Professional Documents
Culture Documents
LESSON 10
Project Planning –
Advanced Scheduling Technique Cont’.
PhD.Vu Tuan Anh
1
Probability of Finishing by a Target Date 1/2
a: optimistic time
b: persimistic time
m: most likely
te: expected time
Beta probability
distribution
a, b are parameters
m end-point (most
frequent value)
2
Probability of Finishing by a Target Date 2/2
Variance
Z score Probability
3
Example
4
What is a probability of completing the project within 140 days?
16%
5
Managing Risks in Projects
6
Risk: Definition
“When our world was created, nobody
remembered to include certainty”
Peter Bernstein (1996)
Risk ~ Uncertainty
8
Identifying Risks: Techniques
• Project Analogy
• Checklist (Risk sources; Risk level)
• WBS
• Process Flowchart
• Network diagram
• Cause and Effect diagram
• Delphi Technique
9
Identifying Risks: Cause – Effect Diagram
10
Risk Assessment: Risk likelihood
12
Risk Assessment: Risk Impact 2/2
15
Solution to Exercise in
Lecture 8
16
Task ID Description Duration Precedent
A Prepare office 12
B Procure equipment 8
C Design tests 5
D Install equipment 10 A and B
E Test system 10 C and D
F Train users 5 E
17
Project – Make Table
Start A B C F End
E 18
Solution to Exercise in
Lecture 9
19
Activity Precedent Normal Normal Cost Crash Duration Crash Cost Expedite Cost
Duration ($ Thounsand) ($ Thounsand) Slope ($/day)
A - 6 6 3 9 1
B A 9 9 5 12 0.75
C B 3 4.5 2 7 2.5
D B 5 10 2 16 2
E C,D 2 2 2 2
F C 4 6 1 10 1.3
G E,F 8 8 5 10 0.67
For each saving day, project would get a bonus of $500 from the
investor. Determine the minimum cost of this project.
4,1,1.3
3,2,2.5
C F
6,3,1 9,5,0.75 2,2 8,5,0.67
Start A B E G End
5,2,2
Critical Path: D
C F
6,3,1 9,5,0.75 2,2 8,5,0.67
Start A B E G End
5,2,2
Critical Path: D