PROGRAM FOR INSTALLATION OF 25KVA AND 80 KVA GENSETS

ID Task Task Name Duration Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20
1 PROGRAM FOR INSTALLATION OF 43 days PROGRAM FOR INSTALLATION OF 25KVA AND 80 KVA GENSETS
25KVA AND 80 KVA GENSETS

2 INSTALLATION OF A 25kVA DIESEL 41 days INSTALLATION OF A 25kVA DIESEL GENERATOR SET AT MINING INDUSTRY ARCHIVES I
GENERATOR SET AT MINING
INDUSTRY ARCHIVES IN NDOLA

3 Mobilisation 2 days Mobilisation

4 Construction of a Genset open shelter


14 days Construction of a Genset open shelter

5 Supply, Install and Connect Genset35 days Supply, Install and Connect Genset

6 Commissioning of Genset 2 days Commissioning of Genset

7 Demobilisation 2 days Demobilisation

8 INSTALLATION OF AN 80kVA 41 days INSTALLATION OF AN 80kVA SILENT DIESEL GENERATOR SET AT MAWE COMPLEX IN
SILENT DIESEL GENERATOR SET AT
MAWE COMPLEX IN KALULUSHI

9 Mobilisation 2 days Mobilisation

10 Construction of a Genset open shelter


14 days Construction of a Genset open shelter

11 Supply and install feeder pillar 7 days Supply and install feeder pillar

12 Supply, Install and Connect Genset35 days Supply, Install and Connect Genset

13 Commissioning of Genset 2 days Commissioning of Genset

14 Demobilisation 2 days Demobilisation

15 Finish Project 0 days 02/12

Task Inactive Milestone Start-only Critical Split

Split Inactive Summary Finish-only Progress

Project: Program - 25KVA an 80 Milestone Manual Task External Tasks Manual Progress
Date: Sun 13/10/19 Summary Duration-only External Milestone

Project Summary Manual Summary Rollup Deadline

Inactive Task Manual Summary Critical