Professional Documents
Culture Documents
Owner’s Engineer
Contractor
Sub-Supplier
Project
MRT- DS00-P0ZEN-840508
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
RECORD OF REVISION
Rev.2 2 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
CONTENTS
CONTENTS........................................................................................................................................... 3
FIGURES ............................................................................................................................................... 5
TABLES ................................................................................................................................................. 6
Rev.2 3 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 4 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
FIGURES
Rev.2 5 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
TABLES
Rev.2 6 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
SECTION I
INTRODUCTION
1.1 INTRODUCTION
Medium Voltage Switchgear are the point in the power network where transmission lines and
distribution feeders are connected through MV circuit breaker or MV switches via busbars and
transformers. This allows for the control of power flows in the network and general switching
operations for maintenance purposes.
Test and commissioning personnel should have a good understanding of the equipment involved
and the modes of operation of the system. Safety of personnel and plant during commissioning is
also vital; this is best addressed by good planning and procedural and safety documentation.
Before a MV switchgear may be tested, this involves satisfactory Factory Acceptance Test (FAT)
of all various switchyard equipment should be compared. In cases of MV Switchgear test &
commissioning work will also include verification of correct interfacing between new test &
Factory Acceptance Test.
1.2 OBJECTIVE
The site testing & commissioning of a distribution plant are the final activities to confirm that the
plant operates correctly and fulfils specified requirements. Normally, the equipment is already
factory tested and it is the duty and responsibility of the commissioning engineers to make sure
that the equipment is assembled / installed correctly. The main objectives are:
Specified equipment has been correctly installed as per specification and design.
Equipment operates correctly and has not been damage during transportation or installation
process.
That the required operations / functions are obtained with chosen design.
Obtain a set of as-built drawings and test records as reference for future modifications and
periodic maintenance.
In order to be able to perform the test & commissioning work, this procedure was made to define
the process and control of the quality system, safety and technical services by giving a
fundamental procedure testing & commissioning MV Switchgear. This procedure applied to all
technical personnel and managed by quality management systems as outlined in the document
master list.
Rev.2 7 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
- Motor Analysis
- Sync Time (Open & Close)
- Sequence / Cycle Time
- Minimum Pick Up
b. Current Transformer
- CT Ratio, Polarity, and Burden
- Knee point (Magnitization Curve)
- Winding Resistance
- Insulation Resistance
- Primary Injection
c. Voltage Transformer
- VT Ratio, Polarity, and Burden
- Winding Resistance
- Insulation Resistance
- Primary Injection
d. Bus Bar
- Insulation Resistance
- Contact Resistance
- Hi-pot Test (HV Test)
e. MV Power Cables
- Continuity Test
- Insulation Resistance
- Hi-pot Test (HV Test)
f. Earthing Switch
- Insulation Resistance (Include on Proces of Busbar Insulation Resistance Test)
- Function Test
g. Relay
- Measurement Test
- Pick up and Drop up Test
- Characteristic Test
- Tripping Time Test
h. Panel Metering
- Measurement Test (current & Voltage test)
i. Surge Arrester
- Insulation Resistance Test (If Any)
j. Indication Lamp
- Function Test
k. Interlocking System
- Function Test
Rev.2 8 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
1.4 REFERRENCE
ANSI/NETA ATS-2017, Standard for Acceptance Testing Specifications for Electrical Power
Equipment and Systems
No. Doc. MRT-DD00-P0BAT-155124 – First FAT Report Block 2 & common
No. Doc. MRT-DD00-P0BAT-155125 – Second FAT Report Block 3 and 4
No. Doc. MRT-YF01-P0BBA-150106 – Logic Diagram MV Switchgear
Keputusan Direksi PT PLN (PERSERO) Nomor :0520-2.K/DIR/2014
IEC 60694 -2002, Common specifications for high voltage switchgear and control gear
standards
PM/EC/MV SWGR/01 Rev.0, ABB Erecting, Testing and Commissioning Protocol for MV
SWITCHGEAR
IEC 255-5, Insulation Tests for Electrical Relays
IEC 255-6, Measuring Relay with More than one input energizing quantity
IEC 255-7, Test and Measurement Procedures for Electromechanical All or nothing relays
CPC 100, Instruction Manual
CTAnalyzer, Instruction Manual
ABB Manufacture, Manual Commissioning Procedure
CIBANO 500, Instruction Manual
Fluke 1555, Instruction Manual
CMC 356, Instruction Manual
Rev.2 9 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
SECTION II
SAFETY PRECAUTION
Rev.2 10 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
SECTION III
WORK PREPARATION & EXECUTION
3.2.1 PREPARATION
Prior execution of testing and Commissioning MV Switchgear, all preliminary condition shall be
fulfilled.
Below is the preliminary condition that required to prepare before Testing and Commissioning
of MV Switchgear:
1. All MV Switchgear Panel shall be installed correctly.
2. It is recommended to all auxiliary Power has been tested. (Auxiliary DC Power, either 110
VDC, 240VDC, or etc.)
3. All other simultaneous job that not related with this testing and commissioning shall be
communicated to leader team of commissioning.
4. Install adequate lighting.
5. Barricade the area of work.
6. All main power shall be isolated, and conduct LOTO
Supply Power
Supply power (AC 220V, 16 Amp) for Testing and commissioning tools will be provided by
other party or alternatively will provided onsite by Portable Genset 3 KVA. This power supply
will be feed testing tools such as Secondary testing tools, primary testing tools, and Hi-Pot testing
tools.
Rev.2 11 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
D- D- D- D- D- D- D- D- D- D- D-
No MV Switchgear ID D-1 D-2 D-3 D-4 D-5 D-6 D-7 D-8 D-9 10 11 12 13 14 15 16 17 18 19 20
1 24BBA01
2 34BBC01
3 34BBC02
D- D- D- D- D- D- D- D- D- D- D- D- D- D- D- D- D- D- D- D-
No MV Switchgear ID
21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
4 34BBA01
5 44BBA01
Remark:
Total Time Required per MV Switchgear
Rev.2 12 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Table 3 Personnel
Commissioning Coordinator:
A Commissioning Coordinator is responsible to organize all works related to testing &
commissioning and to implement the “Site inspection and test plan for testing and
commissioning”.
Testing & Commissioning Engineer:
A Testing & commissioning engineer is responsible for the testing & commission of equipment
and to ensure that the correct procedures are followed. Upon completion of each test, he will sign
the appropriate test record and request any witnessing representative to do the same.
Rev.2 13 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
3.4 TOOLS
Rev.2 14 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Measurement Range
7 High Voltage Measurement of Kyoritsu 3125 –
from 500 Volt to
Insulation insulation resistance Japan
5000 Volt
Resistance Transformer, Cable,
Insulation
Bus-Bar
Resistance Range
from up to 1000GΩ
Capable to Measure
IR, PI, DAR
Rev.2 15 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 16 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 17 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
ITEM
TOOLS DESCRIPTION
NO
1 Torch light
2 Emergency Light
3 Flood lights fittings
4 Extension Cable roll
Rev.2 18 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
SECTION IV
TESTING & COMMISSIONING PROCEDURE & METHODOLOGY
B. References
ANSI/NETA ATS 2017, Acceptance Testing Specifications for Electrical Power
Distribution Equipment and Systems
PM/EC/MV SWGR/01 Rev.0, ABB Erecting, Testing and Commissioning Protocol for
MV SWITCHGEAR
C. Standard Criteria
Suitability between actual condition and design/ drawing and standard
There are no damage or difference in condition visually.
Rev.2 19 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 20 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
C. Standard Criteria
Voltage Supply Panel
o Refer to IEC 60439-1 – 2004 - LV switchgear and controlgear assemblies. Actual voltage
within standard tolerance (Un±10%)
o And below is the report of FAT Document (No. Doc. MRT-DD00-P0BAT-155124 – First
FAT Report Block 2 & common and No. Doc. MRT-DD00-P0BAT-155125 – Second
FAT Report Block 3 and 4).
Rev.2 21 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Criteria Measured
Test Point
[V] [V]
AC Supply VAC±10%
DC Supply VDC±10%
Rev.2 22 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
C. Standard Criteria
Insulation Resistance Test
Refer to ANSI/NETA ATS 2017, Acceptance Testing Specifications for Electrical Power
Distribution Equipment and Systems
Rev.2 23 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Criteria Measured
Test Point
[V] [V]
AC Supply Marked on Drawing
DC Supply Refer to Drawing Marked on Drawing
Control Circuit Marked on Drawing
3. Check insulation resistance with applied voltage of 1000VDC between terminal MV circuit
connected to another and earth using insulation tester.
Temp : °C
Criteria Insulation
DC voltage test
Phase [MΩ] Resistance
[VDC]
[MΩ]
AC Supply 1000 > 100
DC Supply 600 >25
Rev.2 24 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
C. Standard Criteria
Insulation resistance
o ANSI/NETA ATS 2017, Acceptance Testing Specifications for Electrical Power
Distribution Equipment and Systems
Rev.2 25 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Contact resistance
o IEC 60694 subsection 6.4 & 7.3
o The difference value with the previous measurement or typical equipment under
same condition is not more than 20%
Rev.2 26 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Timing contact
Refer to Keputusan Direksi PT PLN (PERSERO) Nomor :0520-2.K/DIR/2014.
Minimum Pickup
Refer to FAT test Result and Datasheet from ABB.
Motor Analysis
Refer to FAT test Result and Datasheet from ABB.
Rev.2 27 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Temp : °C
Criteria Insulation Resistance
CB Condition Phase
[µΩ] [µΩ]
Close condition Phase R-r
Data FAT ±20%
Phase S-s
Phase S-s
5. Compare the test result with the FAT or latest measured data, ensure the deviation still within
the standard/ criteria
Rev.2 28 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 29 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 30 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Description Volt
Closing coil
Trip Coil
Rev.2 31 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
C. Standard Criteria
Insulation resistance
o Refer to FAT test Result and Datasheet from ABB.
o ANSI/NETA ATS 2017, Acceptance Testing Specifications for Electrical Power
Distribution Equipment and Systems
Rev.2 32 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Ratio
o Refer to ANSI/NETA ATS - 2017, Acceptance Testing Specification for Electrical
Power Equipment
Polarity
o OK (The difference in the current angle of the primary and secondary CT is close to
0deg (<30deg)
Burden
o Measured Burden value ≤ CT burden rating.
Winding Resistance
o Refer to ANSI/NETA ATS 2017, The deviation for winding resistance per phase is
3% compare with the average of the three readings.
Knee Point
o Refer to FAT test Result and Datasheet from ABB.
Rev.2 33 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
D.5. Knee-point
1. Make sure connection between secondary CT and metering/ relay protection is separate.
2. Put AC volt injector and AC amp meter in the secondary CT.
3. Set limit value for voltage and current.
4. Start the test and record the graph.
5. Ensure the values read on the test equipment are in accordance with the CT rating/
specification or according to the FAT test result.
6. Repeat the test if the results are not match with CT rating to ensure the testing process is
correct.
Rev.2 34 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 35 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rating Measured
Feeder No
S/N Phase Core Burden Polarity Burden R. Winding Kneepoint IR Primer IR Secondary
(Description) Ratio Class Ratio
VA OK / Not OK VA mΩ A; V MΩ MΩ
1S1 - 1S2
L1 2S1 - 2S2
3S1 - 3S2
1S1 - 1S2
L2 2S1 - 2S2
3S1 - 3S2
1S1 - 1S2
L3 2S1 - 2S2
3S1 - 3S2
1S1 - 1S2
L1 2S1 - 2S2
3S1 - 3S2
1S1 - 1S2
L2 2S1 - 2S2
3S1 - 3S2
1S1 - 1S2
L3 2S1 - 2S2
3S1 - 3S2
1S1 - 1S2
L1 2S1 - 2S2
3S1 - 3S2
1S1 - 1S2
L2 2S1 - 2S2
3S1 - 3S2
1S1 - 1S2
L3 2S1 - 2S2
3S1 - 3S2
Rev.2 36 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
C. Standard Criteria
Insulation resistance
o Refer to FAT test Result and Datasheet from ABB.
o ANSI/NETA ATS 2017, Acceptance Testing Specifications for Electrical Power
Distribution Equipment and Systems
Rev.2 37 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Ratio
o Refer to ANSI/NETA ATS - 2017, Acceptance Testing Specification for Electrical
Power Equipment
Polarity
o OK (The difference in the current angle of the primary and secondary CT is close to
0deg (< 30deg)
Winding Resistance
o Refer to ANSI/NETA ATS 2017, The deviation for winding resistance per phase is
3% compare with the average of the three readings.
Rev.2 38 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 39 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 40 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rating Measured
Feeder No Ratio Burden Class Ratio Polarity Burden R.Winding IR HV-LV IR LV-GND
S/N Phase Core
(Description)
VA OK/ Not OK VA mΩ MΩ MΩ
a1-n1
L1
a2-n2
a1-n1
L2
a2-n2
a1-n1
L3
a2-n2
a1-n1
L1
a2-n2
a1-n1
L2
a2-n2
a1-n1
L3
a2-n2
a1-n1
L1
a2-n2
a1-n1
L2
a2-n2
a1-n1
L3
a2-n2
a1-n1
L1
a2-n2
a1-n1
L2
a2-n2
a1-n1
L3
a2-n2
Rev.2 41 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
4.3.5 BUSBAR
A. Objective
Aims to determine the condition, function and characteristics of Busbar installed in the panel
B. References
ANSI/NETA ATS 2017, Acceptance Testing Specifications for Electrical Power
Distribution Equipment and Systems
ABB Manufacture, Manual Commissioning Procedure
No. Doc. MRT-DD00-P0BAT-155124 – First FAT Report Block 2 & common
No. Doc. MRT-DD00-P0BAT-155125 – Second FAT Report Block 3 and 4
OMICRON CPC100, user manual
COMPANO, user manual
Fluke 1555, Instruction Manual
C. Standard Criteria
Insulation resistance
o Refer to No. Doc. MRT-DD00-P0BAT-155124 – First FAT Report Block 2 &
common and No. Doc. MRT-DD00-P0BAT-155125 – Second FAT Report Block 3
and 4.
o Insulation resistance > 1000Mohm with applied voltage test 5000VDC
o But also can refer to ANSI/NETA ATS 2017, Acceptance Testing Specifications for
Electrical Power Distribution Equipment and Systems.
Rev.2 42 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Contact Resistance
o Refer to FAT test Result and
Temp: °C
Rev.2 43 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Temp : °C
Criteria Insulation Resistance
Phase
[MΩ] [MΩ]
R-STGround > 500 for 2500
S-RTGround VDC /1000 for
T-RSGround 5000 VDC
Rev.2 44 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Temp : °C
Voltage Current
Phase Criteria Test Leakage Test Result
[kV] [mA]
R-STGround No disruptive
S-RTGround discharge during the
T-RSGround testing
Rev.2 45 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
B. References
o Standard IEC 255-5 : Insulation Tests for Electrical Relays
o Standard IEC 255-6 : Measuring Relay with More than one input energizing quantity
o Standard IEC 255-7 : Test and Measurement Procedures for Electromechanical All or nothing
relays
C. Standard Criteria
As per design and setting. Both pick up and time test.
Rev.2 46 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
10. after the record voltage reading is complete. Keep doing 1.00*Un voltage injection with current
injection.
o Phase R : 0.10*In 0deg
o Phase S : 0.15*In -120deg
o Phase T : 0.20*In 120deg
11. Ensure the current reading on the metering matches the desired target, check the parameters and
wiring if the parameter readings do not match and repeat the test for data verification.
12. If the current metering is match, set current injector in similar current (0.25*In)
o Phase R : 0.25*In 0deg
o Phase S : 0.25*In -120deg
o Phase T : 0.25*In 120deg
13. Record the current and power reading in metering.
14. Repeat step # 12 - #13 for current injection 0.50*In, 0.75*In and 1.00*In
Rev.2 47 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
a. Current Relay
The following is a relay protection function based on the parameters of the current level:
o Time Over Current (51),
o Instantaneous Over current (50/76),
o Voltage Controlled Overcurrent (27C),
o Negative Sequence (46),
o Overcurrent with Voltage Restraint (27R),
o Thermal Overcurrent (49),
o Differential Relay (87),
o Mechanical Jam (only for motor)
Testing Procedure:
1. Check the protection settings to be tested, make sure the parameter settings, logic and
input/ output relay have been set according to the approved design.
2. Record the active protection function and its parameter settings (set point, curve, and
time setting)
3. Ensure sure the current metering test has been carried out and produced with the
appropriate results.
4. Identify the current input terminal and relay output (as feedback) on the relay that will
be tested.
5. Install the connection between the Relay Tester and the relay that will be tested for
current connections, and the TRIP output of the Relay. Ensure the connection is in
accordance with the drawing type relay used.
6. Change the "output current" until the relay starts moving (see the indication light on the
test equipment). Record the magnitude of the current as the value obtained “as found”
from the Pickup.
7. For "instantaneous relays", the magnitude of the current required for relay testing is
very high. Therefore, we need a very high current source too. Meanwhile, to get a high
current source that can be generated from parallel connections from two or three current
sources (test equipment). And at least the test equipment is equipped with a high current
source. The "Thermal Over Current" relay also has an instantaneous unit. Change the
Rev.2 48 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
output current "output current" step by step and record the value. Adjust the
"Adjustment screw" if deviations from the standard are found.
8. For differential relays, do current injection on both phase and neutral sides or on one
side of the relay if it is for Feeder Protection / Line (differential protection functions
only exist in Generators and Lines). Differentiate the 1800's angle on both sides (to see
the Relay protection normal conditions - the relay reads differential current 0 under
normal conditions), then change the current value or angle (select one) to pick up the
relay.
9. For Unbalance current protection relays, do current injection in each phase (R, S, T)
with a normal angle of 120 difference, then change the current value in one of the
phases, until the relay indicates Pick up. If you use a Digital relay, you can see % of the
actual unbalance value.
10. Match the "as found" value with the standard value. Adjust the controller spring if there
is a value that does not match the default value. Repeat the test until you get the
specified value.
11. Timing Test is done to get the state of the value of the time characteristics toward the
characteristics of the relay settings.
12. Perform current injection according to the form for each protection function, do it with
several variations of the current (example: 1.2 x I set, 1.5 x Iset, 2 x Iset, 4 x I set), this
is useful for checking the TRIP time curve in the protection relay.
13. Record all of the results as values that can be "as found" and compare them to a standard
curve. Adjust the parameters if the value is found not in accordance with the standard
curve. Repeat the test until we get a value that is close to and record as the desired value
"as left".
b. Voltage Relay
The following is a relay protection function based on the parameters of the voltage level:
o Under Voltage Relay (27)
o Over Voltage Relay (59)
o Reverse Phase Voltage Relay
o Negative Sequence Voltage Relay
Testing Procedure:
1. Check the protection settings to be tested, make sure the parameter settings, logic and
input/ output relay have been set according to the approved design.
2. Record the active protection function and its parameter settings (set point, curve, and
time setting)
3. Ensure that the voltage metering test has been carried out and produced with the
appropriate results.
4. Identify the input voltage terminal and output relay (as feedback) on the relay that will
be tested.
5. Prepare test equipment, power connections and connect between other devices if
needed.
Rev.2 49 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
6. Install the connection between the test equipment with the relay to be tested. Ensure the
connection is in accordance with the terminal functions on the relay and the equipment.
7. Test equipment in the "output voltage" position is connected to the induction coil
terminal on the relay.
8. If two connections between the relay and the test equipment need two voltage sources,
set the phase angle between the two voltage sources.
9. Testing "Pick up", change the "voltage output" until the relay starts moving (see the
indicator light on the test equipment).
10. Record the magnitude of the voltage as the value obtained "as found" from the Pickup.
11. Match the value of "as found" with the setting value. Adjust relay if there are values
that do not match the setting values. Repeat the test until you get the specified setting
value and record it as "as left".
12. "Drop out" testing. Set the output voltage slightly below the "high voltage" indicator
(120 V or see the data table).
13. Decrease the "output voltage" slowly until the "indicator light" lights up. Record the
magnitude voltage on the display as the "as found” value.
14. If there is a deviation in values or results against the standard, adjust the relay according
to the settings. Repeat the test until you get the appropriate value and record it as the
"as left" value.
15. Timing Test is done to get the state of the value of the time characteristics toward the
characteristics of the relay settings.
16. Record all results as values that can be "as found". Adjust the parameters if the value is
found not in accordance with the settings. Repeat the test until we get a value that is
close to the setting and record it as the desired value "as left".
c. Power Relay
The following is a relay protection function based on the parameters of the power level:
o Overload Relay
o Reverse Power
Testing Procedure:
1. Check the protection settings to be tested, make sure the parameter settings, logic and
input/ output relay have been set according to the approved design.
2. Record the active protection function and its parameter settings (set point, curve, and
time setting)
3. Ensure that current and voltage metering tests have been carried out and the results are
suitable.
4. Identify the input terminals of the current and voltage and the relay output (as feedback)
on the relay that will be tested.
5. Prepare all test equipment. Check the power source and output from the devices, make
sure that all devices and sources are off.
Rev.2 50 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
6. Install the connection between the test equipment with the relay that will be tested.
Make sure the connection is in accordance with the terminal functions on the relay and
the device. Input power (energize) if all connections have been installed correctly.
7. Test equipment in the "voltage and current output" position is connected to the relay
terminal.
8. Change the "power" until the relay starts moving (see the indicator light on the test
equipment). Record magnitude of frequency as the value obtained "as found" from the
Pickup.
9. Match the "as found" value with the setting value. Adjust relay if there are values that
do not match the standard values. Repeat the test until you get the specified value and
record it as "as left".
10. Record the magnitude of power as the value obtained "as found" from the Pickup.
11. "Drop out" testing. Set the power output slightly below the "power" indicator (100%
load or see data table).
12. Lower the "Power" slowly until the "indication light" lights up. Record the magnitude
power on the display as the "as found” value.
13. If there is a deviation in the value or results of the settings, adjust the relay until the
values match the settings. Repeat the test until you get the desired value and record it
as an "as left" value.
d. Frequency Relay
The following is a relay protection function based on the parameters of the frequency level:
o Over Frequency
o Under Frequency
Testing Procedure:
1. Check the protection settings to be tested, make sure the parameter settings, logic and
input/ output relay have been set according to the approved design.
2. Record the active protection function and its parameter settings (set point, curve, and
time setting)
3. Ensure that current and voltage metering tests have been carried out and the results are
suitable.
4. Identify the input terminals of the current and voltage and the relay output (as feedback)
on the relay that will be tested.
5. Prepare all test equipment. Check the power source and output from the devices, make
sure that all devices and sources are off.
6. Install the connection between the test equipment with the relay that will be tested.
Make sure the connection is in accordance with the terminal functions on the relay and
the device. Input power (energize) if all connections have been installed correctly.
7. Test equipment in the "voltage" position is connected to the induction coil terminal on
the relay.
Rev.2 51 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
8. Change the "output frequency" until the relay starts moving (see the indicator light on
the test equipment). Record magnitude of frequency as the value obtained "as found"
from the Pickup.
9. Match the "as found" value with the setting value. Adjust relay if there are values that
do not match the standard values. Repeat the test until you get the specified value and
record it as "as left".
10. Record the magnitude of power as the value obtained "as found" from the Pickup.
11. "Drop out" testing. Set the frequency output a little below the "Frequency" indicator (50
Hz or see data table).
12. Lower the "Frequency" slowly until the "indication light" lights up. Record the
magnitude frequency on the display as the "as found” value.
13. If there is a deviation in the value or results of the settings, adjust the relay until the
values match the settings. Repeat the test until you get the desired value and record it
as an "as left" value.
Rev.2 52 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Expected
Description ANSI Code Curve Pickup TMS Value Injection
Result
Pickup Drop Off Trip
Rev.2 53 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
C. Standard Criteria
Insulation resistance
o ANSI/NETA ATS 2017, Acceptance Testing Specifications for Electrical Power
Distribution Equipment and Systems
Rev.2 54 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Continuity
Phase Check
[Ok/ Not Ok]
Phase R -Phase R
Phase S -Phase S
Phase T -Phase T
Temp : °C
Criteria Insulation Resistance
Phase
[MΩ] [MΩ]
R-STGround > 500 for 2500
S-RTGround VDC or 1500 for
T-RSGround 5000 VDC
Rev.2 55 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Temp : °C
Voltage Current
Phase Criteria Test Leakage Test Result
[kV] [mA]
R-STGround No disruptive
S-RTGround discharge during the
testing
T-RSGround
Rev.2 56 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
C. Standard Criteria
Suitability between actual operation function with the standards / philosophy / design that has
been approved
D. Check/ Inspection Details
Contact Resistance Test
( ) Close the Earthing Switch
( ) Inspect bolted electrical connections for High resistance using low-resistance ohmmeter.
( ) Ensure the contact resistance value is under 100 µΩ
( ) Check the continuity between ES to grounding bar.
Rev.2 57 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
B. References
ANSI/NETA 2007, Acceptance Testing Specifications for Electrical Power Distribution
Equipment and Systems
C. Standard Criteria
Refer to ANSI/NETA ATS 2017, Acceptance Testing Specifications for Electrical Power
Distribution Equipment and Systems.
Rev.2 58 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Temp : °C
Criteria Insulation Resistance
Phase
[MΩ] [MΩ]
R-STGround
> 100
S-RTGround
T-RSGround
Rev.2 59 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
C. Standard Criteria
Suitability between actual operation function with the standards / philosophy / design that has
been approved
Rev.2 60 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
( ) Check the function of open & close from the front panel selector/ pushbutton – Local & CB
in the services position (rack in)
( ) Put local/ remote selector in the local position – if available
( ) Put CB in the test position (rack out)
( ) Put selector/ pushbutton in the position close
( ) Monitor indicator status CB, and make sure CB status is closing (CB close
indicator light on)
( ) Put selector/ pushbutton in the position trip
( ) Monitor indicator status CB, and make sure CB status is opening (CB trip
indicator light off)
( ) Check the function of open & close from the front panel selector/ pushbutton – Remote &
CB in the services position (rack in)
( ) Put local/ remote selector in the remote position – if available
( ) Give a close CB command from remote device or by force command on the related
terminal
( ) Monitor indicator status CB, and make sure CB status is closing (CB close
indicator light on)
( ) Put selector in the position trip/ press trip button
( ) Monitor indicator status CB, and make sure CB status is opening (CB trip
indicator light off)
Rev.2 61 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
( ) Check the function of open & close CB from local/ remote command/ order below the
matrix:
RESULT
BUS COUPLER
TIE FEEDER
TIE FEEDER
TIE FEEDER
BLOCK-3/4
INCOMER-1
INCOMER-2
OUTGOING
BLOCK-3/4
MV SWGR
MV SWGR
MV SWGR
BLOCK-2
BLOCK-3
BLOCK-2
INCOMER
INCOMER
SUPPLY
FEEDER
FEEDER
MOTOR
TRAFO
FUNCTION TARGET
(52F)
(52A)
(52C)
(52D)
(52B)
(52C)
(52D)
(52D)
WET
CLOSE CB
LOCAL ORDER CB Close Push Button Close CB
REMOTE ORDER Close Order from TNC switch Close CB
Close order from DCS Close CB
Close order from HSBT Close CB
OPEN CB
LOCAL ORDER CB Open Push Button Open CB
REMOTE ORDER Open Order from TNC switch Open CB
Open order from DCS Open CB
Open order from HSBT Open CB
Intertrip Signal Open CB
Protection/ Lockout Relay Open CB
Rev.2 62 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
( ) Perform interlock function test follow the matrix in the table below:
4 x x x x 0 Can't close
5 Close Interlock 1 1 1 1 1 Close
1 x 0 x x x x Can't close
2 Open Interlock x x 0 x x x Can't close
3 x x x 0 x x Can't close
4 Close Interlock 1 1 1 1 0 1 Close
1 x 0 x x x x Can't close
2 Open Interlock x x x 0 x x Can't close
3 x x x x 0 x Can't close
4 Close Interlock 1 1 1 1 1 0 Close
Rev.2 63 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Interlock SWGR Incomer-1 52D
1 x 0 x x Can't close
Open Interlock
2 x x 0 x Can't close
1 x 0 x x x Can't close
Open Interlock
2 x x 0 x x Can't close
1 x 0 x x Can't close
Open Interlock
2 x x 0 x Can't close
Dry Transformer
Transformer
Anti Pumping
TCS feeder Downstream
relay Enclosure door
(95) Lockout relay breaker
(94)
No Action description (86) Target Test Result
1. Healthy 1. Reset 1. Not Operated 1. Closen 1. Close
0. Unhealthy 0. Operated 0. Operated 0. Open 0. Open
x. don't care x. don't care x. don't care x. don't care x. don't care
1 x 0 x x x Can't close
Open Interlock
2 x x 0 x x Can't close
Outgoing Feeder
Transformer
Anti Pumping
TCS feeder Downstream
relay
(95) Lockout relay breaker
(94)
No Action description (86) Target Test Result
1. Healthy 1. Reset 1. Not Operated 1. Closen
0. Unhealthy 0. Operated 0. Operated 0. Open
x. don't care x. don't care x. don't care x. don't care
1 x 0 x x Can't close
Open Interlock
2 x x 0 x Can't close
Motor Feeder
Transformer
Anti Pumping
TCS feeder
relay
(95) Lockout relay
(94)
No Action description (86) Target Test Result
1. Healthy 1. Reset 1. Not Operated
0. Unhealthy 0. Operated 0. Operated
x. don't care x. don't care x. don't care
1 x 0 x Can't close
Open Interlock
2 x x 0 Can't close
Rev.2 64 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
CB test/services
Close Interlock
Antipump not
DCS selector
switch Auto
CB spring
CB Close
Operated
condition
Charged
HSBT IN
Position
position
HSBT
HSBT
DCS
Circuit Breaker Target T est Result
0 1 1 1 1 1 x 1 1 0 Close CB
Block-2 Incomer (52A)
1 x x x x x x x x 1 Open CB
0 1 1 1 1 1 1 1 1 0 Close CB
Block-2 Tie Feeder (52C)
1 x x x x x x x x 1 Open CB
N/A N/A
Block-3 Tie Feeder (52D)
N/A N/A
0 1 1 1 1 1 x 1 1 0 Close CB
Block 3/4 Incomer (52B)
1 x x x x x x x x 1 Open CB
N/A N/A
Block 3/4 T ie Feeder (52C)
N/A N/A
N/A N/A
Incomer-1 (52D)
N/A N/A
0 1 1 1 1 1 x 1 1 0 Close CB
Buscoupler (52E)
1 x x x x x x x x 1 Open CB
0 1 1 1 1 1 x 1 1 0 Close CB
Incomer-2 (52F)
1 x x x x x x x x 1 Open CB
Rev.2 65 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
B. Energize Busbar
( ) Make sure power receiving success without finding
( ) Check condition in feeder incoming
( ) There are no indication trip or relay working
( ) Make sure lockout relay on the reset condition, reset lockout if there is lockout relay
operate
( ) Make sure close interlock is active (all permissive for interlock are fulfilled)
( ) Rack in CB in the feeder incoming MV switchgear
( ) Make sure CB motorized is charged
( ) Make sure anti pumping protection not operated
( ) Close CB in the feeder incoming MV switchgear
( ) Voltage reding in the bus / outgoing feeder with correct value
( ) Phase sequence in bus / outgoing feeder are correct
( ) Hold and monitor the test for 1* 24 Hours
Rev.2 66 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
C. Energize Load
( ) Make sure power receiving and energize busbar success without finding
( ) Determine the load will be energized
( ) Ensure the load has been tested and ready to energize
( ) Make sure CB downstream in the open condition
( ) There are no indication trip or relay working
( ) Make sure lockout relay on the reset condition, reset lockout if there is lockout relay
operate
( ) Make sure close interlock is active (all permissive for interlock are fulfilled)
( ) Open ES in the outgoing feeder to energize
( ) Rack in CB feeder outgoing MV switchgear
( ) Make sure CB motorized is charged
( ) Make sure anti pumping protection not operated
( ) Close CB feeder outgoing MV switchgear
( ) Capacitive phase indicator lights up
( ) Record parameter reading in the MV switchgear
( ) Especially for outgoing feeder to LV panel, to be recommended to hold the power in the
upstream CB incoming for 1*24hours before energize the busbar
Rev.2 67 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
SECTION V
FAT REPORT
Rev.2 68 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
SECTION VI
FORM TEST
Rev.2 69 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 70 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 71 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 72 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 73 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 74 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 75 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 76 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 77 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 78 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 79 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 80 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 81 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 82 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 83 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 84 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 85 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 86 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 87 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 88 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 89 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 90 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 91 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 92 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 93 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 94 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 95 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 96 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 97 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 98 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 99 of 100
[SITE COMMISSIONING PROCEDURE] MV SWITCHGEAR
COMMISSIONING PROCEDURE
MRT-DS00-P0ZEN-840508
Rev.2 100 of
100