MOBILISATION SCHEDULE FOR THE PROPOSED EARTH DAM IN CHIKUNI MONZE

ID Task Task Name Duration Day -1 Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12 Day 13 Day 14 Day 15 Day 16 Day 17 Day 18 Day 19 Day 20 Day 21 Day 22 Day 23
1 MOBILISATION SCHEDULE 14 days MOBILISATION SCHEDULE

2 PREMOBILISATION 6 days PREMOBILISATION

3 Site Possession, Project Guarantees, 6 days


Project Insurance

4 MOBILISATION OF EQUIPMENT 5 days MOBILISATION OF EQUIPMENT

5 Back hoe TLB, Front End Loader, Tippers, 5 days


Utility pickup, Roller Compactors, Water
bowser, Water pump, Dumpy leveletc.

6 MOBILISATION OF KEY PERSONNEL 4 days MOBILISATION OF KEY PERSONNEL

7 Project Manager, Site Engineer, General 4 days


Foreman, Bricklayer Foreman, Carpenter
Foreman, Plumbing Foreman

8 SITE ESTABLISHMENT 5 days SITE ESTABLISHMENT

9 Site Isolation, safety warning, 5 days


Accomodation of Traffic

10 ESTABLISHMENT OF SITE OFFICE 4 days ESTABLISHMENT OF SITE OFFICE

11 Accomodation facilities, Power, Water 4 days


Connection, etc

12 RECRUITMENT 8 days RECRUITMENT

13 Recruitment of Skilled Workers and 7 days


General workers

14 Finish Mobilisation 0 days Finish Mobilisation

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Mobilisation Schedule
Milestone Inactive Summary Start-only Critical
Date: Tue 15/10/19
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

WOODLOCK LTD Page 1