You are on page 1of 4

WEEK 1 2 3 4 5

MONTH OCTOBER NOVEMBER

DAY 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
SCOPE Sl No. NAME OF WORK
Leveling with
1 Measurement
2 DAYS

2
SCOPE OF SES

Fixing Brackets 2 DAYS

Fixing I Beam & Guide


3 Rail
10 WORKING DAYS

Fixing Frame, Sill and


4 Header of Landing Door 7 WORKING DAYS
MARINUS
SCOPE OF

CIVIL WORK, POWER


5 CABLE LAYING ETC BY 7 WORKING DAYS by MARINUS
MARINUS

FIXING CABIN, MOTOR &


6 CONTROLLER

ROPING & SLOW SPEED


7 RUN
SCOPE OF SES

8 FIXING DOORS

WIRING, LEVELLING
9 LIMIT & DOOR
ADJUSTMENT

HIGH SPEED RUN, FINAL


10 INSPECTION, SERVICING
BEFORE HANDOVER

NOTE: # In Shaa Allah if everything is fine without any natural calamities, Strict Lockdown (May Allah SWT save us) and any unwanted issues arises, we will do the works step by s
# These are approximate timings. The elevators can be handed over after approximately 55 days (Including Fraidays). Our part is for 38 working days.
# Fraidays are Off days; Government holidays (if any) are Off days.
5 6 7 8

DECEMBER
28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

RKING DAYS by MARINUS

5 WORKING DAYS

3D

2D

5 WORKING DAYS

5 WORKING DAYS

we will do the works step by step according to this schedule


ng days.