1 Description Of Change
Installation & Dismantling Rectyfier
1
Confidential
1.1 Description of Activity
Network
Topology
Diagram
Activity Requirements
1 Taking preparation and collect Alarm log and backup info 28:00 22:30 25 MAR 24 No
2
Confidential
4 Check if any additional Alarm after execution 00:00 00:30 25 MAR 24 No
5 KPI checking (Check Parameter Setting and Test Backup 00:30 02:00 25 MAR 24 No
Time)
1.2.1 Change
The upgrade software will change the NE software version as follows:
3
Confidential
ASRUL +62 822-3999-8221
4
Confidential
1 PLN Capacity Check ASRUL 25 MAR 2024 23:00 ~ 28
+62 822-3999-8151 MAR 2024 04:00
1 Backup and Check Backup data log rectifier andcheck alarm ASRUL 2024-03-25
Alarm +62 822-3999-8151 22:00-22:00
4 Load Balancing Load share to new rectifier (make new ASRUL 2024-03-25
connection cable by injected to cable +62 822-3999-8151 00:00-00:30
existing)
5 Power On New Power On New Rectifier and check all ASRUL 2024-03-25
Rectifier fungtion rectifier module, battery and +62 822-3999-8151 00:00-00:30
load.
5
Confidential
7 Dismantle Rectifier Dismantle injected cable existing, rack and ASRUL 2024-03-25
battery +62 822-3999-8151 00:45-02:30
1 Test Backup Battery Test backup battery after MCB PLN ASRUL 2024-03-25 00:30-
Off +62 822-3999-8151 00:40
Fallback Reason 1. The operation is not completed within the time specified in the solution.
2. Power system Abnormal
2 Move load to Make Sure Load has Move to Existing ASRUL 2024-04-25
Existing Recty Rectifier +62 822-3999-8151 03:15-03:30
6
Confidential
Rectifier +62 822-3999-8151 03:30-03:45
1 Checking Alarm and Load Check alarm and load recty after fallback
2 Service Monitor status Backup time and alarm 2024-03-25 05:00-23:00 ASRUL
+62 822-3999-8151
7
Confidential
6.2 Supporting Material (if any)
No. Work content PIC
8
Confidential