You are on page 1of 4

ID Task Task Name Duration Start Finish 2024

Mode Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 ASHIANA MALHAR PH-2 717 days 01 Jun '2306 Jun '25
2 TOWER 8 660 days 01 Jun '2309 Apr '25
3 FOUNDATION 75 days 01 Jun '2314 Aug '23
6 RCC SUPERSTRUCTURE
250 days 16 Aug '2329 Apr '24
23 INTERNAL AND 192 days 22 Oct 07 May '24
EXTERNAL '23
38 BLOCK WORK 188 days 29 Oct '2310 May '24
55 INTERNAL PLASTER 168 days 30 Nov '2320 May '24
72 FABRICATION WORKS257 days 05 Dec '2323 Aug '24
76 PH WORKS 343 days 15 Nov '2330 Oct '24
80 WATER PROOFING 211 days 17 Dec '2319 Jul '24
84 SCAFFOLDING & 240 days 23 Sep 27 May '24
SAFTEY NET '23
86 DADO FIXING 168 days 25 Dec '2314 Jun '24
101 GYP WORK / POP 210 days 07 Jan '24 07 Aug '24
116 FLOORING 225 days 22 Feb '2409 Oct '24
132 INT ELECT WIRING 210 days 25 Mar 24 Oct '24
+ D/SHUTTERS '24
147 LIFT WORK 120 days 24 Sep '2425 Jan '25
151 EXTERNAL PAINTING204 days 30 Jun '2425 Jan '25
154 INTERNAL 198 days 16 Apr 03 Nov '24
PAINTING 1ST '24
169 TILE GROUTING 180 days 20 May '2420 Nov '24
170 DOOR FITTINGS 180 days 04 Jun '24 05 Dec '24
171 ALUMINIUM WINDOWS116 days 04 Aug '2402 Dec '24
186 INTERNAL 112 days 17 Aug 10 Dec '24
PAINTING 2ND '24

Task Inactive Milestone Start-only Critical Split

Split Inactive Summary Finish-only Progress

Milestone Manual Task External Tasks Manual Progress

Summary Duration-only External Milestone

Project Summary Manual Summary Rollup Deadline

Inactive Task Manual Summary Critical

Page 1
ID Task Task Name Duration Start Finish 2024
Mode Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
201 CP & VITROUS FITTINGS
112 days 25 Aug '2418 Dec '24
216 FLAT CLEANING 90 days 22 Oct '2422 Jan '25
217 QCC RELEASE 56 days 11 Feb '2509 Apr '25
232 DEVELOPMENT 216 days 15 Jul '24 23 Feb '25
246 TOWER 9 702 days 16 Jun '2306 Jun '25

Task Inactive Milestone Start-only Critical Split

Split Inactive Summary Finish-only Progress

Milestone Manual Task External Tasks Manual Progress

Summary Duration-only External Milestone

Project Summary Manual Summary Rollup Deadline

Inactive Task Manual Summary Critical

Page 2
2025 2026 2027
Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026 Qtr 3, 2026 Qtr 4, 2026 Qtr 1, 2027 Qtr 2, 2027 Qtr 3, 2027
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Milestone Start-only Critical Split

Split Inactive Summary Finish-only Progress

Milestone Manual Task External Tasks Manual Progress

Summary Duration-only External Milestone

Project Summary Manual Summary Rollup Deadline

Inactive Task Manual Summary Critical

Page 3
2025 2026 2027
Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026 Qtr 3, 2026 Qtr 4, 2026 Qtr 1, 2027 Qtr 2, 2027 Qtr 3, 2027
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Task Inactive Milestone Start-only Critical Split

Split Inactive Summary Finish-only Progress

Milestone Manual Task External Tasks Manual Progress

Summary Duration-only External Milestone

Project Summary Manual Summary Rollup Deadline

Inactive Task Manual Summary Critical

Page 4

You might also like