ITEMS OF WORK

1. Mobilization. 3 days
2. Layout 1 day
3. Excavation 10 days
4. Backfilling 3 days
5. False Work/Form Works 116 days
6. Foundation 12 days
 Column Footing
7. Columns 15 days
8. Beams 15 days
9. Masonry Works 20 days
 Wall footing
 Walls
 Stairs and Ramps
10. Slab 15 days
 Ground Floor Slab
 2nd Floor Slab
11. Roofing 5 days
 Roof Slab
12. Electric Works 8 days
13. Plumbing Works 8 days
14. Plastering Works 15 days
15. Installation of Doors and Windows 5 days
16. Tile Works 8 days
17. Painting 10 days