Professional Documents
Culture Documents
ID Task Task Name Duration Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20
1 PROGRAM FOR INSTALLATION OF 43 days PROGRAM FOR INSTALLATION OF 25KVA AND 80 KVA GENSETS
25KVA AND 80 KVA GENSETS
2 INSTALLATION OF A 25kVA DIESEL 41 days INSTALLATION OF A 25kVA DIESEL GENERATOR SET AT MINING INDUSTRY ARCHIVES I
GENERATOR SET AT MINING
INDUSTRY ARCHIVES IN NDOLA
5 Supply, Install and Connect Genset35 days Supply, Install and Connect Genset
8 INSTALLATION OF AN 80kVA 41 days INSTALLATION OF AN 80kVA SILENT DIESEL GENERATOR SET AT MAWE COMPLEX IN
SILENT DIESEL GENERATOR SET AT
MAWE COMPLEX IN KALULUSHI
11 Supply and install feeder pillar 7 days Supply and install feeder pillar
12 Supply, Install and Connect Genset35 days Supply, Install and Connect Genset
Project: Program - 25KVA an 80 Milestone Manual Task External Tasks Manual Progress
Date: Sun 13/10/19 Summary Duration-only External Milestone
Page 1