MANPOWER SCHEDULE Project Month

Description Qty Duration 6/5/2020 7/5/2020 8/5/2020 9/5/2020 10/5/2020 11/5/2020 12/5/2020 1/5/2021 2/5/2021
Site Engineer 1 140 days 10 8 12 16 20 13 17 18 26
Construction Foreman 3 268 days 30 31 31 29 31 30 31 31 28
Skilled Workers 35 274 days 30 31 31 31 31 30 31 31 28
Laborer 25 274 days 30 31 31 31 31 30 31 31 28
Electrician 6 55 days 15 10 8 5 5 12
Steel Man 3 48 days 18 14 10 6
Welder 3 48 days 18 14 10 6
Master Plumber 9 65 days 10 15 10 8 5 5 12
Tinsmith 5 42 days 12 12 10 8
Driver 4 268 days 30 31 31 31 31 30 31 31 28
Leadman 4 80 days 25 20 20 15
Heavy equipment Operator 3 52 days 15 15 10 12
Total 101 170 167 176 195 176 197 189 180 174
EQUIPMENT SCHEDULE
Duration
Equipment Name Unit with Duration Start Finish
(in days)
Dozer 85 cu. m. per hour 6/5/2020 9/5/2020 92
Payloader 30 cu. m. per hour 6/5/2020 9/5/2020 92
Backhoe 15 cu. m. per hour 6/5/2020 10/15/2020 108
Jackhammer (common earth) 15.0 cu. m. per man-hour 7/15/2020 9/3/2020 50
Jackhammer (rock) 0.60 cu. m. per man-hour 7/17/2020 9/5/2020 51
Bar Cutter & Welding Machine 200 kg per hour 6/20/2020 1/15/2021 209
1 Bagger mixer 1.80 cu. m per hour 6/28/2020 1/10/2021 197
Concrete vibrator 3.00 cu. m per hour 7/10/2020 12/12/2021 155