workstation

Type Content Planned Time

Spare parts NA NA

4 Work After Change

4.1 Observation

Observation
No. Observation Item* Observation time* Owner*
method*

1 KPI Take the KPI of the 03-01-2023 12:00- MA Team

same time range one 03-01-2023 15:00

week and one month

before the change as

reference.

2 Alarm Whether there is new 03-01-2023 12:00- MOC Team

generated alarm 03-01-2023 15:00


Monito Before After
Bia
NE red Change(F Change( Accept Bias
s
KPI ill in) Fill in)
Xxx and xxx Cell ≤±3%

Availability

Cell Output KPI (%) was

Availabi for Cell slightly

lity Availability improved

and back to

normal.

CS Call

Setup

Success

Rate(%) &

CS Call PS Call
Output CS
Setup Setup
call setup
Success Success
Success Rate
Rate Rate(%)

were going

in the

normal

trends.

PS Call Output PS PS Call

Drop Call Drop Drop Ratio

Ratio Ratio with with

with PCH PCH(%),

PCH PS R99 Call

Drop Ratio

with
PCH(%)

were

slightly

decreased

as of today

measureme

nt.