You are on page 1of 81

Classification: PUBLIC Use

Preliminary Acceptance Test

PAT for IPMPLS (CSG) NE8000 M8


HUAWEI

Issued: 10-Aug-2020
Version: 1.6

PAT Reference

SED No.: W-2375-CSG-01-EXP(REL)-01 Rack Location: RACK-06

Project Name / No.:


Saudi Mobily Intelligent Transport Network Project 2018
W-2375-CSG-01-
Job No.: District: West City: Makkah
EXP(REL)-01
Site No.: WR_2375 Site Coordinates: 39.905100; 21.430900
1628568
Mobily TAG No.:
210235550210H7000053
Shelf Serial No.:

PAT {NE8000 M8} {HUAWEI} Page 1 of 58

PUBLIC
Classification: PUBLIC Use

Document Control Reference

Version Date Comments Author


1.0 20-Nov-2016 Initial Deng Yanchao

1.1 04-May-2017 Release Deng Yanchao

1.2 15-Aug-2017 Revise 4.4.2 Deng Yanchao

1.3 05-Nov-2017 Revise Songwei

1.4 14-Jan-2018 Delete 3.4 & Revise 3.6 Guan Jun


Update SFP, Switchover/throughput
1.5 29-Jan-2020 Test, Rehan

1.6 10-Aug-2020 Update 4.4.3 Ring Test Scenario Sajid Hussain

Document Approval Reference

Name Designation Department Signatures Date


Turki H. Transport Products & IoT Technical
Almoterey Senior Specialist Manager Solutions 10-Aug-2020
Technical
Adnan Farid Chief Engineer
Solutions 10-Aug-2020

PAT {NE8000 M8} {HUAWEI} Page 2 of 58

PUBLIC
Classification: PUBLIC Use

Contents
1. INTRODUCTION .................................................................................................................................. 5
1.1 SCOPE ............................................................................................................................................. 5
1.2 EQUIPMENT, SUB-RACKS AND FIRMWARE ............................................................................... 6
1.3 LIST OF TEST EQUIPMENT’S USED DURING THIS PAT ............................................................ 6
2. LIST OF TEST CASES ........................................................................................................................ 7
3. HARDWARE ACCEPTANCE TEST .................................................................................................... 9
3.1 NE8000 M8 PANEL .......................................................................................................................... 9
3.2 SITE ACCEPTANCE QUALITY CHECK LIST .............................................................................. 10
Mechanical Installation Verification. ................................................................................................... 10
3.3 BILL OF QUANTITIES AVAILABLE AS PER SITE ...................................................................... 15
3.4 BOARD HOT PLUG ABILITY TEST FOR PIC (FIELD) ................................................................ 16
3.5 POWER MODULE REDUNDANCY TEST (FIELD) ....................................................................... 17
3.6 NE8000 M8 SYSTEM REBOOT BY POWER OFF (FIELD) .......................................................... 18
3.7 DC VOLTAGE AND GROUNDING TEST (FIELD) ........................................................................ 19
3.8 NE8000 M8 INTERFACE TRANSCEIVER TX POWER VERIFICATION (FIELD) ....................... 20
3.9 NE8000 M8 INTERFACE TRANSCEIVER RX POWER VERIFICATION (FIELD) ....................... 22
3.10 NE8000 M8 OPTICAL MODULE RECEIVER SENSITIVITY TEST (FIELD) ................................ 24
3.11 NE8000 M8 BIDI OPTICAL MODULE RECEIVER SENSITIVITY TEST (FIELD) ....................... 26
3.12 NE8000 M8 1000BASE-T-SFP MODULE PORT TEST (FIELD) .................................................. 28
4. SOFTWARE ACCEPTANCE TEST .................................................................................................. 29
4.1 SOFTWARE AND DEVICE STATUS ............................................................................................ 29
4.1.1 NE8000 M8 CONFIGURATION (NOC) ...................................................................................... 29
4.1.2 NE8000 M8 ROUTER VRP SOFTWARE VERSION (NOC) ...................................................... 30
4.1.3 STORAGE SPACE (NOC).......................................................................................................... 31
4.1.4 NE8000 M8 DEVICE STATUS (NOC) ........................................................................................ 32
4.1.5 NE8000 M8 CARD STATUS (NOC) ........................................................................................... 33
4.1.6 NE8000 M8 INTERFACE STATUS (NOC) ................................................................................. 34
4.1.7 NE8000 M8 CONFIGURATION BACKUP & RESTORE (NOC) ................................................ 35
4.1.8 NMS TEST (NOC + FIELD) ........................................................................................................ 36
4.2 DEVICE ACCESS INFORMATION ................................................................................................ 37
4.2.1 NE8000 M8 SSH STATUS (NOC) .............................................................................................. 37
4.2.2 NE8000 M8 DEVICE LOGIN INFORMATION (NOC) ................................................................ 38
4.3 IP PROTOCOL STATUS ................................................................................................................ 39
4.3.1 NE8000 M8 IGP STATUS (NOC) ............................................................................................... 39
4.3.2 NE8000 M8 LDP STATUS (NOC) .............................................................................................. 40
4.3.3 NE8000 M8 BGP STATUS (NOC) ............................................................................................. 41
4.3.4 NE8000 M8 NTP STATUS (NOC) .............................................................................................. 42

PAT {NE8000 M8} {HUAWEI} Page 3 of 58

PUBLIC
Classification: PUBLIC Use

4.3.5 NE8000 M8 BFD STATUS (NOC) .............................................................................................. 43


4.4 LINK PROTECTION/STABILITY TESTING .................................................................................. 44
4.4.1 NE8000 M8 TRAFFIC SWITCHOVER TEST (FIELD) ............................................................... 44
4.4.2 RING STABILITY TEST (Y.1564 TEST) (NOC + FIELD) FOR EXISTING LINK ...................... 45
4.4.3 RING STABILITY TEST (Y.1564 TEST) (NOC + FIELD) NEW LINK ADDITION. .................... 46
4.5 SECURITY TEST ........................................................................................................................... 47
4.5.1 MBSS VERIFICATION (NOC) .................................................................................................... 47
4.5.2 PROTOCOL AUTHENTICATION (NOC) ................................................................................... 48
4.5.3 SNMP SECURITY (NOC) ........................................................................................................... 49
5. TEST RESULTS PARTICIPATION REFERENCE ............................................................................ 50
6. ACCEPTANCE TEST REPORT (FIELD) .......................................................................................... 51
7. OUTSTANDING ISSUES LIST (FIELD) ............................................................................................ 52
8. ACCEPTANCE TEST REPORT (NOC) ............................................................................................. 53
9. OUTSTANDING ISSUES LIST (NOC) .............................................................................................. 54
10. TEST RESULTS SUMMARY ......................................................................................................... 55
11. ABBREVIATIONS .......................................................................................................................... 57

PAT {NE8000 M8} {HUAWEI} Page 4 of 58

PUBLIC
Classification: PUBLIC Use

1. Introduction
1.1 Scope
This document presents the Preliminary Acceptance Test prerequisites, test procedure for the Etihad Etisalat

Company Project according to Mobily and Huawei Tech. Inv. Saudi Arabia standards. The following diagram
shows the topology of this project.

M2000
U2000
EPC
IP Clock
RNC
Core Network BSC

P/DST
Metro DWDM AGG
ASG CX600-X16A
ACC ACC
CSG NE8000 M8

MW

BS
eNodeB NodeB BTS eGNodeB
(SRAN)

PAT {NE8000 M8} {HUAWEI} Page 5 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

1.2 Equipment, Sub-racks and Firmware

Name Version Quantity

w2375-ICSG-HU01 V800R012 1

1.3 List of Test Equipment’s used during this PAT


The analyzers that will be used during the test are listed below:

Test Equipment Brand Name Model No Serial No Calibration Date

Optical power Meter JDSU OLP-35 AY-386 2020-12-10(3 Year)

Optical light attenuator VIAVI OLA-55 AD-0208 2020-04-26(3 Year)

PAT {NE8000 M8} {HUAWEI} Page 6 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

2. List of Test Cases


Detail Test description

Test Categorization
Test Descriptions
No (SA/NSA)

3.2 Site Acceptance Quality Check List See QCC list


SA (exemption:
accessories e.g.
3.3 Bill of Quantities Available As Per Site
grounding
strap..etc)
3.4 Board Hot Plug Ability Test for PIC SA

3.5 Power Module(PSU) Redundancy Test SA

3.6 NE8000 M8 System reboot by Power off SA

3.7 DC Voltage and Grounding Test SA

3.8 NE8000 M8 interface transceiver TX Power Verification SA

3.9 NE8000 M8 interface transceiver RX Power Verification SA

3.10 NE8000 M8 optical module receiver sensitivity test (Field) SA

3.11 NE8000 M8 BIDI optical module receiver sensitivity test (Field) SA

3.12 NE8000 M8 1000BASE-T-SFP Module port test SA

4.1.1 NE8000 M8 Configuration Verification SA

4.1.2 NE8000 M8 Router VRP Software Version SA

4.1.3 Storage Space SA

4.1.4 NE8000 M8 Device Status SA

4.1.5 NE8000 M8 Card Status SA

4.1.6 NE8000 M8 Interface Status SA

4.1.7 NE8000 M8 Configuration Backup & Restore Test NSA

4.1.8 NMS Test SA

4.2.1 NE8000 M8 SSH Status NSA

4.2.2 NE8000 M8 Device login information NSA

PAT {NE8000 M8} {HUAWEI} Page 7 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.3.1 NE8000 M8 IGP status SA

4.3.2 NE8000 M8 LDP Status SA

4.3.3 NE8000 M8 BGP Status SA

4.3.4 NE8000 M8 NTP Status SA

4.3.5 NE8000 M8 BFD Status SA

4.4.1 Traffic Protection Test (remote-LFA) SA

4.4.2 Ring stability test (Y.1564 Test) SA

4.5.1 MBSS Verification (NOC) SA

4.5.2 Protocol Authentication (NOC) SA

4.5.3 SNMP Security (NOC) SA

PAT {NE8000 M8} {HUAWEI} Page 8 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

3. Hardware Acceptance Test


3.1 NE8000 M8 Panel

Equipment Inventory
Site Name Slot/Port List of Equipment Quantity SN#
Optical Transceiver(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,-
0/2/4 1 INGBQ0032127
12.6dBm,LC,SM,10km)
Optical Transceiver(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,-
0/2/6 1 EM195200030679
12.6dBm,LC,SM,10km)
Optical Transceiver(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,-
0/2/7 1 EC195200090348
12.6dBm,LC,SM,10km)
Optical Transceiver(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,-
0/2/8 1 EM195200030652
12.6dBm,LC,SM,10km)

w2375-ICSG-HU01

PAT {NE8000 M8} {HUAWEI} Page 9 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

3.2 Site Acceptance Quality Check List

Mechanical Installation Verification.


Objective: Hardware installation, rack, cable and fiber labeling is complete and to Vendors and customer
standards.
Item Result Categorization Issue
Topic Check content Reference
No Pass Fail NA (SA/NSA) Description
The installation position of racks,
subrack/chassis, ODF and DDF is
according to the site engineering design Approved Floor
1
and the vertical errors of the racks Plan
SA
should be less than 3mm. (vertical
slope).
The assembly of subracks, shelves , air
ramps ,FPP, (chassis) are reliable and air
space is as per installation manual Installation
2
available for equipment sub racks (3 inch manual
SA
air space if not stated on the installation
A. Cabinet or Rack Installation

manual).
Racks fixed
All of the expansion bolts used to fix properly from
support (or foot) should be installed top and
firmly. Fixing screws and nuts (bolt) bottom
3 should be installed by the correct order. (according to SA
The installation holes of the support (or the installation
foot) are matched with expansion bolts manual/ITFM
perfectly. installation
guidelines)
The mechanical accessories of cabinet Installation
4
should be installed correctly manual
NSA
The movable accessories of the cabinet
should work normally. Doors locks, Fan Installation
5
tray, The cabinet key has to be attached Manual
NSA
and working well.
All connecting bolts in the cabinet are Installation
6
installed correctly and firmly Manual
NSA
The racks, sub racks or part of the racks
are not scratched or smeared or
7
distorted. This may be affecting the
NSA
equipment appearance.
The boards can be plugged and
unplugged smoothly (cards ejectors are
Installation
8 working normally). Its panel screws
Manual
SA
should have appropriate tightness if they
exist.

PAT {NE8000 M8} {HUAWEI} Page 10 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

Item Result Categorization Issue


Topic Check content Reference
No Pass Fail NA (SA/NSA) Description
All of the inlet/outlet cable holes of the Reference
cabinet should be blocked out. The Manual,
width of gap should be less than 1.8 cm. Approved
9 The side of plastic inlet/outlet cable hole materials & NSA
A. Cabinet or Rack Installation

should be cut properly. Tidy and ITFM


Insulating and fireproof materials should Installation
be used. Guidelines
The antistatic wrist strap is existed &
10 inserted into the antistatic installation NSA
hole in the cabinet.
All of dummy plates (filler card) and
11 panels should be installed according to SED NSA
requirements & per the SED.
The sundries of redundant cable ties and Best Practice &
screws and other things should not exist ITFM
12
inside, or at the bottom, or on the top of Installation
NSA
the cabinet. Guidelines
As per the
The row and column labels of the approved
cabinet should be stuck in a clear and material,
13 tidy way. If there has a dashed box on Labeling NSA
the cabinet, labels should be stuck within Format & ITFM
it. Installation
Guidelines
Signals cables should be properly routed
without crossing the equipment Installation
14
ventilation holes, fan trays and power manual
SA
modules.
No breakage or rupture and
15 intermediate connector is found on the Best Practice SA
B. Installation of Signal Cables

signal cable or connectors


Cables should be tied with uniform
spacing and moderate tightness. Cable Installation
16 ties should be tied in a tidy way. Their manual &Best NSA
redundant/excess parts should be cut Practice
from their bottom.
Distribution of cables outside cabinet:
1. The cables should be distributed
without any crossing and bending.
2. Arranged and organized in the cable
tray without bending, and cables are not
overflow the tray.
3. When using the cable ladder, they
should be tied in rectangular beams. Installation
17 When the spacing between the cable Manual ,SED, SA
ladder and the top of the cabinet is more Best Practice
than 0.6 m, a cable ladder should be
added on the top of cabinet.
4. When several layers of cables are
distributed under the floor in an
overlapped way, their height should not
exceed 1/2 of the height of the space
below the raised floor.
Topic Check content Reference Result Categorization

PAT {NE8000 M8} {HUAWEI} Page 11 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

Item (SA/NSA) Issue


Pass Fail NA
No Description
If cables should be peeled off at the
position where they would be led out
18
from the sub-rack, they should be peeled
Best Practice SA
off in an orderly and proper way.
When the fiber is outside the cabinet, it
must be protected with Spiral Wrap,
routed away from the rack using proper
19 tie- down bar along the rack. Best Practice SA
Spiral/"hook-and-loop fasteners"
(Velcro) to be used inside the rack for
fibers.
When laying patch cords out site cabinet
fiber guides/trunk should be used and
SA
B. Installation of Signal Cables

20 Best Practice
the patch cords should be organized
properly inside the facility.
Fibers jumpers (FPP-to-FPP/ODF) are
Installation
routed using the right side of the cable
21
management facilities and fiber guides in
manual & Best SA
Practice
tidy and organized manner.
The “left side” of the ODF cable
Installation
management should be used for all
22
equipment termination (Equipment-to-
manual & Best SA
Practice
FPP/ODF)
Proper patch cords length should be
used to avoid fiber coils inside a cabinet
(should be coiled into a circle of more
than 8 cm before it is fixed if it is a must).
23
1meter is the maximum allowed excess
Best Practice SA
length and this should be properly
routed/coiled to avoid blocking airflow
or over utilizing space.
The patch cords connector should be
clean without any dust. The unused
24 optical fiber head and board optical port Best Practice NSA
should be covered with protection caps
(dust caps).
The cable labels are filled in and pasted
As per the
correctly and reliably. Their positions are
Approved
25 orderly and in the same uniform. Cable
Format &
NSA
labels should be stuck at the place 2cm
Materials
away from their connector.

PAT {NE8000 M8} {HUAWEI} Page 12 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

Item Result Categorization Issue


Topic Check content Reference
No Pass Fail NA (SA/NSA) Description
DC Distribution Panel and the Fuse Unit is Installation
installed with correct rating, undamaged Manual/
26 & labeled. All installed fuses are functional approved SA
& its protection rating as per designated materials
load requirement. &format

The cable route of the power cable or


ground cable should be distributed and Installation
27 manual & Best SA
tied tidily, and should be connected in a Practice
correct and reliable way.
The diameter of the power cable, ground
Equipment
cable or equipment potential cable
28
between cabinets should meet the power
reference SA
manual
distribution requirement of equipment.
The power cable and grounding cable
applicable
29 must be without any connector in SA
C. Power and Ground Cabling

standards
between.
When the grounding cable and power Installation
cable is connected to the distribution box manual, F40,
30
or PDU/TRU/PDP, its redundant/excess F42 Guidelines
SA
part should be cut and cannot be coiled. & Best Practice
The power cable/ground cable should be
Installation
routed away from the signal cable outside
31
the cabinet at least it should be more than
manual & Best NSA
Practice
3 cm.
The color of power cables and ground
cables should be specified according to
the standard The –48V power cable is applicable
32
blue; the GND (BGND) ground cable is standards
SA
black (red), and the PGND protection
cable is yellowish green or yellow.
The bending position of the power cable
33
and ground cable should be smooth.
Best Practice NSA
When making lugs for the power and
ground cables, the lugs should be
Installation
soldered or crimped firmly. Lugs edge
manual, F40,
34 should touch the cable insulation, copper
F42 Guidelines
SA
shouldn't be visible and then crimped
& Best Practice
point should be covered with shrinking
tube.
The protection grounding cable of DDF
Installation
and ODF should be connected firmly.
35
Those between adjacent frames should be
manual & Best NSA
Practice
interconnected.(6mm2)
The ground cable of cabinet door should Installation
36 be connected in a correct and reliable manual & Best NSA
way。 Practice

PAT {NE8000 M8} {HUAWEI} Page 13 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

Item Result Categorization Issue


Topic Check content Reference
No Pass Fail NA (SA/NSA) Description
D. General Environment of the site / C. Power and Ground

The power cable labels are filled in and


pasted correctly and reliably. Their
As per the
Cabling

positions are orderly and in the same


approved
37 uniform. Cable labels should be stuck at
material
NSA
the place 2cm away from their
&format
connector.(according the approved
material and format)

The floor gaps or tiles around the rack


Best Practice
should be blocked up. Discarded cable
38
ties, screws and other sundries should not
and ITFM NSA
Guidelines
be found under the floor.
Equipment Room

The equipment room should be clean and


39 tidy. Discarded packing materials should Best Practice NSA
be cleaned.

Loop patch cords, punching tools or other


40 O&M tools should be available in secured Best Practice NSA
area

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 14 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

3.3 Bill of Quantities Available As Per Site

Bill Of Quantities Verification


Site: w2375-ICSG-HU01 System NE8000 M8 Software V800R012
Item Description Item Code Qty.
Optical Transceiver(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,-
OSX001002 4
12.6dBm,LC,SM,10km)

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 15 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

3.4 Board Hot Plug Ability Test for PIC (Field)

Purpose To verify the board hot plug ability of the router (PIC)

Setup

CX600-
Procedure 1. Plug out the hot pluggable cards from device and record the device state by below
X2M8A

CLI.
display device pic
display health
display alarm hardware
display alarm active

2. Plug card into the router again and observe the state.
display device pic
display health
display alarm hardware
display alarm active

Expected The router should run stably, the router is kept working without interruption.
Results

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 16 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

3.5 Power Module Redundancy Test (Field)

Purpose Verify redundancy of power supply and the actual capability.

Setup

CX600-M2F
1. The router provides 1+1 redundancy backup for the DC power supply.
Procedure 1. Pre check the router status by below conmmand.
Display health
Display alarm all
Display device pic
2. Keep pinging the loopback address of NE8000 M8.
3. Power off one PM of the router when the router is running.
4. Observe the working Status of the redundant power supply and the router, check
whether there is any packet lost.
Expected The redundant power supply should take over the work of the primary power supply
Results and the router should run stably, the router keeps working without interrupt.

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 17 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

3.6 NE8000 M8 System reboot by Power off (Field)

Purpose Confirm the NE8000 M8 can recover after hard reboot.

Setup None
Procedure 1. Keep pinging the NE8000 M8 loopback address
2. Use command line to record the configuration, logs, CPU/memory, alarms,
interface status, card register status.
Display current-configuration
Display logbuffer
Display alarm all
Display device
Display device pic
Display health
Display interface brief
3. Turn off the power.
4. After 5 min, turn on the power again.
5. Check the configuration/status after reboot and compare with file before reboot.
Display current-configuration
Display logbuffer
Display alarm all
Display device
Display device pic
Display health
Display interface brief

Expected After hard reboot, no configuration is lost.


Results
Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 18 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

3.7 DC Voltage and Grounding Test (Field)

Purpose Confirm the NE8000 M8 received normal power voltage and normal grounding
resistance.
Setup None
Procedure 1. Use the multi-meter to connect the positive and negative terminal of the Power Module to
check the voltage value.
2. Before Power on, measure the grounding resistance, including chassis to rack and rack to
grounding bus bar.
3. Before connecting power cable (If connected, keep the break switch off), measure all the
power module’s resistance from RTN (+) to NEG (-). And measure the opposite from NEG (-)
to RTN (+).
Expected 1. The voltage range is -40V DC ~ -72V DC.
Results 2. The resistance is less than 50 ohms.
3. The resistance between RTN(+) to NEG(-) and NEG(-) to RTN(+) should be greater than
1KΩ.
Results 1. Power module voltage result.

Fuse rating/Fuse Fuse rating


PM Measured Voltage(V) Pass/Fail
location as per EIR Installed/Fuse location
PM1
PM2

2. Grounding cable resistance result.


Between Measured Resistance(OHMS) Pass/Fail
Chassis to Rack
Rack to Grounding

3. PEM resistance result.


PM Measured Resistance(OHMS) Pass/Fail
PM1 RTN(+) to NEG(-)
PM1 NEG(-) to RTN(+)
PM2 RTN(+) to NEG(-)
PM2 NEG(-) to RTN(+)

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 19 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

3.8 NE8000 M8 interface transceiver TX Power Verification (Field)

Purpose Confirm the NE8000 M8 interface transceiver Power is within normal range.

Setup None

Procedure 1. Connect one end of the fiber patchcords to the TX optical interface of the optical
board/module to be tested through the assigned ODF/FPP and the other end to the
test input port of the optical power meter (Note: Set wavelength according to SFP
module type).
2. Read the stable optical power value from the Optical Power Meter.
3. Record the result on Table 1: TX Power result.
4. The Expected Results show the reference value for Tx power.

Expected The actual TX power is within the normal range shown by detailed.
Results SFP Transmit Power Range Model No.
10G-LC-SM-10KM -8.2 to +0.5 dBm OSX001002
10G-LC-SM-40KM -4.7 to +4 dBm OMXD30002
10G-LC-SM-80KM 0 to +4 dBm OSX080N04
10G-LC-MM-0.3KM -7.3 to -1 dBm OSX040N03
1G-LC-SM-10KM -9 to -3 dBm OSG010N05
1G-LC-SM-40KM -5 to 0 dBm OSG040002
1G-LC-SM-80KM -2 to +5 dBm Zx/FC100
1G-LC-MM-0.5KM -9.5 to 0 dBm Sx/FC200 MM
40G-LC-SM-10KM -7 to +2.3 dBm OSM010C02
100G-LC-SM-10KM 0 to +10.5 dBm OSN010N09
10G-LC-SM-10KM (BIDI) -8.5 to +0.4 dBm OSX010B10
10G-LC-SM-10KM (BIDI) -8.5 to +0.4 dBm OSX010B11
10G-LC-SM-40KM (BIDI) 0 to +5 dBm OSX040B02
10G-LC-SM-40KM (BIDI) 0 to +5 dBm OSX040B03
100G-LC-SM-30-40KM +3.5dBm to +8.9dBm OSN030N05
100G-LC-SM-10KM +1.7dBm to +10.5dBm OSN010N24
1G-LC-SM-40KM -2dBm to +3dBm OGEBIDI40
Results See Table 1: TX Power Result.

PAT {NE8000 M8} {HUAWEI} Page 20 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

Table 1: Tx Power Result:

Interface SFP type Expected value Measured value Pass/Fail

0/2/4 10G-LC-SM-10KM -8.2 to +0.5 dBm


0/2/6 10G-LC-SM-10KM -8.2 to +0.5 dBm
0/2/7 10G-LC-SM-10KM -8.2 to +0.5 dBm
0/2/8 10G-LC-SM-10KM -8.2 to +0.5 dBm

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 21 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

3.9 NE8000 M8 interface transceiver RX Power Verification (Field)

Purpose Confirm the NE8000 M8 interface transceiver Power is within normal range.

Setup None

Procedure Optical Ports connected to other equipment:

1. Remove the fiber patchcords to the RX optical interface of the optical board to be
tested and measure the input RX port using the optical power meter.
2. Read the stable optical power value from the Optical Power Meter.
3. Record the result on Table 2: RX Power result.
4. The Expected Results show the reference value for Rx power.

Optical Ports not connected (Free Ports):

1. Make loop the opposing jumpers of the same module through the assigned
ODF/FPP.
2. Remove the fiber patchcords to the RX optical interface of the optical board to be
tested and measure the input RX port using the optical power meter.
3. Read the stable optical power value from the Optical Power Meter.
4. Record the result on Table 2: RX Power result.
The Expected Results show the reference value for Rx power.
Expected The Actual Rx measurement should be 3db greater than the minimum RX threshold.
Results
SFP Received Power Range Model No.
10G-LC-SM-10KM -14.4 to +0.5 dBm OSX001002
10G-LC-SM-40KM -15.8 to -1 dBm OMXD30002
10G-LC-SM-80KM -24 to -7 dBm OSX080N04
10G-LC-MM-0.3KM -9.9 to -1 dBm OSX040N03
1G-LC-SM-10KM -20 to -3 dBm OSG010N05
1G-LC-SM-40KM -23 to -3 dBm OSG040002
1G-LC-SM-80KM -23 to -3 dBm Zx/FC100
1G-LC-MM-0.5KM -17 to 0 dBm Sx/FC200 MM
40G-LC-SM-10KM -13.7 to 2.3 dBm OSM010C02
100G-LC-SM-10KM -4 to +10.5 dBm OSN010N09
10G-LC-SM-10KM (BIDI) -14.4 to +0.5 dBm OSX010B10
10G-LC-SM-10KM (BIDI) -14.4 to +0.5 dBm OSX010B11
10G-LC-SM-40KM (BIDI) -18 to -9 dBm OSX040B02
10G-LC-SM-40KM (BIDI) -18 to -9 dBm OSX040B03
100G-LC-SM-30-40KM -15.4dBm to +2.5dBm OSN030N05
100G-LC-SM-10KM -2.6dBm to +10.5dBm OSN010N24
1G-LC-SM-40KM -23dBm to -3dBm OGEBIDI40
Results See Table 2: Rx Power Result.

PAT {NE8000 M8} {HUAWEI} Page 22 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

Table 2: Rx Power Result:

Interface SFP type Expected value Measured value Pass/Fail


0/2/4 10G-LC-SM-10KM -14.4 to +0.5 dBm
0/2/6 10G-LC-SM-10KM -14.4 to +0.5 dBm
0/2/7 10G-LC-SM-10KM -14.4 to +0.5 dBm
0/2/8 10G-LC-SM-10KM -14.4 to +0.5 dBm

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 23 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

3.10 NE8000 M8 optical module receiver sensitivity test (Field)

Purpose Ensure all optical modules on NE8000 M8 have optimal performance under low optical
power input.
Setup Fiber FPP/
Ports Patch ODF
cords

TX
TX
RX

RX

OPM VOA

Procedure 1. Connect the tester (VOA) to router’s optical port through assigned ODF/FPP as
shown above.
2. Increase the optical attenuation gradually (VOA) till the port go to down state.
3. Measure and record the optical power value on Table 3: RX Sensitivity Result.
4. Test all the port one by one and record the result.

Expected The port of router should not go down as per below receive power range.
Results
SFP Received Power Range Model No.
10G-LC-SM-10KM Less than -14.4 dBm OSX001002
10G-LC-SM-40KM Less than -15.8 dBm OMXD30002
10G-LC-SM-80KM Less than -24 dBm OSX080N04
10G-LC-MM-0.3KM Less than -9.9 dBm OSX040N03
1G-LC-SM-10KM Less than -20 dBm OSG010N05
1G-LC-SM-40KM Less than -17 dBm OSG040002
1G-LC-SM-80KM Less than -23 dBm Zx/FC100
1G-LC-MM-0.5KM Less than -17 dBm Sx/FC200 MM
40G-LC-SM-10KM Less than -13.7 dBm OSM010C02
100G-LC-SM-10KM Less than -4 dBm OSN010N09
100G-LC-SM-30-40KM Less than -15.4 OSN030N05
100G-LC-SM-10KM Less than -2.6 OSN010N24
1G-LC-SM-40KM Less than -23 OGEBIDI40

Note:

A. Not Applicable for collocated connections (NE to NE connection) either


assigned or connected during PAT as per approved design (TDD/SED).

That means the sensitivity test will be not be performed for the following:
1. Ports which are assigned as locally (collocated) or terminated to other
routers (locally connected).
2. Ports which are connected to routers installed on remote POPs via
collocated transmission equipment.

PAT {NE8000 M8} {HUAWEI} Page 24 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

B. Free optical ports that are connected up to assigned FPP, should be clearly
identified and assigned as locally connected or thru dark fiber (OSP) on the
approved TDD/SED.
C. Any Free Optical ports that are connected up to assigned FPP and has no
assigned connectivity as per approved design (TDD/SED), sensitivity test
should be performed.

Results See Table 3: Rx Sensitivity Result.

Table 3: Rx Sensitivity Result:

Measured
Interface SFP type Expected value Pass/Fail
value
0/2/4 10G-LC-SM-10KM Less than -14.4 dBm
0/2/6 10G-LC-SM-10KM Less than -14.4 dBm
0/2/7 10G-LC-SM-10KM Less than -14.4 dBm
0/2/8 10G-LC-SM-10KM Less than -14.4 dBm

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 25 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

3.11 NE8000 M8 BIDI optical module receiver sensitivity test (Field)

Purpose Ensure all optical modules on CX600 have optimal performance under low optical power
input.
Setup

Procedure 1. Connect the tester (VOA) to router’s optical port through assigned ODF/FPP as
shown above. The BIDI SFPs in port1 and port2 should be a pair.
Pair 10KM = (OSX010B11 - OSX010B10)
Pair 40KM = (OSX040B02 - OSX040B03)
2. Increase the optical attenuation gradually (VOA) till one port go to down state.
3. Connect the down port fiber to OPM, Measure and record the optical power value on
Table 4: RX Sensitivity Result.
4. Test all the port pair by pair and record the result.

Expected The port of router should not go down as per below receive power range.
Results
SFP Received Power Range Model No.
10G-LC-SM-10KM (BIDI) Less than -14.4 dBm OSX010B10
10G-LC-SM-10KM (BIDI) Less than -14.4 dBm OSX010B11
10G-LC-SM-40KM (BIDI) Less than -18 dBm OSX040B02
10G-LC-SM-40KM (BIDI) Less than -18 dBm OSX040B03

Note:

A. Not Applicable for collocated connections (NE to NE connection) either


assigned or connected during PAT as per approved design (TDD/SED).

That means the sensitivity test will be not be performed for the following:
1. Ports which are assigned as locally (collocated) or terminated to other routers
(locally connected).
2. Ports which are connected to routers installed on remote POPs via collocated
transmission equipment.

B. Free optical ports that are connected up to assigned FPP, should be clearly
identified and assigned as locally connected or thru dark fiber (OSP) on the
approved TDD/SED.

PAT {NE8000 M8} {HUAWEI} Page 26 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

C. Any Free Optical ports that are connected up to assigned FPP and has no
assigned connectivity as per approved design (TDD/SED), sensitivity test should
be performed.

Results See Table 4: Rx Sensitivity Result.

Table 4: Rx Sensitivity Result:

Measured
Interface SFP type Expected value Pass/Fail
value

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 27 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

3.12 NE8000 M8 1000BASE-T-SFP Module port test (Field)

Purpose Ensure 1000BASE-T-SFP Module work normal.

Setup

CX600
Procedure 1. Connect the laptop to router’s 1000BASE-T-SFP Module port.
2. Configure IP address on NE8000 M8 electrical port and laptop with same subnet,
do ping test.

Expected The ping successful without packet loss


Results

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 28 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4. Software Acceptance Test

4.1 Software and Device Status

4.1.1 NE8000 M8 Configuration (NOC)

Purpose Record the configuration of NE8000 M8

Setup None.

Procedure 1. Login to the NE8000 M8, the node name is displayed before the “#” prompt.
2. Use command “display ip interface brief | include LoopBack0” to check the node IP.
3. Use command “display current-configuration”
4. Verify the node name and IP.
5. Save the configuration.
Expected The Node name and IP is as per SED.
Results
Node name Loopback0
W2375-ICSG-HU01 10.168.1.154

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 29 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.1.2 NE8000 M8 Router VRP Software Version (NOC)

Purpose Confirm the NE8000 M8 Software is the same as mentioned.

Setup None.

Procedure 1. Loggin to CLI of NE8000 M8.


2. Use command “display version”.

Expected The “display version” command shows that the version is V800R011C10.
Results

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 30 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.1.3 Storage Space (NOC)

Purpose Confirm the NE8000 M8 Storage is the same as mentioned.

Setup None.

Procedure 1. Loggin to CLI of NE8000 M8.


2. Use command “display version”.

Expected The “display version” command shows the detailed information of SDRAM and Flash
Results size. Flash should be 32MB. SDRAM should be 8GB.

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 31 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.1.4 NE8000 M8 Device Status (NOC)

Purpose Confirm the NE8000 M8 Status is healthy.

Setup None

Procedure Loggin to CLI of NE8000 M8.


1. Use command “display temperature”.
2. Use command “display alarm all”.
3. display power.
4. display license.
Expected 1. The temperature show normal status.
Results 2. The active alarm list is empty.
3. Both power boards show normal status.
4. License expiry date is "PERMANENT".

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 32 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.1.5 NE8000 M8 Card Status (NOC)

Purpose Confirm the NE8000 M8 Card is working normally.

Setup None

Procedure 1. Loggin to CLI of NE8000 M8.


2. Use command “display device”.

Expected The card status is “normal”.


Results

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 33 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.1.6 NE8000 M8 Interface Status (NOC)

Purpose Confirm the NE8000 M8 interface Status.

Setup None

Procedure 1. Loggin to CLI of NE8000 M8.


2. Use command “display interface brief”.

Expected The interface connected should be up. Unused interfaces should be down.
Results

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 34 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.1.7 NE8000 M8 Configuration Backup & Restore (NOC)

Purpose Confirm the NE8000 M8 doesn’t loss configuration.

Setup None

Procedure 1. Save and backup configuration by “save test.cfg” command.


2. Ping the NE8000 M8 loopback address from ASG.
3. Change the configuration under an unused interface by following command:
Interface gi0/3/X
Shutdown
Quit
Commit
4. Quit to user mode, use “rollback configuration to file test.cfg”.
5. Use “display current interface gig0/3/X”
Expected Interface gig0/3/2 is undo shutdown.
Results

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 35 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.1.8 NMS Test (NOC + Field)

Purpose ensure that the any alarm or abnormality on the equipment should be monitored by the
NMS
Setup None

Procedure 1. Save the configuration.


2. Shutdown a interface from NE8000 M8 and check the alarm form U2000.
3. Record the result and enable the interface.
4. Remove a SFP from NE8000 M8 and check the alarm from U2000.
5. Record the result and plug in the card.

Expected Both interface down and card removal status should be have alarm from U2000.
Results

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 36 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.2 Device Access Information

4.2.1 NE8000 M8 SSH Status (NOC)

Purpose Confirm the NE8000 M8 SSH user data.

Setup None

Procedure 1. Loggin to CLI of NE8000 M8.


2. Use command “display ssh user-information”.

Expected The SSH user information is shown.


Results

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 37 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.2.2 NE8000 M8 Device login information (NOC)

Purpose Confirm the device login information is completed.

Setup None

Procedure 1. Loggin to CLI of NE8000 M8.


2. Use command “display ip interface description” to check the description.

Expected * *
Results * This equipment is private system operated for and by Etihad Etisalat *
* Company. The equipment now being accessed and information available through *
* this equipment is confidential and proprietary. It may be accessed or used *
* only as specifically authorized. Usage of the Device is monitored. By *
* Proceeding with this Logon the User Understands and Consents to the *
* Conditions noted above. All other access or use is prohibited and is *
* Subject to legal action * *
*
***********************************************************************
1. All used interfaces have proper descriptions.

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 38 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.3 IP Protocol Status

4.3.1 NE8000 M8 IGP status (NOC)

Purpose Confirm the NE8000 M8 IGP peer is normal.

Setup None

Procedure 1. Loggin to CLI of NE8000 M8.


2. Use command “display isis peer”.
3. Use command “display isis bfd session all”.

Expected The IS-IS peer state is “up”.


Results The bfd state for isis is up.

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 39 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.3.2 NE8000 M8 LDP Status (NOC)

Purpose Confirm the NE8000 M8 LDP peer is normal.

Setup None

Procedure 1. Loggin to CLI of NE8000 M8.


2. Use command “display mpls ldp session”.
3. Use command “display mpls ldp peer”.
4. Use command “display mpls lsp protocol ldp”.
5. Use command “display mpls bfd session”
Expected 1. All the ldp session is in “operational” status.
Results 2. Ldp peer includes directly connected and remote.
3. Ldp LSP is protected by FRR except there is load-sharing.
4. The bfd for ldp lsp tunnel is up.
Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 40 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.3.3 NE8000 M8 BGP Status (NOC)

Purpose Confirm the BGP Status.

Setup None

Procedure 1. Use command “display bgp peer”.


2. Use command “display bgp vpnv4 all peer”.

Expected 1. The bgp peers status should be “established”.


Results 2. The bgp peers status should be “established”.

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 41 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.3.4 NE8000 M8 NTP Status (NOC)

Purpose Confirm the NE8000 M8 NTP-Service is normal.

Setup None

Procedure 1. Loggin to CLI of NE8000 M8.


2. Use command “display ntp-service status”.

Expected The clock status is shown as “synchronized”


Results

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 42 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.3.5 NE8000 M8 BFD Status (NOC)

Purpose Confirm the NE8000 M8 BFD Status.

Setup None

Procedure 1. Loggin to CLI of NE8000 M8.


2. Use command “display bfd interface”.
3. Use command “display bfd session all verbose”.

Expected The BFD Info should be shown and the status should be up.
Results

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 43 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.4 Link Protection/Stability testing

4.4.1 NE8000 M8 Traffic Switchover Test (Field)

Purpose Verify the link protection mechanism (Remote-LFA) work normally. (only closed ring
applicable)
Setup

Procedure 1. Generate traffic between tester1 and tester2.


2. Disconnect fiber between CSG3 and CSG2. Record switching time.
3. Record and obtain the test results from the Analyzer.
4. Reconnect fiber between CSG3 and CSG2.
5. Record and obtain the test results from the Analyzer.

Expected
Results Scenario Time
Switchover <=200ms
Recovery <=200ms

Results
Measured
Field Scenario PASS/FAIL
Switchover time
Disconnect Fiber Switchover
Reconnect fiber Recovery

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 44 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.4.2 Ring stability test (Y.1564 Test) (NOC + Field) For Existing link

Purpose To verify the capability of board in processing data through measuring the packet loss
ratio, throughput, and delay (Perform by Ring/Link).
Setup

Procedure 1. Connect one analyzer to CSG1, while another to ASG1.


2. Configure L3/L2 VPN service between CSG1 and ASG1.
3. Start the test by using Test standard Y.1564 for 30 minutes for the short path,
including throughput, packet loss and delay, record and obtain the test results from
the Analyzer.
4. Shutdown the link between ASG1 and CSG1 (short path), and start the Y.1564 test
again for 12 hours (via long path), record and obtain the test results from the
Analyzer.
5. Field FME should attend PAT and confirm test result, and NOC engineer sign the
document.
Expected
Results Throughput Packet Loss One Way Delay
Ratio
=interface ≦0.01 % Distance (One way delay)
bandwidth D <=1000km 6ms
D >1000km D x 6µs
Results
Packet Loss One Way Delay
Throughput Pass/Fail
Ratio (ms)

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 45 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.4.3 Ring stability test (Y.1564 Test) (NOC + Field) New link addition.

Purpose To verify the capability of board in processing data through measuring the packet loss
ratio, throughput, and delay (Perform by Ring/Link).For new link addition.
Setup

Procedure 1. Connect one analyzer to UPE1 and another to UPE2.


2. Do CCC configuration for all the in and Out ports for all CSGs for the new
expanded links
3. Start the Y.1564 test for 12 hours (via long path), record and obtain the test results
from the Analyzer.
4. Field FME should attend PAT and confirm test result, and NOC engineer sign the
document.

Expected
Results Throughput Packet Loss One Way Delay
Ratio
=interface ≦0.01 % Distance (One way delay)
bandwidth D <=1000km 6ms
D >1000km D x 6µs
Results
Packet Loss One Way Delay
Throughput Pass/Fail
Ratio (ms)

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 46 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.5 Security test

4.5.1 MBSS Verification (NOC)

Purpose MBSS requirement verification

Setup None
Procedure 1. display current-configuration configuration aaa
2. display current-configuration configuration radius
3. display telnet server
display ftp-server
4. display current-configuration configuration user-interface
5. display current-configuration configuration ntp
6. display ssh server status
7. display info-center
8. display logbuffer
9. display clock
Expected 1.local-user password should be irreversible-cipher
Results authentication scheme should be RADIUS
2. there should be two remote radius service for the authentication.
3.The telnet server shows disable
The FTP server state is disabled
4. Console interface authentication mode should be password, the password should be
encrypted.
VTY interface authentication mode should be aaa, and the protocol is SSH only.
5. NTP service should be with authentication and password is encrypted.
6. SSH version is 2.0, authentication timeout 60 seconds, retry times 3.
SSH login is with ACL restrained
7. Primary and backup log server are configured for the logs backup.
8. Recent log should be showing normally with correct timestamp.
9. The router should be configured with the correct timezone and time is correct.

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 47 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.5.2 Protocol Authentication (NOC)

Purpose Protocol authentication

Setup None

Procedure 1. display current configuration

Expected 1. ISIS should be configured with authentication


Results 2. BGP should be configured with authentication

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 48 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.5.3 SNMP Security (NOC)

Purpose SNMP security

Setup None

Procedure 1. display current configuration

Expected 1. SNMP version is V3


Results 2. SNMP should be configured with authentication
3. SNMP should configure ACL to limit the access

Results Pass / Fail

Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:

Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:

Remarks:

PAT {NE8000 M8} {HUAWEI} Page 49 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

5. Test Results Participation Reference

Mobily Project Mobily Project Mobily Project


Representative Representative Representative PAT Date
Name Designation Signature

Vendor Project Vendor Project Vendor Project


Representative Representative Representative PAT Date
Name Designation Signature

Mobily O&M Mobily O&M Mobily O&M


Representative Representative Representative PAT Date
Name Designation Signature

Vendor MNS Vendor MNS Vendor MNS


Representative Representative Representative PAT Date
Name Designation Signature

PAT {NE8000 M8} {HUAWEI} Page 50 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

6. ACCEPTANCE TEST REPORT (Field)

PROVISIONAL ACCEPTANCE FIELD TEST REPORT

a. Work without Outstanding Items

Work with Non-Service Affecting Items


b.
See the list(s) of Outstanding Items attached (pages ___to ___)

Work with Service Affecting Items


c.
See the list(s) of Outstanding Items attached (pages ___to ___)

Only Local PAT (special circumstances)


d.
See the list(s) of Outstanding Items attached (pages ___to ___)

PAT Start Date (DD/MM/YY): _________________

PAT Completion Date (DD/MM/YY): _________________

Mobily Project Vendor Project Mobily O&M Mobily MNS


Representative Representative Representative Representative
Signature: Signature: Signature: Signature:

Name: Name: Name: Name:


Phone#: Phone#: Phone#: Phone#:
Date: Date: Date: Date:

PAT {NE8000 M8} {HUAWEI} Page 51 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

7. Outstanding Issues List (Field)


The below items have been noted during PAT and shall be cleared within
Clearance
three (3) months from the Preliminary Acceptance Date
Categorization Verified by
Item Date
Description of Outstanding Items Rectified
No.
SA NSA Vendor Mobily

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

Outstanding Items List


Mobily Project Vendor Project Mobily O&M Mobily MNS
Representative Representative Representative Representative
Signature: Signature: Signature: Signature:
Name: Name: Name: Name:
Phone#: Phone#: Phone#: Phone#:

Date: Date: Date: Date:

Clearance
Mobily Project Vendor Project Mobily O&M Mobily MNS
Representative Representative Representative Representative
Signature: Signature: Signature: Signature:

Name: Name: Name: Name:


Phone#: Phone#: Phone#: Phone#:

Date: Date: Date: Date:

PAT {NE8000 M8} {HUAWEI} Page 52 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

8. ACCEPTANCE TEST REPORT (NOC)

PROVISIONAL ACCEPTANCE FIELD TEST REPORT

a. Work without Outstanding Items

Work with Non-Service Affecting Items


b.
See the list(s) of Outstanding Items attached (pages ___to ___)

Work with Service Affecting Items


c.
See the list(s) of Outstanding Items attached (pages ___to ___)

Only Local PAT (special circumstances)


d.
See the list(s) of Outstanding Items attached (pages ___to ___)

PAT Start Date (DD/MM/YY): _________________

PAT Completion Date (DD/MM/YY): _________________

Mobily Project Vendor Project Mobily O&M Mobily MNS


Representative Representative Representative Representative
Signature: Signature: Signature: Signature:

Name: Name: Name: Name:


Phone#: Phone#: Phone#: Phone#:
Date: Date: Date: Date:

PAT {NE8000 M8} {HUAWEI} Page 53 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

9. Outstanding Issues List (NOC)


The below items have been noted during PAT and shall be cleared within
Clearance
three (3) months from the Preliminary Acceptance Date
Categorization Verified by
Item Date
Description of Outstanding Items Rectified
No.
SA NSA Vendor Mobily

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

Outstanding Items List


Mobily Project Vendor Project Mobily O&M Mobily MNS
Representative Representative Representative Representative
Signature: Signature: Signature: Signature:
Name: Name: Name: Name:
Phone#: Phone#: Phone#: Phone#:

Date: Date: Date: Date:

Clearance
Mobily Project Vendor Project Mobily O&M Mobily MNS
Representative Representative Representative Representative
Signature: Signature: Signature: Signature:

Name: Name: Name: Name:


Phone#: Phone#: Phone#: Phone#:

Date: Date: Date: Date:

PAT {NE8000 M8} {HUAWEI} Page 54 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

10. Test Results Summary


Test
Test Description Passed: Failed NA Remarks
No
3.2 Site Acceptance Quality Check List

3.3 Bill of Quantities Available As Per Site

3.4 Board Hot Plug Ability Test for PIC

3.5 Power Module(PSU) Redundancy Test

3.6 NE8000 M8 System reboot by Power off

3.7 DC Voltage and Grounding Test


NE8000 M8 interface transceiver TX Power
3.8
Verification
NE8000 M8 interface transceiver RX Power
3.9
Verification
NE8000 M8 optical module receiver sensitivity
3.10
test
NE8000 M8 BIDI optical module receiver
3.11
sensitivity test (Field)
NE8000 M8 1000BASE-T-SFP Module port
3.12
test
4.1.1 NE8000 M8 Configuration Verification

4.1.2 NE8000 M8 Router VRP Software Version

4.1.3 Storage Space

Mobily Project Representative Vendor Project Representative

Name: Date: Name: Date:

Signature: Signature:

Mobily O&M Representative Vendor MNS Representative

Name: Date: Name: Date:

Signature: Signature:

Test
Test Description Passed: Failed NA Remarks
No

PAT {NE8000 M8} {HUAWEI} Page 55 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

4.1.4 NE8000 M8 Device Status

4.1.5 NE8000 M8 Card Status

4.1.6 NE8000 M8 Interface Status


NE8000 M8 Configuration Backup & Restore
4.1.7
Test
4.1.8 NMS Test

4.2.1 NE8000 M8 SSH Status

4.2.2 NE8000 M8 Device login information

4.3.1 NE8000 M8 IGP status

4.3.2 NE8000 M8 LDP Status

4.3.3 NE8000 M8 BGP Status

4.3.4 NE8000 M8 NTP Status

4.3.5 NE8000 M8 BFD Status

4.4.1 Traffic Protection Test (remote-LFA)

4.4.2 Ring stability test (Y.1564 Test)

4.5.1 MBSS Verification (NOC)

4.5.2 Protocol Authentication (NOC)

4.5.3 SNMP Security (NOC)

Mobily Project Representative Vendor Project Representative

Name: Date: Name: Date:

Signature: Signature:

Mobily O&M Representative Vendor MNS Representative

Name: Date: Name: Date:

Signature: Signature:

PAT {NE8000 M8} {HUAWEI} Page 56 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

11. Abbreviations

Abbreviations Description
ASG Aggregation Site Gateway
BFD Bidirectional Forwarding Detection
BGP Border Gateway Protocol
BSC Base Station Controller
CLI Command Line Interface
CPU Central Process Unit
CRC Cyclic Redundancy Check
CSG Cell Site Gateway
DC Direct Current
DDF Digital Distribution Frame
DWDM Dense Wavelength Division Multiplexing
EPC Evolved Packet Core
FTTX Fiber to the X
IGP Interior Gateway protocol
LAN Local Area Network
LDP Label Distribution Protocol
LPU Line Process Unit
MNS Management Network Service
MPU Main Process unit
MW Microwave
NEG Negative
NTP Network Time Protocol
NPU Network Processing Unit
ODF Optical Distribution Frame
PAT Preliminary Acceptance Test
PEM Power Entry Module
Remote-LFA Remote Loop Free Alternative
RNC Radio Network Controller
RTN Radio Transmission Node
SDH Synchronize Digital Hierarchy
SDRAM Synchronous Dynamic Random Access Memory
SED Site Engineering Design
SFP Small Form Factor Pluggable
SFU Switch Fabric unit
PSU Power supply unit
SNMP Simple Network Management Protocol
SSH Secure Shell
VRP Versatile Routing Platform
WAN Wide Area Network

PAT {NE8000 M8} {HUAWEI} Page 57 of 58

PUBLIC
Classification: PUBLIC Use

Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A

END OF THE DOCUMENT

PAT {NE8000 M8} {HUAWEI} Page 58 of 58

PUBLIC
Saudi Mobily Rise Project W-MAK5-2375-CSG-02-00

SITE ENGINEERING DESIGN

SED Number Job Number Ring Code NE Name

W-2375-CSG-01-EXP(REL)-
W-2375-CSG-01-EXP(REL)-01 01
MKK-10S-H13 W2375-ICG-HU01

District Site Code Long. Lat.


West 2375 39.905095 21.430910

2018

Kingdom of Saudi Arabia


Table of Contents

Section 1. Scope
1.1 Document Change Record---------------------------------------- 3
1.2 Scope Of Work------------------------------------------------------- 4
1.3 Equipment Overview
1.3.1 NE8K Introduction ------------------------------------------ 5
1.3.2 Environmental Specification------------------------------------ 5
1.3.3 Equipment Appearance-------------------------------------------- 5
1.3.4 Power Supply------------------------------------------------------- 5
1.3.5 Mechanical Structure--------------------------------------------- 6
1.3.6 Warning-------------------------------------------------------------- 6
1.4 List of Materials--------------------------------------------------------- 7

Section 2. Detailed Design


2.1 Network Diagram NE8K--------------------------------- 8
2.1.1 Ring Diagram --------------------------------- 9
2.2 Splice Plan ----------------------------------------------------------- 10
2.3 Key MAP -------------------------------------------------------------- 11
2.4 Huawei NE8K Slot Design------------------------------ 12
2.5 Link Connectivity Table
2.5.1 NE8K----------------------------------------------- 13

Section 3.DC Power


3.1 NE8K Power Connectivity Drawing--------------- 14
3.2 Power and Earth Cable Table--------------------------------- 15
3.3 NE8K EIR--------------------------------------------------------- 16

Section 4. Connectivity Information


4.1 Downlink Information-------------------------------------------- 17
4.2 Uplink Information---------------------------------------------------------- 18
4.3 TXM port Information------------------------------------------------------ 19

Section 5.Appendix
5.1 Rack Layout------------------------------------------------------ 20
5.2 Approved Floor plan-------------------------------------------- 21
5.3 Site Location------------------------------------------------------------- 22

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ

VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 2
1.1 Document Change Record

VER Date Revision Description Changed by


1.0 18-June-2020 Saudi Mobily Rise Project Azhar

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ

VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 3
1.2. Scope of Work

This document contains the detailed design of Huawei provisioning platform for all
CSG sites under Mobily Rise Project PO # 61073-0 & 61073-3

1.2.1 Main Scope : (W-MAK5-2375-CSG-02-00)

In this scope, Huawei is installing new equipment NetEngine 8000 M8 on FON sites as
new CSG. This new equipment will replace old existing CSG equipment (model CX600-
M2F & X2M8).

1.2.2 Expansion 1: (SFP Relocation) W-2375-CSG-01-EXP(REL)-01

In this current scope, 4*10G 10km sfp will be installed

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ

VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 4
1.3 Equipment Overview

1.3.1 NE8K Introduction

The NetEngine 8000 has the following characteristics:


Large capacity
Compact size
High reliability
Segment Routing IPv6 (SRv6)
Ethernet virtual private network (EVPN)
In-situ Flow Information Telemetry (iFIT)
Flexible configuration rollback

1.3.2 Environmental Specification

1.3.3 Equipment Appearance

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ

VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 5
1.3.4 Power Supply
[IPU-1T2]DC: 2*IPU-1T2+1*fan+2*DC
power+2*CR5D0E5XMF94+1*CR5D00E4XM25+2*CR5D00LAXF91+2*CR5D00EAGF96=484.34 W
[IPU-1T2]AC: 2*IPU-1T2+1*fan+2*AC
power+2*CR5D0E5XMF94+1*CR5D00E4XM25+2*CR5D00LAXF91+1*CR5D00EAGF96=485.27 W
[IPU-480]DC: 2*IPU-480+1*fan+2*DC power+2*CR5D0E5XMF94+2*CR5D00LAXF91+2*CR5D00EAGF96=428.11 W
[IPU-480]AC: 2*IPU-480+1*fan+2*AC power+2*CR5D0E5XMF94+2*CR5D00LAXF91+2*CR5D00EAGF96=457.79 W

1.3.5 Mechanical Structure

NE8K Chassis main body dimensions and Weight: 132.6 mm x 442 mm x 220 mm (5.22 in. x 17.4 in. x 8.66 in.)

1.3.6 WARNING

Before add the DC power to the equipment, must test the voltage.
When you touch the board, must wear electrostatic strip to prevent damages because of static electricity.

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ

VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 6
1.4 List of Materials

Part
No. Model Description 2375
Number
Qty
1 S0012996 NetEngine 8000 M8(V800R012)
1.1 Hardw are
1.1.1 Basic Configuration
NetEngine 8000 M8 Basic Configuration
(Includes NetEngine 8000 M8 Chassis,2*IPU-
02353ANN CR8PM8BASDC1 1
1T2, 2*DC Pow er,w ithout Softw are Charge
and Document)
1.1.2 Interface Card
Finished Board,NetEngine 8000
03033FXE CR5D00EAGF95 M14,CR51EAGF0,10-port 100/1000Base-X- 1
SFP MACsec Physical Interface Card(PIC)
10-Port 10GE/GE LAN/WAN-SFP+ MACsec
03033BLN CR5D00LAXF91 2
Physical Interface Card(PIC)
1.2 Optical Transceiver
1.2.1 10G SFP+ Optical Transceiver
Optical Transceiver(SFP+,1310nm,10Gb/s,-
S4017483 OSX001002 4
8.2~0.5dBm,-12.6dBm,LC,SM,10km)
Optical
02310PVU OSX080N04 Transceiver(SFP+,1550nm,9.953~10.3125Gb
/s,0~4dBm,-24dBm,LC,SM,80km)
1.2.2 1G SFP/eSFP Optical/Electrical Transceiver
Optical transceiver(eSFP,1310nm,1.25Gb/s,-
S4016067 OSG010N05 1
9dBm~-3dBm,-20dBm,LC,SM,10km)
1.3 Softw are
NetEngine 8000 M8 Base
88035XBC CR8S00BS8CC3 1
SW,VRP8,V800R012
NetEngine 8000 M Series Time
88035VDM CR8S00TMSYC1 1
Synchronization Function License
NetEngine 8000 M Series Core&Aggregation
88035VDV CR8S00CRAGC4 20
Scenario Port Function License(per 10GE)
NetEngine 8000 M Series L3VPN Port
88035VEB CR8S00L3VPC4 20
Function License(per 10GE)
1.4 Softw are Subscription and Support, 1 Year
NetEngine 8000 M Series Base
88060QTQ CR8SMSBS8CC1 1
SW,VRP8,SnS(1 year)
NetEngine 8000 M Series Time
88060QTS CR8SMSTMSYC1 Synchronization Function License SnS(1 1
year)
NetEngine 8000 M Series Core&Aggregation
88060QUB CR8SM4CRAGC1 Scenario Port Function License SnS(per 20
10GE,1year)
NetEngine 8000 M Series L3VPN Port
88060QUG CR8SM4L3VPC1 20
Function License SnS(per 10GE,1year)
1.5 Installation Material
1.5.1 Optical Patch Cord
S4024281 F000FSL00 Optical Patch Cord(PCS) 10
1.5.2 Pow er Cable
Pow er Cable,450V/750V,H07Z-K
25030710 P-10mm^2-Blue-LSZH UL3386,10mm^2,Blue,80A,LSZH 20
Cable,VDE,UL (Unit:meter)
Pow er Cable,450V/750V,H07Z-K
P-10mm^2-Black-
25030711 UL3386,10mm^2,Black,80A,LSZH 20
LSZH
Cable,VDE,UL (Unit:meter)
Pow er Cable,450V/750V,H07Z-K
25030698 CPGN01001 UL3386,10mm^2,Yellow /Green,80A,LSZH 10
Cable,VDE,UL (Unit:meter)

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 7
2.1 Network Diagram

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ

VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 8
2.6 Ring Diagram

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ

VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 9
2.2 Splice Plan

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 10
2.3 KEY MAP

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 11
2.4 Huawei NE8K Slot Design

NE8000-M8
7 8 PIU
5 6 10-port 100/1000M PIC
9 IPU
FAN
10 IPU
3 4 10-Port 10GE/GE PIC
1 2 10-Port 10GE/GE PIC PIU

Slot Card type Function qty


2,4 10-Port 10GE/GE PIC Uplink to other CSG or UPE 2

6 10-port 100/1000M PIC downlink to service node 1

1,5 Reserved downlink to service node 2

3,7,8 Reserved downlink to service node 3

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 12
2.5 Link Connectivity Table

2.5.1 2375-8000 M8

Connectivity will be direct (P2P) between old device to new device


Old device port New Device port
Uplink
W2375.HX2I.01 0/2/5 W2375.HM8I.01 0/3/2

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 13
3.1 NE8K Power Connectivity Drawing

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 14
3.2 Power and Earth Cable Table

POWER I & II + EARTH


CABLE TYPE: Flexible Copper Cable
SITE ID : 2375

FROM TO CABLE
Rectifier
Model Power Type CB No. Rating Equipment Power Supply Module Cable Size (mm2) Type
EMERSON -48V Rectifier CB # 08 32A W2375.HM8I.01 PEM A 10 Blue&Red(-48V)
EMERSON -48V Rectifier CB # 09 32A W2375.HM8I.01 PEM B 10 Blue&Red(-48V)

N/A PGND N/A N/A Earth Point N/A 10 Yellow+Green(PGND)


N/A PGND N/A N/A Earth Point N/A 10 Yellow+Green(PGND)

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 15
3.3 2375 NE8K EIR

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 16
4.1 Downlink connectivity Information

Ports Interface SFP Type FPP connectivity


0/2/0 Optical 10300Mb/s-1310nm-LC-10km(0.009mm) RK06/P04/TR4/Pt 1,2 Local
0/2/1 Optical 10300Mb/s-1310nm-LC-10km(0.009mm) RK06/P04/TR4/Pt 3,4 Local
0/4/0 Optical 10300Mb/s-1310nm-LC-10km(0.009mm) RK06/P04/TR4/Pt 5,6 Local
0/4/1 Optical 10300Mb/s-1310nm-LC-10km(0.009mm) RK06/P04/TR4/Pt 7,8 Local
0/6/5 Optical 1200Mb/s-1310nm-LC-10km(0.009mm) RK06/P04/TR4/Pt 9,10 Local

W-2375-CSG-01-EXP(REL)-01 Downlink Expansion Scope

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 17
4.2 Uplink Connectivity Information

Connectivity will be direct (P2P) between old device to new device


Old device port New Device port
Uplink
W2375.HX2I.01 0/2/5 W2375.HM8I.01 0/3/2

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 18
5.2 Port Information

Ports Interface SFP Type FPP connectivity


0/2/0 Optical 10300Mb/s-1310nm-LC-10km(0.009mm) RK06/P04/TR4/Pt 1,2 Local
0/2/1 Optical 10300Mb/s-1310nm-LC-10km(0.009mm) RK06/P04/TR4/Pt 3,4 Local
0/4/0 Optical 10300Mb/s-1310nm-LC-10km(0.009mm) RK06/P04/TR4/Pt 5,6 Local
0/4/1 Optical 10300Mb/s-1310nm-LC-10km(0.009mm) RK06/P04/TR4/Pt 7,8 Local
0/6/5 Optical 1200Mb/s-1310nm-LC-10km(0.009mm) RK06/P04/TR4/Pt 9,10 Local

CONTRACTOR OWNER

Huawei Technologies Co., Ltd Equipment


P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 19
49 U
5.1 Rack Layout RACK 06

3U PROPOSED SPACE FOR NET ENGINE8000

2U HUAWEI CX600

2U FPP

2U HUAWEI CX600

2U FPP
CONTRACTOR OWNER
2U ODF
Huawei Technologies Co.,
Ltd TITL Equipm
P.O.BOX: 295320 RIYADH 11351 E ent
TEL: 00966 1 2011505 FAX: 00966 1 NE800
Saudi Mobily Rise Project 18-June- Saudi Mobily Rise Project 0M8
1.0 Azhar Project Code: 56A07GZ
2011255
SED 2020
Saudi Mobily Rise Project \
PREPARED
VER REVISION DESCRIPTION DATE PO NO. 61073-0
BY HUAWEI\Page 20
5.1 Approved Floor-plan

CONTRACTOR OWNER

2375
Huawei Technologies Co., Ltd Equipment
P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 21
5.2 Location Information

CONTRACTOR OWNER

2375
Huawei Technologies Co., Ltd Equipment
P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 22
Etihad Etisalat Company
Hardware Relocation Form

Project Title Hardware Relocation Project ID 56A04LD

Project Sponsor Mr. Saeed Date 02-June-2022

PROJECT EQUIPMENTS

The Project Team representatives formally perform Hardware Relocation on operational routers as the following:

# Item Description From Site Slot To Site Slot SN

1 Optical Transceiver W2399-ICSG-HU01 0/4/9 W2375-ICSG-HU01 0/2/4


(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,- INGBQ0032127
12.6dBm,LC,SM,10km)
Optical Transceiver
2 W2399-ICSG-HU01 W2375-ICSG-HU01 0/2/6 EM195200030679
(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,- 0/4/7
12.6dBm,LC,SM,10km)

Optical Transceiver
3
(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,-
W2399-ICSG-HU01
0/4/5
W2375-ICSG-HU01 0/2/7 EC195200090348
12.6dBm,LC,SM,10km)

4 Optical Transceiver W2399-ICSG-HU01 W2375-ICSG-HU01 0/2/8 EM195200030652


(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,- 0/4/3
12.6dBm,LC,SM,10km)
STATEMENT OF FORMAL HARDWARE RELOCATION

The undersigned Project team representative(s) formally performing Hardware Relocation, and the period between dismantling and
installing will be under project responsibility in case of card damage (misuse, stolen, broken)
Project team Representative(s)

Name Name

Position Position

Signature Signature

Date Date

Operations and Maintenance Representative(s)

Name Name

Position Position

Signature Signature

Date Date

You might also like