ID Task Task Name Duration Start Finish Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Mode S O N D J F M A M J J A S O N D J F M A M J 1 Kagera Sugar Ltd. Kitengule - 600 TCH 547 days Sat 01-10-22 Sat 20-04-24 2 Power Generation 547 days Sat 01-10-22 Sat 20-04-24 3 Receipt of Purchase Order with 1st Advance 0 days Sat 01-10-22 Sat 01-10-22 01-10 4 Design - Layout Location freeze 10 days Sat 01-10-22 Tue 11-10-22 5 TA Set 18MW Back Pressure-1 No. Complete with 475 days Thu 13-10-22 Sat 17-02-24 Accessories,Insrtrumentation & Control 6 Design & Engineering 30 days Thu 13-10-22 Mon 14-11-22 7 Manufacturing 365 days Mon 14-11-22 Mon 27-11-23 8 Testing & Inspection 20 days Mon 27-11-23 Mon 18-12-23 9 Supply upto Project Site 60 days Mon 18-12-23 Sat 17-02-24 10 TA Set 32MW Pass Out-1No Complete with 535 days Thu 13-10-22 Sat 20-04-24 Accessories,Instrumentation & Control 11 Design & Engineering 30 days Thu 13-10-22 Mon 14-11-22 12 Manufacturing 425 days Mon 14-11-22 Mon 29-01-24 13 Testing & Inspection 20 days Mon 29-01-24 Sat 17-02-24 14 Supply upto Project Site 60 days Sat 17-02-24 Sat 20-04-24 15 Material Receipt At site 0 days Sat 20-04-24 Sat 20-04-24 20-04