Assignment no. 3
2. Time remaining until due date (working days) for each job:
Working days in July:
Time Remaining until Due Date = Working Day Due Date – Today’s Working Day Number (1)
6
4
18
13
22
Job Job Time Remaining Due Date (days) Critical Ratio Calculation
A --- --- ---
B --- --- ---
C 8.25 18 1.121212121
D 3.5 13 1.214285714
E 9.5 22 1.394736842
Job C is scheduled next.
Job Job Time Remaining Due Date (days) Critical Ratio Calculation
A --- --- ---
B --- --- ---
C --- --- ---
D 3.5 13 -1.142857143
E 9.5 22 0.526315789
Job D is scheduled next.
Job E is scheduled last.
CR Sequence: A-B-C-D-E
1. Calculations for the average flow time, average tardiness, and average number of jobs at the work center
for each rule:
Average job flow time = Total job flow time / Number of jobs= 16.5 days
Average job tardiness = Total job tardiness / Number of jobs = 4.1 days
Average job flow time = Total job flow time / Number of jobs = 14.25 days
Average job tardiness = Total job tardiness / Number of jobs = 3.35 days
Average job flow time = Total job flow time / Number of jobs = 14.8 days
Average job tardiness = Total job tardiness / Number of jobs = 2.65 days
Average job flow time = Total job flow time / Number of jobs = 16.5 days
Average job tardiness = Total job tardiness / Number of jobs = 4.1 days