ID Task Name Duration

1st Quarter 2nd Quarter 3rd Quarter 4th Quarter


Feb Mar Apr May Jun Jul Aug Sep Oct No
1 Whistler Ski Resort Project ( Stage 1) 130 days

2 Material Ordering for chair lift 30 days


3 Material Ordering for rope tow 12 days
4 Lumber Ordering for day lodge, 9 days
generator hut and foundation
5 Electrical and plumbing materials 12 days
ordering
6 Ordering generators 12 days
7 Built road to site 6 days
8 Clearing day lodge 6 days
9 Clearing Generator House 3 days
10 Clearing chair lift 36 days
11 Clearing rope tow 6 days
12 Clearing main ski slopes 84 days
13 Construct foundation for day lodge 12 days

14 Construct main framework for day 18 days


lodge
15 Wire Electric 24 days
16 Installing Plumbing 30 days
17 Finish construction day lodge 36 days
18 Construct chair lift foundation 6 days
19 Install chair lift towers 67 days

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: Q5_project
Summary Manual Task Critical
Date: Sun 27-12-20
Project Summary Duration-only Critical Split
External Tasks Manual Summary Rollup Progress
External Milestone Manual Summary

Page 1
ID Task Name Duration
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Feb Mar Apr May Jun Jul Aug Sep Oct No
20 Construct permanent road to upper 24 days
tower
21 Installing electric motor for chair lift 24 days

22 Install chair lift cable 3 days


23 Install chairs 12 days
24 Build rope tower foundation 4 days
25 Installing rope tow towers 20 days
26 Installing electric motor for rope 24 days
tow
27 String rope tow cable 1 day
28 Clear parking Lot 18 days
29 Construct foundation for generator 6 days
house
30 Construct main framework for 12 days
generator house
31 Installing diesel generator 18 days
32 Finish construction for Generator 12 days
house

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: Q5_project
Summary Manual Task Critical
Date: Sun 27-12-20
Project Summary Duration-only Critical Split
External Tasks Manual Summary Rollup Progress
External Milestone Manual Summary

Page 2