CRONOGRAMA IMPERMEABILIZACION PIURA 04.12.23.

mpp
Id Modo Task Name Duración dom 26 nov
lun 27 novmar 28 nov
mié 29 novjue 30 novvie 1 dic sáb 2 dic dom 3 diclun 4 dic mar 5 dic mié 6 dic jue 7 dic
de 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0
1 AGENCIA BANCARIA BCP - PIURA 9 días 74%

2 INSTALACIÓN DE COBERTURA METALICA 7 días 80%

3 INSTALACION DE CANALETAS GALVANIZADAS 2 días 100%

4 IMPERMEABILIZACION CANALETAS 2 días 25%

5 FIN 0 días 5/12

Critical Progress Duration-only Summary Progress Inactive Milestone

Task Critical Summary Inactive Summary

Split Critical Split Manual Summary Deadline

Task Progress Baseline Project Summary Slippage

Manual Task Baseline Split External Tasks Baseline Summary

Start-only Baseline Milestone External Milestone

Finish-only Milestone Inactive Task

CONSULTORIA EXTERNA SODEXO PERU SAC

This document was created by an application that isn’t licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.

You might also like