Hi-Ho, Yo-Yo, Inc.

1. The job time for each job (a day is 8 hours):

Set-up Time Production


Job Time Job Time
A 2 hours 6 days (2/8) + 6 = 6.25 days
B 4 hours 2 days (4/8) + 2 = 2.5 days
C 2 hours 8 days (2/8) + 8 = 8.25 days
D 4 hours 3 days (4/8) + 3 = 3.5 days
E 4 hours 9 days (4/8) + 9 = 9.5 days

2. Time remaining until due date (working days) for each job:

Working days in July:

Time Remaining until Due Date = Working Day Due Date – Today’s Working Day Number (1)

Mon Tue Wed Thu Fri Sat


(7/1) 1
(7/5) 2 (7/6) 3 (7/7) 4 (7/8) 5 (7/9) 6
(7/11) 7 (7/12) 8 (7/13) 9 (7/14) 10 (7/15) 11 (7/16) 12
(7/18) 13 (7/19) 14 (7/20) 15 (7/21) 16 (7/22) 17 (7/23) 18
(7/25) 19 (7/26) 20 (7/27) 21 (7/28) 22 (7/29) 23

Working Days
Job Due Date Until Due Date
A 7/11 7–1=6
B 7/8 5–1=4
C 7/25 19 – 1 = 18
D 7/19 14 – 1 = 13
E 7/29 23 – 1 = 22

3. Job details:

Job Time
Date Order Remaining Working Days
Job Received (Days) Until Due Date
A 6/4 6.25 6
B 6/7 2.5 4
C 6/12 8.25 18
D 6/14 3.5 13
E 6/15 9.5 22

4. Sequence for different rules:

FCFS Sequence: A-B-C-D-E


SPT Sequence: B-D-A-C-E
EDD Sequence: B-A-D-C-E
CR Sequence: A-B-C-D-E
CR Calculations (round to 2 decimals):

𝑇𝑖𝑚𝑒 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑈𝑛𝑡𝑖𝑙 𝐷𝑢𝑒 𝐷𝑎𝑡𝑒


𝐶𝑅 =
𝑃𝑟𝑜𝑐𝑒𝑠𝑠𝑖𝑛𝑔 𝑇𝑖𝑚𝑒 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔

Job Time Due Date Critical Ratio


Job Remaining (days) Calculation
A 6.25 6 (6 – 0) / 6.25 = 0.96
B 2.5 4 (4 – 0) / 2.5 = 1.60
C 8.25 18 (18 – 0) / 8.25 = 2.18
D 3.5 13 (13 – 0) / 3.5 = 3.71
E 9.5 22 (22 – 0) / 9.5 = 2.32
Job A is scheduled first.

Job Time Due Date Critical Ratio


Job Remaining (days) Calculation
A --- --- ---
B 2.5 4 (4 – 6.25) / 2.5 = -0.90
C 8.25 18 (18 – 6.25) / 8.25 = 1.42
D 3.5 13 (13 – 6.25) / 3.5 = 1.93
E 9.5 22 (22 – 6.25) / 9.5 = 1.66
Job B is scheduled next.

Job Time Due Date Critical Ratio


Job Remaining (days) Calculation
A --- --- ---
B --- --- ---
C 8.25 18 (18 – 8.75) / 8.25 = 1.12
D 3.5 13 (13 – 8.75) / 3.5 = 1.21
E 9.5 22 (22 – 8.75) / 9.5 = 1.39
Job C is scheduled next.

Job Time Due Date Critical Ratio


Job Remaining (days) Calculation
A --- --- ---
B --- --- ---
C --- --- ---
D 3.5 13 (13 – 17) / 3.5 = -1.14
E 9.5 22 (22 – 17) / 9.5 = 0.53
Job D is scheduled next.
Job E is scheduled last.

CR Sequence: A-B-C-D-E

5. Calculations for the average flow time, average tardiness, and average number of jobs at the
work center for each rule:

FCFS: Job time Flow time Due date Days


Job (days) (days) (days) tardy
A 6.25 6.25 6 0.25
B 2.50 8.75 4 4.75
C 8.25 17.00 18 0.00
D 3.50 20.50 13 7.50
E 9.50 30.00 22 8.00
30.00 82.50 20.50

Average job flow time = Total job flow time / Number of jobs = 82.50 / 5 = 16.50 days.

Average job tardiness = Total job tardiness / Number of jobs = 20.50 / 5 = 4.10 days.

Average number of jobs = Total flow time / Makespan = 82.50 / 30.00 = 2.75 jobs.

SPT: Job time Flow time Due date Days


Job (days) (days) (days) tardy
B 2.50 2.50 4 0.00
D 3.50 6.00 13 0.00
A 6.25 12.25 6 6.25
C 8.25 20.50 18 2.50
E 9.50 30.00 22 8.00
30.00 71.25 16.75

Average job flow time = Total job flow time / Number of jobs = 71.25 / 5 = 14.25 days.

Average job tardiness = Total job tardiness / Number of jobs = 16.75 / 5 = 3.35 days.

Average number of jobs = Total flow time / Makespan = 71.25 / 30.00 = 2.38 jobs.
EDD: Job time Flow time Due date Days
Job (days) (days) (days) tardy
B 2.50 2.50 4 0.00
A 6.25 8.75 6 2.75
D 3.50 12.25 13 0.00
C 8.25 20.50 18 2.50
E 9.50 30.00 22 8.00
30.00 74.00 13.25

Average job flow time = Total job flow time / Number of jobs = 74.00 / 5 = 14.80 days.

Average job tardiness = Total job tardiness / Number of jobs = 13.25 / 5 = 2.65 days.

Average number of jobs = Total flow time / Makespan = 74.00 / 30.00 = 2.47 jobs.

CR: Job time Flow time Due date Days


Job (days) (days) (days) tardy
A 6.25 6.25 6 0.25
B 2.50 8.75 4 4.75
C 8.25 17.00 18 0.00
D 3.50 20.50 13 7.50
E 9.50 30.00 22 8.00
30.00 82.50 20.50

Average job flow time = Total job flow time / Number of jobs = 82.50 / 5 = 16.50 days.

Average job tardiness = Total job tardiness / Number of jobs = 20.50 / 5 = 4.10 days.

Average number of jobs = Total flow time / Makespan = 82.50 / 30.00 = 2.75 jobs.