ID Task Task Name Duration Start 2024

Mode 2023 2024 2025


Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
1 ASHIANA MALHAR 796 days 15 Feb '23
2 NIWAS PART 1 796 days 15 Feb '23
3 FOUNDATION 75 days 15 Feb '23
6 RCC SUPERSTRUCTURE313 days 04 May '23
23 BRICK WORK 258 days 08 Jul '23
40 INTERNAL PLASTER 255 days 12 Aug '23
57 EXTERNAL PLASTER 258 days 09 Oct '23
62 FABRICATION WORKS 325 days 23 Aug '23
66 PH WORKS 290 days 18 Sep '23
70 WATER PROOFING 261 days 09 Sep '23
74 SCAFFOLDING & 478 days 05 Jun '23
SAFTEY NET FIXING
77 DADO FIXING 197 days 19 Oct '23
92 GYP WORK / POP 210 days 10 Nov '23
107 FLOORING 225 days 10 Jan '24
123 INT ELECT WIRING + 210 days 10 Feb '24
D/SHUTTERS
138 LIFT WORK 150 days 11 Aug '24
142 EXTERNAL PAITING 147 days 22 Aug '24
145 INTERNAL PAINTING 210 days 28 Mar '24
1ST COAT
160 TILE GROUTING 180 days 13 May '24

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Xrbia Smartcity Warai M
Summary Manual Summary Rollup Critical
Date: 14 Mar '23
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 1
ID Task Task Name Duration Start 2024
Mode 2023 2024 2025
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
161 DOOR FITTINGS 180 days 27 Apr '24
162 ALUMINIUM WINDOWS 100 days 01 Sep '24
177 INTERNAL PAINTING 140 days 08 Oct '24
2ND COAT
192 CP & VITROUS FITTINGS138 days 18 Oct '24
207 FLAT CLEANING 90 days 17 Dec '24
208 QCC RELEASE 56 days 18 Mar '25
223 DEVELOPMENT 330 days 28 Mar '24
243 NIWAS PART 2 781 days 02 Mar '23

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Xrbia Smartcity Warai M
Summary Manual Summary Rollup Critical
Date: 14 Mar '23
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 2