Task Name Complet Duration Start Finish


LADO OESTE e 263.83 ### ###
Entrega de Ingenieria 0 days ### ###
Area 05 Pumps Room And Cooling Tower Basins part 1of2 38 ### ###
Area 06 Pumps Room And Cooling Tower Basins part 2of2 31 ### ###
Area 07 Water Treatment Plant Electric Cabin 27 ### ###
Area 8. Rack Between WTP Y RMB 15 ### ###
Area Cuarto de Compresores 33 ### ###
LADO ESTE ### ###
Entrega de Ingenieria 0 days ### ###
Area 02: Settling Basin 43 ### ###

Area 03: Sand Filters (with backwashing tank) and Dry Beds 47 ### ###

Area 04: Thickener 30 ### ###

AREA 5 Pumps Room And Cooling Tower Basins part 1of2 10 FUNDACIONES
EXCAVACION 3.3333 DIAS
ZAPATAS 15 DIAS
LOSA DE PISO 5 DIAS
CIERRES PERIMETRALES 10 DIAS
BASES DE EQUIPOS 5 DIAS
SUBTOTAL 38.333 DIAS

AREA 6 Pumps Room And Cooling Tower Basins part 2of2 8 FUNDACIONES
EXCAVACION 2.6667 DIAS
ZAPATAS 12 DIAS
LOSA DE PISO 4 DIAS
CIERRES PERIMETRALES 8 DIAS
BASES DE EQUIPOS 4 DIAS
SUBTOTAL 30.667 DIAS

AREA 7 Water Treatment Plant Electric Cabin 7 FUNDACIONES


EXCAVACION 2.3333 DIAS
ZAPATAS 10.5 DIAS
LOSA DE PISO 3.5 DIAS
CIERRES PERIMETRALES 7 DIAS
BASES DE EQUIPOS 3.5 DIAS
SUBTOTAL 26.833 DIAS

AREA 8 Rack Between WTP Y RMB


EXCAVACION 3 DIAS
ZAPATAS 10 DIAS
BASES DE EQUIPOS 2 DIAS
SUBTOTAL 15 DIAS

AREA CUARTO COMPRESORES


EXCAVACION 4 DIAS
ZAPATAS 14 DIAS
COLUMNAS CONCRETO 3 DIAS
LOSA DE PISO 5 DIAS
BASES DE EQUIPOS 7 DIAS
SUBTOTAL 33 DIAS

AREA 2 Settling Basin


EXCAVACION 7 DIAS
LOSA DE FUNDACION 10 DIAS
MUROS DE CONTENCION Y DIVISORIOS 21 DIAS
BASES DE EQUIPOS 5 DIAS
SUBTOTAL 43 DIAS

AREA 3 Sand Filters


EXCAVACION 10 DIAS
ZAPATAS 10 DIAS
MUROS DE SAND FILTER 15 DIAS
LOSA DE PISO 7 DIAS
BASES DE EQUIPOS 5 DIAS
SUBTOTAL 47 DIAS

AREA 4 Thickener
EXCAVACION 10 DIAS
ZAPATAS 7 DIAS
MURO PERIMETRAL DE TANQUE 10 DIAS
LOSA DE PISO INTERNA 3 DIAS
SUBTOTAL 30 DIAS