Issued: 10-Aug-2020
Version: 1.6
PAT Reference
PUBLIC
Classification: PUBLIC Use
PUBLIC
Classification: PUBLIC Use
Contents
1. INTRODUCTION .................................................................................................................................. 5
1.1 SCOPE ............................................................................................................................................. 5
1.2 EQUIPMENT, SUB-RACKS AND FIRMWARE ............................................................................... 6
1.3 LIST OF TEST EQUIPMENT’S USED DURING THIS PAT ............................................................ 6
2. LIST OF TEST CASES ........................................................................................................................ 7
3. HARDWARE ACCEPTANCE TEST .................................................................................................... 9
3.1 NE8000 M8 PANEL .......................................................................................................................... 9
3.2 SITE ACCEPTANCE QUALITY CHECK LIST .............................................................................. 10
Mechanical Installation Verification. ................................................................................................... 10
3.3 BILL OF QUANTITIES AVAILABLE AS PER SITE ...................................................................... 15
3.4 BOARD HOT PLUG ABILITY TEST FOR PIC (FIELD) ................................................................ 16
3.5 POWER MODULE REDUNDANCY TEST (FIELD) ....................................................................... 17
3.6 NE8000 M8 SYSTEM REBOOT BY POWER OFF (FIELD) .......................................................... 18
3.7 DC VOLTAGE AND GROUNDING TEST (FIELD) ........................................................................ 19
3.8 NE8000 M8 INTERFACE TRANSCEIVER TX POWER VERIFICATION (FIELD) ....................... 20
3.9 NE8000 M8 INTERFACE TRANSCEIVER RX POWER VERIFICATION (FIELD) ....................... 22
3.10 NE8000 M8 OPTICAL MODULE RECEIVER SENSITIVITY TEST (FIELD) ................................ 24
3.11 NE8000 M8 BIDI OPTICAL MODULE RECEIVER SENSITIVITY TEST (FIELD) ....................... 26
3.12 NE8000 M8 1000BASE-T-SFP MODULE PORT TEST (FIELD) .................................................. 28
4. SOFTWARE ACCEPTANCE TEST .................................................................................................. 29
4.1 SOFTWARE AND DEVICE STATUS ............................................................................................ 29
4.1.1 NE8000 M8 CONFIGURATION (NOC) ...................................................................................... 29
4.1.2 NE8000 M8 ROUTER VRP SOFTWARE VERSION (NOC) ...................................................... 30
4.1.3 STORAGE SPACE (NOC).......................................................................................................... 31
4.1.4 NE8000 M8 DEVICE STATUS (NOC) ........................................................................................ 32
4.1.5 NE8000 M8 CARD STATUS (NOC) ........................................................................................... 33
4.1.6 NE8000 M8 INTERFACE STATUS (NOC) ................................................................................. 34
4.1.7 NE8000 M8 CONFIGURATION BACKUP & RESTORE (NOC) ................................................ 35
4.1.8 NMS TEST (NOC + FIELD) ........................................................................................................ 36
4.2 DEVICE ACCESS INFORMATION ................................................................................................ 37
4.2.1 NE8000 M8 SSH STATUS (NOC) .............................................................................................. 37
4.2.2 NE8000 M8 DEVICE LOGIN INFORMATION (NOC) ................................................................ 38
4.3 IP PROTOCOL STATUS ................................................................................................................ 39
4.3.1 NE8000 M8 IGP STATUS (NOC) ............................................................................................... 39
4.3.2 NE8000 M8 LDP STATUS (NOC) .............................................................................................. 40
4.3.3 NE8000 M8 BGP STATUS (NOC) ............................................................................................. 41
4.3.4 NE8000 M8 NTP STATUS (NOC) .............................................................................................. 42
PUBLIC
Classification: PUBLIC Use
PUBLIC
Classification: PUBLIC Use
1. Introduction
1.1 Scope
This document presents the Preliminary Acceptance Test prerequisites, test procedure for the Etihad Etisalat
Company Project according to Mobily and Huawei Tech. Inv. Saudi Arabia standards. The following diagram
shows the topology of this project.
M2000
U2000
EPC
IP Clock
RNC
Core Network BSC
P/DST
Metro DWDM AGG
ASG CX600-X16A
ACC ACC
CSG NE8000 M8
MW
BS
eNodeB NodeB BTS eGNodeB
(SRAN)
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
w2375-ICSG-HU01 V800R012 1
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Test Categorization
Test Descriptions
No (SA/NSA)
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Equipment Inventory
Site Name Slot/Port List of Equipment Quantity SN#
Optical Transceiver(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,-
0/2/4 1 INGBQ0032127
12.6dBm,LC,SM,10km)
Optical Transceiver(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,-
0/2/6 1 EM195200030679
12.6dBm,LC,SM,10km)
Optical Transceiver(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,-
0/2/7 1 EC195200090348
12.6dBm,LC,SM,10km)
Optical Transceiver(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,-
0/2/8 1 EM195200030652
12.6dBm,LC,SM,10km)
w2375-ICSG-HU01
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
manual).
Racks fixed
All of the expansion bolts used to fix properly from
support (or foot) should be installed top and
firmly. Fixing screws and nuts (bolt) bottom
3 should be installed by the correct order. (according to SA
The installation holes of the support (or the installation
foot) are matched with expansion bolts manual/ITFM
perfectly. installation
guidelines)
The mechanical accessories of cabinet Installation
4
should be installed correctly manual
NSA
The movable accessories of the cabinet
should work normally. Doors locks, Fan Installation
5
tray, The cabinet key has to be attached Manual
NSA
and working well.
All connecting bolts in the cabinet are Installation
6
installed correctly and firmly Manual
NSA
The racks, sub racks or part of the racks
are not scratched or smeared or
7
distorted. This may be affecting the
NSA
equipment appearance.
The boards can be plugged and
unplugged smoothly (cards ejectors are
Installation
8 working normally). Its panel screws
Manual
SA
should have appropriate tightness if they
exist.
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
20 Best Practice
the patch cords should be organized
properly inside the facility.
Fibers jumpers (FPP-to-FPP/ODF) are
Installation
routed using the right side of the cable
21
management facilities and fiber guides in
manual & Best SA
Practice
tidy and organized manner.
The “left side” of the ODF cable
Installation
management should be used for all
22
equipment termination (Equipment-to-
manual & Best SA
Practice
FPP/ODF)
Proper patch cords length should be
used to avoid fiber coils inside a cabinet
(should be coiled into a circle of more
than 8 cm before it is fixed if it is a must).
23
1meter is the maximum allowed excess
Best Practice SA
length and this should be properly
routed/coiled to avoid blocking airflow
or over utilizing space.
The patch cords connector should be
clean without any dust. The unused
24 optical fiber head and board optical port Best Practice NSA
should be covered with protection caps
(dust caps).
The cable labels are filled in and pasted
As per the
correctly and reliably. Their positions are
Approved
25 orderly and in the same uniform. Cable
Format &
NSA
labels should be stuck at the place 2cm
Materials
away from their connector.
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
standards
between.
When the grounding cable and power Installation
cable is connected to the distribution box manual, F40,
30
or PDU/TRU/PDP, its redundant/excess F42 Guidelines
SA
part should be cut and cannot be coiled. & Best Practice
The power cable/ground cable should be
Installation
routed away from the signal cable outside
31
the cabinet at least it should be more than
manual & Best NSA
Practice
3 cm.
The color of power cables and ground
cables should be specified according to
the standard The –48V power cable is applicable
32
blue; the GND (BGND) ground cable is standards
SA
black (red), and the PGND protection
cable is yellowish green or yellow.
The bending position of the power cable
33
and ground cable should be smooth.
Best Practice NSA
When making lugs for the power and
ground cables, the lugs should be
Installation
soldered or crimped firmly. Lugs edge
manual, F40,
34 should touch the cable insulation, copper
F42 Guidelines
SA
shouldn't be visible and then crimped
& Best Practice
point should be covered with shrinking
tube.
The protection grounding cable of DDF
Installation
and ODF should be connected firmly.
35
Those between adjacent frames should be
manual & Best NSA
Practice
interconnected.(6mm2)
The ground cable of cabinet door should Installation
36 be connected in a correct and reliable manual & Best NSA
way。 Practice
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Purpose To verify the board hot plug ability of the router (PIC)
Setup
CX600-
Procedure 1. Plug out the hot pluggable cards from device and record the device state by below
X2M8A
CLI.
display device pic
display health
display alarm hardware
display alarm active
2. Plug card into the router again and observe the state.
display device pic
display health
display alarm hardware
display alarm active
Expected The router should run stably, the router is kept working without interruption.
Results
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup
CX600-M2F
1. The router provides 1+1 redundancy backup for the DC power supply.
Procedure 1. Pre check the router status by below conmmand.
Display health
Display alarm all
Display device pic
2. Keep pinging the loopback address of NE8000 M8.
3. Power off one PM of the router when the router is running.
4. Observe the working Status of the redundant power supply and the router, check
whether there is any packet lost.
Expected The redundant power supply should take over the work of the primary power supply
Results and the router should run stably, the router keeps working without interrupt.
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Procedure 1. Keep pinging the NE8000 M8 loopback address
2. Use command line to record the configuration, logs, CPU/memory, alarms,
interface status, card register status.
Display current-configuration
Display logbuffer
Display alarm all
Display device
Display device pic
Display health
Display interface brief
3. Turn off the power.
4. After 5 min, turn on the power again.
5. Check the configuration/status after reboot and compare with file before reboot.
Display current-configuration
Display logbuffer
Display alarm all
Display device
Display device pic
Display health
Display interface brief
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Purpose Confirm the NE8000 M8 received normal power voltage and normal grounding
resistance.
Setup None
Procedure 1. Use the multi-meter to connect the positive and negative terminal of the Power Module to
check the voltage value.
2. Before Power on, measure the grounding resistance, including chassis to rack and rack to
grounding bus bar.
3. Before connecting power cable (If connected, keep the break switch off), measure all the
power module’s resistance from RTN (+) to NEG (-). And measure the opposite from NEG (-)
to RTN (+).
Expected 1. The voltage range is -40V DC ~ -72V DC.
Results 2. The resistance is less than 50 ohms.
3. The resistance between RTN(+) to NEG(-) and NEG(-) to RTN(+) should be greater than
1KΩ.
Results 1. Power module voltage result.
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Purpose Confirm the NE8000 M8 interface transceiver Power is within normal range.
Setup None
Procedure 1. Connect one end of the fiber patchcords to the TX optical interface of the optical
board/module to be tested through the assigned ODF/FPP and the other end to the
test input port of the optical power meter (Note: Set wavelength according to SFP
module type).
2. Read the stable optical power value from the Optical Power Meter.
3. Record the result on Table 1: TX Power result.
4. The Expected Results show the reference value for Tx power.
Expected The actual TX power is within the normal range shown by detailed.
Results SFP Transmit Power Range Model No.
10G-LC-SM-10KM -8.2 to +0.5 dBm OSX001002
10G-LC-SM-40KM -4.7 to +4 dBm OMXD30002
10G-LC-SM-80KM 0 to +4 dBm OSX080N04
10G-LC-MM-0.3KM -7.3 to -1 dBm OSX040N03
1G-LC-SM-10KM -9 to -3 dBm OSG010N05
1G-LC-SM-40KM -5 to 0 dBm OSG040002
1G-LC-SM-80KM -2 to +5 dBm Zx/FC100
1G-LC-MM-0.5KM -9.5 to 0 dBm Sx/FC200 MM
40G-LC-SM-10KM -7 to +2.3 dBm OSM010C02
100G-LC-SM-10KM 0 to +10.5 dBm OSN010N09
10G-LC-SM-10KM (BIDI) -8.5 to +0.4 dBm OSX010B10
10G-LC-SM-10KM (BIDI) -8.5 to +0.4 dBm OSX010B11
10G-LC-SM-40KM (BIDI) 0 to +5 dBm OSX040B02
10G-LC-SM-40KM (BIDI) 0 to +5 dBm OSX040B03
100G-LC-SM-30-40KM +3.5dBm to +8.9dBm OSN030N05
100G-LC-SM-10KM +1.7dBm to +10.5dBm OSN010N24
1G-LC-SM-40KM -2dBm to +3dBm OGEBIDI40
Results See Table 1: TX Power Result.
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Purpose Confirm the NE8000 M8 interface transceiver Power is within normal range.
Setup None
1. Remove the fiber patchcords to the RX optical interface of the optical board to be
tested and measure the input RX port using the optical power meter.
2. Read the stable optical power value from the Optical Power Meter.
3. Record the result on Table 2: RX Power result.
4. The Expected Results show the reference value for Rx power.
1. Make loop the opposing jumpers of the same module through the assigned
ODF/FPP.
2. Remove the fiber patchcords to the RX optical interface of the optical board to be
tested and measure the input RX port using the optical power meter.
3. Read the stable optical power value from the Optical Power Meter.
4. Record the result on Table 2: RX Power result.
The Expected Results show the reference value for Rx power.
Expected The Actual Rx measurement should be 3db greater than the minimum RX threshold.
Results
SFP Received Power Range Model No.
10G-LC-SM-10KM -14.4 to +0.5 dBm OSX001002
10G-LC-SM-40KM -15.8 to -1 dBm OMXD30002
10G-LC-SM-80KM -24 to -7 dBm OSX080N04
10G-LC-MM-0.3KM -9.9 to -1 dBm OSX040N03
1G-LC-SM-10KM -20 to -3 dBm OSG010N05
1G-LC-SM-40KM -23 to -3 dBm OSG040002
1G-LC-SM-80KM -23 to -3 dBm Zx/FC100
1G-LC-MM-0.5KM -17 to 0 dBm Sx/FC200 MM
40G-LC-SM-10KM -13.7 to 2.3 dBm OSM010C02
100G-LC-SM-10KM -4 to +10.5 dBm OSN010N09
10G-LC-SM-10KM (BIDI) -14.4 to +0.5 dBm OSX010B10
10G-LC-SM-10KM (BIDI) -14.4 to +0.5 dBm OSX010B11
10G-LC-SM-40KM (BIDI) -18 to -9 dBm OSX040B02
10G-LC-SM-40KM (BIDI) -18 to -9 dBm OSX040B03
100G-LC-SM-30-40KM -15.4dBm to +2.5dBm OSN030N05
100G-LC-SM-10KM -2.6dBm to +10.5dBm OSN010N24
1G-LC-SM-40KM -23dBm to -3dBm OGEBIDI40
Results See Table 2: Rx Power Result.
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Purpose Ensure all optical modules on NE8000 M8 have optimal performance under low optical
power input.
Setup Fiber FPP/
Ports Patch ODF
cords
TX
TX
RX
RX
OPM VOA
Procedure 1. Connect the tester (VOA) to router’s optical port through assigned ODF/FPP as
shown above.
2. Increase the optical attenuation gradually (VOA) till the port go to down state.
3. Measure and record the optical power value on Table 3: RX Sensitivity Result.
4. Test all the port one by one and record the result.
Expected The port of router should not go down as per below receive power range.
Results
SFP Received Power Range Model No.
10G-LC-SM-10KM Less than -14.4 dBm OSX001002
10G-LC-SM-40KM Less than -15.8 dBm OMXD30002
10G-LC-SM-80KM Less than -24 dBm OSX080N04
10G-LC-MM-0.3KM Less than -9.9 dBm OSX040N03
1G-LC-SM-10KM Less than -20 dBm OSG010N05
1G-LC-SM-40KM Less than -17 dBm OSG040002
1G-LC-SM-80KM Less than -23 dBm Zx/FC100
1G-LC-MM-0.5KM Less than -17 dBm Sx/FC200 MM
40G-LC-SM-10KM Less than -13.7 dBm OSM010C02
100G-LC-SM-10KM Less than -4 dBm OSN010N09
100G-LC-SM-30-40KM Less than -15.4 OSN030N05
100G-LC-SM-10KM Less than -2.6 OSN010N24
1G-LC-SM-40KM Less than -23 OGEBIDI40
Note:
That means the sensitivity test will be not be performed for the following:
1. Ports which are assigned as locally (collocated) or terminated to other
routers (locally connected).
2. Ports which are connected to routers installed on remote POPs via
collocated transmission equipment.
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
B. Free optical ports that are connected up to assigned FPP, should be clearly
identified and assigned as locally connected or thru dark fiber (OSP) on the
approved TDD/SED.
C. Any Free Optical ports that are connected up to assigned FPP and has no
assigned connectivity as per approved design (TDD/SED), sensitivity test
should be performed.
Measured
Interface SFP type Expected value Pass/Fail
value
0/2/4 10G-LC-SM-10KM Less than -14.4 dBm
0/2/6 10G-LC-SM-10KM Less than -14.4 dBm
0/2/7 10G-LC-SM-10KM Less than -14.4 dBm
0/2/8 10G-LC-SM-10KM Less than -14.4 dBm
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Purpose Ensure all optical modules on CX600 have optimal performance under low optical power
input.
Setup
Procedure 1. Connect the tester (VOA) to router’s optical port through assigned ODF/FPP as
shown above. The BIDI SFPs in port1 and port2 should be a pair.
Pair 10KM = (OSX010B11 - OSX010B10)
Pair 40KM = (OSX040B02 - OSX040B03)
2. Increase the optical attenuation gradually (VOA) till one port go to down state.
3. Connect the down port fiber to OPM, Measure and record the optical power value on
Table 4: RX Sensitivity Result.
4. Test all the port pair by pair and record the result.
Expected The port of router should not go down as per below receive power range.
Results
SFP Received Power Range Model No.
10G-LC-SM-10KM (BIDI) Less than -14.4 dBm OSX010B10
10G-LC-SM-10KM (BIDI) Less than -14.4 dBm OSX010B11
10G-LC-SM-40KM (BIDI) Less than -18 dBm OSX040B02
10G-LC-SM-40KM (BIDI) Less than -18 dBm OSX040B03
Note:
That means the sensitivity test will be not be performed for the following:
1. Ports which are assigned as locally (collocated) or terminated to other routers
(locally connected).
2. Ports which are connected to routers installed on remote POPs via collocated
transmission equipment.
B. Free optical ports that are connected up to assigned FPP, should be clearly
identified and assigned as locally connected or thru dark fiber (OSP) on the
approved TDD/SED.
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
C. Any Free Optical ports that are connected up to assigned FPP and has no
assigned connectivity as per approved design (TDD/SED), sensitivity test should
be performed.
Measured
Interface SFP type Expected value Pass/Fail
value
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup
CX600
Procedure 1. Connect the laptop to router’s 1000BASE-T-SFP Module port.
2. Configure IP address on NE8000 M8 electrical port and laptop with same subnet,
do ping test.
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None.
Procedure 1. Login to the NE8000 M8, the node name is displayed before the “#” prompt.
2. Use command “display ip interface brief | include LoopBack0” to check the node IP.
3. Use command “display current-configuration”
4. Verify the node name and IP.
5. Save the configuration.
Expected The Node name and IP is as per SED.
Results
Node name Loopback0
W2375-ICSG-HU01 10.168.1.154
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None.
Expected The “display version” command shows that the version is V800R011C10.
Results
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None.
Expected The “display version” command shows the detailed information of SDRAM and Flash
Results size. Flash should be 32MB. SDRAM should be 8GB.
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Expected The interface connected should be up. Unused interfaces should be down.
Results
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Purpose ensure that the any alarm or abnormality on the equipment should be monitored by the
NMS
Setup None
Expected Both interface down and card removal status should be have alarm from U2000.
Results
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Expected * *
Results * This equipment is private system operated for and by Etihad Etisalat *
* Company. The equipment now being accessed and information available through *
* this equipment is confidential and proprietary. It may be accessed or used *
* only as specifically authorized. Usage of the Device is monitored. By *
* Proceeding with this Logon the User Understands and Consents to the *
* Conditions noted above. All other access or use is prohibited and is *
* Subject to legal action * *
*
***********************************************************************
1. All used interfaces have proper descriptions.
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Expected The BFD Info should be shown and the status should be up.
Results
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Purpose Verify the link protection mechanism (Remote-LFA) work normally. (only closed ring
applicable)
Setup
Expected
Results Scenario Time
Switchover <=200ms
Recovery <=200ms
Results
Measured
Field Scenario PASS/FAIL
Switchover time
Disconnect Fiber Switchover
Reconnect fiber Recovery
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
4.4.2 Ring stability test (Y.1564 Test) (NOC + Field) For Existing link
Purpose To verify the capability of board in processing data through measuring the packet loss
ratio, throughput, and delay (Perform by Ring/Link).
Setup
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
4.4.3 Ring stability test (Y.1564 Test) (NOC + Field) New link addition.
Purpose To verify the capability of board in processing data through measuring the packet loss
ratio, throughput, and delay (Perform by Ring/Link).For new link addition.
Setup
Expected
Results Throughput Packet Loss One Way Delay
Ratio
=interface ≦0.01 % Distance (One way delay)
bandwidth D <=1000km 6ms
D >1000km D x 6µs
Results
Packet Loss One Way Delay
Throughput Pass/Fail
Ratio (ms)
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Procedure 1. display current-configuration configuration aaa
2. display current-configuration configuration radius
3. display telnet server
display ftp-server
4. display current-configuration configuration user-interface
5. display current-configuration configuration ntp
6. display ssh server status
7. display info-center
8. display logbuffer
9. display clock
Expected 1.local-user password should be irreversible-cipher
Results authentication scheme should be RADIUS
2. there should be two remote radius service for the authentication.
3.The telnet server shows disable
The FTP server state is disabled
4. Console interface authentication mode should be password, the password should be
encrypted.
VTY interface authentication mode should be aaa, and the protocol is SSH only.
5. NTP service should be with authentication and password is encrypted.
6. SSH version is 2.0, authentication timeout 60 seconds, retry times 3.
SSH login is with ACL restrained
7. Primary and backup log server are configured for the logs backup.
8. Recent log should be showing normally with correct timestamp.
9. The router should be configured with the correct timezone and time is correct.
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Setup None
Acceptance Engineer
Signature: Date:
Vendor:
Witnessing Project
Signature: Date:
Engineer Mobily:
Witnessing Engineer
Signature: Date:
O&M MNS/Mobily:
Remarks:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Clearance
Mobily Project Vendor Project Mobily O&M Mobily MNS
Representative Representative Representative Representative
Signature: Signature: Signature: Signature:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Clearance
Mobily Project Vendor Project Mobily O&M Mobily MNS
Representative Representative Representative Representative
Signature: Signature: Signature: Signature:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Signature: Signature:
Signature: Signature:
Test
Test Description Passed: Failed NA Remarks
No
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
Signature: Signature:
Signature: Signature:
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
11. Abbreviations
Abbreviations Description
ASG Aggregation Site Gateway
BFD Bidirectional Forwarding Detection
BGP Border Gateway Protocol
BSC Base Station Controller
CLI Command Line Interface
CPU Central Process Unit
CRC Cyclic Redundancy Check
CSG Cell Site Gateway
DC Direct Current
DDF Digital Distribution Frame
DWDM Dense Wavelength Division Multiplexing
EPC Evolved Packet Core
FTTX Fiber to the X
IGP Interior Gateway protocol
LAN Local Area Network
LDP Label Distribution Protocol
LPU Line Process Unit
MNS Management Network Service
MPU Main Process unit
MW Microwave
NEG Negative
NTP Network Time Protocol
NPU Network Processing Unit
ODF Optical Distribution Frame
PAT Preliminary Acceptance Test
PEM Power Entry Module
Remote-LFA Remote Loop Free Alternative
RNC Radio Network Controller
RTN Radio Transmission Node
SDH Synchronize Digital Hierarchy
SDRAM Synchronous Dynamic Random Access Memory
SED Site Engineering Design
SFP Small Form Factor Pluggable
SFU Switch Fabric unit
PSU Power supply unit
SNMP Simple Network Management Protocol
SSH Secure Shell
VRP Versatile Routing Platform
WAN Wide Area Network
PUBLIC
Classification: PUBLIC Use
Project Name: Saudi Mobily ITN Project SED No: W-2375-CSG-01-EXP(REL)-01 City/District: Makkah/West
Site Code:WR_2375 Job No.: W-2375-CSG-01-EXP(REL)-01 Ring No.: MKK-20S-H19
NE Name: W2375-ICSG-HU01 Rack Location: RACK-06 Shelf Location: P01A
PUBLIC
Saudi Mobily Rise Project W-MAK5-2375-CSG-02-00
W-2375-CSG-01-EXP(REL)-
W-2375-CSG-01-EXP(REL)-01 01
MKK-10S-H13 W2375-ICG-HU01
2018
Section 1. Scope
1.1 Document Change Record---------------------------------------- 3
1.2 Scope Of Work------------------------------------------------------- 4
1.3 Equipment Overview
1.3.1 NE8K Introduction ------------------------------------------ 5
1.3.2 Environmental Specification------------------------------------ 5
1.3.3 Equipment Appearance-------------------------------------------- 5
1.3.4 Power Supply------------------------------------------------------- 5
1.3.5 Mechanical Structure--------------------------------------------- 6
1.3.6 Warning-------------------------------------------------------------- 6
1.4 List of Materials--------------------------------------------------------- 7
Section 5.Appendix
5.1 Rack Layout------------------------------------------------------ 20
5.2 Approved Floor plan-------------------------------------------- 21
5.3 Site Location------------------------------------------------------------- 22
CONTRACTOR OWNER
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 2
1.1 Document Change Record
CONTRACTOR OWNER
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 3
1.2. Scope of Work
This document contains the detailed design of Huawei provisioning platform for all
CSG sites under Mobily Rise Project PO # 61073-0 & 61073-3
In this scope, Huawei is installing new equipment NetEngine 8000 M8 on FON sites as
new CSG. This new equipment will replace old existing CSG equipment (model CX600-
M2F & X2M8).
CONTRACTOR OWNER
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 4
1.3 Equipment Overview
CONTRACTOR OWNER
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 5
1.3.4 Power Supply
[IPU-1T2]DC: 2*IPU-1T2+1*fan+2*DC
power+2*CR5D0E5XMF94+1*CR5D00E4XM25+2*CR5D00LAXF91+2*CR5D00EAGF96=484.34 W
[IPU-1T2]AC: 2*IPU-1T2+1*fan+2*AC
power+2*CR5D0E5XMF94+1*CR5D00E4XM25+2*CR5D00LAXF91+1*CR5D00EAGF96=485.27 W
[IPU-480]DC: 2*IPU-480+1*fan+2*DC power+2*CR5D0E5XMF94+2*CR5D00LAXF91+2*CR5D00EAGF96=428.11 W
[IPU-480]AC: 2*IPU-480+1*fan+2*AC power+2*CR5D0E5XMF94+2*CR5D00LAXF91+2*CR5D00EAGF96=457.79 W
NE8K Chassis main body dimensions and Weight: 132.6 mm x 442 mm x 220 mm (5.22 in. x 17.4 in. x 8.66 in.)
1.3.6 WARNING
Before add the DC power to the equipment, must test the voltage.
When you touch the board, must wear electrostatic strip to prevent damages because of static electricity.
CONTRACTOR OWNER
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 6
1.4 List of Materials
Part
No. Model Description 2375
Number
Qty
1 S0012996 NetEngine 8000 M8(V800R012)
1.1 Hardw are
1.1.1 Basic Configuration
NetEngine 8000 M8 Basic Configuration
(Includes NetEngine 8000 M8 Chassis,2*IPU-
02353ANN CR8PM8BASDC1 1
1T2, 2*DC Pow er,w ithout Softw are Charge
and Document)
1.1.2 Interface Card
Finished Board,NetEngine 8000
03033FXE CR5D00EAGF95 M14,CR51EAGF0,10-port 100/1000Base-X- 1
SFP MACsec Physical Interface Card(PIC)
10-Port 10GE/GE LAN/WAN-SFP+ MACsec
03033BLN CR5D00LAXF91 2
Physical Interface Card(PIC)
1.2 Optical Transceiver
1.2.1 10G SFP+ Optical Transceiver
Optical Transceiver(SFP+,1310nm,10Gb/s,-
S4017483 OSX001002 4
8.2~0.5dBm,-12.6dBm,LC,SM,10km)
Optical
02310PVU OSX080N04 Transceiver(SFP+,1550nm,9.953~10.3125Gb
/s,0~4dBm,-24dBm,LC,SM,80km)
1.2.2 1G SFP/eSFP Optical/Electrical Transceiver
Optical transceiver(eSFP,1310nm,1.25Gb/s,-
S4016067 OSG010N05 1
9dBm~-3dBm,-20dBm,LC,SM,10km)
1.3 Softw are
NetEngine 8000 M8 Base
88035XBC CR8S00BS8CC3 1
SW,VRP8,V800R012
NetEngine 8000 M Series Time
88035VDM CR8S00TMSYC1 1
Synchronization Function License
NetEngine 8000 M Series Core&Aggregation
88035VDV CR8S00CRAGC4 20
Scenario Port Function License(per 10GE)
NetEngine 8000 M Series L3VPN Port
88035VEB CR8S00L3VPC4 20
Function License(per 10GE)
1.4 Softw are Subscription and Support, 1 Year
NetEngine 8000 M Series Base
88060QTQ CR8SMSBS8CC1 1
SW,VRP8,SnS(1 year)
NetEngine 8000 M Series Time
88060QTS CR8SMSTMSYC1 Synchronization Function License SnS(1 1
year)
NetEngine 8000 M Series Core&Aggregation
88060QUB CR8SM4CRAGC1 Scenario Port Function License SnS(per 20
10GE,1year)
NetEngine 8000 M Series L3VPN Port
88060QUG CR8SM4L3VPC1 20
Function License SnS(per 10GE,1year)
1.5 Installation Material
1.5.1 Optical Patch Cord
S4024281 F000FSL00 Optical Patch Cord(PCS) 10
1.5.2 Pow er Cable
Pow er Cable,450V/750V,H07Z-K
25030710 P-10mm^2-Blue-LSZH UL3386,10mm^2,Blue,80A,LSZH 20
Cable,VDE,UL (Unit:meter)
Pow er Cable,450V/750V,H07Z-K
P-10mm^2-Black-
25030711 UL3386,10mm^2,Black,80A,LSZH 20
LSZH
Cable,VDE,UL (Unit:meter)
Pow er Cable,450V/750V,H07Z-K
25030698 CPGN01001 UL3386,10mm^2,Yellow /Green,80A,LSZH 10
Cable,VDE,UL (Unit:meter)
CONTRACTOR OWNER
CONTRACTOR OWNER
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 8
2.6 Ring Diagram
CONTRACTOR OWNER
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 Saudi Mobily Rise Project \HUAWEI\Page 9
2.2 Splice Plan
CONTRACTOR OWNER
CONTRACTOR OWNER
NE8000-M8
7 8 PIU
5 6 10-port 100/1000M PIC
9 IPU
FAN
10 IPU
3 4 10-Port 10GE/GE PIC
1 2 10-Port 10GE/GE PIC PIU
CONTRACTOR OWNER
2.5.1 2375-8000 M8
CONTRACTOR OWNER
CONTRACTOR OWNER
FROM TO CABLE
Rectifier
Model Power Type CB No. Rating Equipment Power Supply Module Cable Size (mm2) Type
EMERSON -48V Rectifier CB # 08 32A W2375.HM8I.01 PEM A 10 Blue&Red(-48V)
EMERSON -48V Rectifier CB # 09 32A W2375.HM8I.01 PEM B 10 Blue&Red(-48V)
CONTRACTOR OWNER
CONTRACTOR OWNER
CONTRACTOR OWNER
CONTRACTOR OWNER
CONTRACTOR OWNER
2U HUAWEI CX600
2U FPP
2U HUAWEI CX600
2U FPP
CONTRACTOR OWNER
2U ODF
Huawei Technologies Co.,
Ltd TITL Equipm
P.O.BOX: 295320 RIYADH 11351 E ent
TEL: 00966 1 2011505 FAX: 00966 1 NE800
Saudi Mobily Rise Project 18-June- Saudi Mobily Rise Project 0M8
1.0 Azhar Project Code: 56A07GZ
2011255
SED 2020
Saudi Mobily Rise Project \
PREPARED
VER REVISION DESCRIPTION DATE PO NO. 61073-0
BY HUAWEI\Page 20
5.1 Approved Floor-plan
CONTRACTOR OWNER
2375
Huawei Technologies Co., Ltd Equipment
P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 21
5.2 Location Information
CONTRACTOR OWNER
2375
Huawei Technologies Co., Ltd Equipment
P.O.BOX: 295320 RIYADH 11351
TITLE
TEL: 00966 1 2011505 FAX: 00966 1 2011255 NE8000M
Saudi Mobily Rise Project 8
1.0 Saudi Mobily Rise Project SED 18-June-2020 Azhar Project Code: 56A07GZ
Saudi Mobily Rise Project \HUAWEI\Page
VER REVISION DESCRIPTION DATE PREPARED BY PO NO. 61073-0 22
Etihad Etisalat Company
Hardware Relocation Form
PROJECT EQUIPMENTS
The Project Team representatives formally perform Hardware Relocation on operational routers as the following:
Optical Transceiver
3
(SFP+,1310nm,10Gb/s,-8.2~0.5dBm,-
W2399-ICSG-HU01
0/4/5
W2375-ICSG-HU01 0/2/7 EC195200090348
12.6dBm,LC,SM,10km)
The undersigned Project team representative(s) formally performing Hardware Relocation, and the period between dismantling and
installing will be under project responsibility in case of card damage (misuse, stolen, broken)
Project team Representative(s)
Name Name
Position Position
Signature Signature
Date Date
Name Name
Position Position
Signature Signature
Date Date