2. Time remaining until due date (working days) for each job:
Time Remaining until Due Date = Working Day Due Date – Today’s Working Day Number (1)
Working Days
Job Due Date Until Due Date
A 7/11 7–1=6
B 7/8 5–1=4
C 7/25 19 – 1 = 18
D 7/19 14 – 1 = 13
E 7/29 23 – 1 = 22
3. Job details:
Job Time
Date Order Remaining Working Days
Job Received (Days) Until Due Date
A 6/4 6.25 6
B 6/7 2.5 4
C 6/12 8.25 18
D 6/14 3.5 13
E 6/15 9.5 22
CR Sequence: A-B-C-D-E
5. Calculations for the average flow time, average tardiness, and average number of jobs at the
work center for each rule:
Average job flow time = Total job flow time / Number of jobs = 82.50 / 5 = 16.50 days.
Average job tardiness = Total job tardiness / Number of jobs = 20.50 / 5 = 4.10 days.
Average number of jobs = Total flow time / Makespan = 82.50 / 30.00 = 2.75 jobs.
Average job flow time = Total job flow time / Number of jobs = 71.25 / 5 = 14.25 days.
Average job tardiness = Total job tardiness / Number of jobs = 16.75 / 5 = 3.35 days.
Average number of jobs = Total flow time / Makespan = 71.25 / 30.00 = 2.38 jobs.
EDD: Job time Flow time Due date Days
Job (days) (days) (days) tardy
B 2.50 2.50 4 0.00
A 6.25 8.75 6 2.75
D 3.50 12.25 13 0.00
C 8.25 20.50 18 2.50
E 9.50 30.00 22 8.00
30.00 74.00 13.25
Average job flow time = Total job flow time / Number of jobs = 74.00 / 5 = 14.80 days.
Average job tardiness = Total job tardiness / Number of jobs = 13.25 / 5 = 2.65 days.
Average number of jobs = Total flow time / Makespan = 74.00 / 30.00 = 2.47 jobs.
Average job flow time = Total job flow time / Number of jobs = 82.50 / 5 = 16.50 days.
Average job tardiness = Total job tardiness / Number of jobs = 20.50 / 5 = 4.10 days.
Average number of jobs = Total flow time / Makespan = 82.50 / 30.00 = 2.75 jobs.