Professional Documents
Culture Documents
BSCE – 5B
Project Name: Proposed 3 Bedroom Residential Date Starts: September 20, 2019
Area: 84.25 sq. m Date Finish: December 01, 2019
NO. NODES ACTIVITY NUMBER OF DURATION DESCRIPTION
WORKERS (DAYS)
1 A 3 5 Site Setting and Clearing
2 B 3 5 Layout and Fabrication of Steel Rebar
3 C 2 3 Excavation ,Demolition and Earthworks
4 D 3 4 Installation of Footing Rebar and
Framework
5 E 3 7 Concrete Pouring for Footing
6 F 3 5 Installation of Tie Beam Rebar and
Framework
7 G 3 5 Installation of Formwork for Tie Beam
8 H 3 7 Concrete Pouring for Tie Beam
9 I 3 4 Installation of Column Rebar and
Framework
10 J 4 8 Installation of Formwork for Column
11 K 5 7 Concrete Pouring for Column
12 L 3 5 Installation of Roof Beam Rebar and
Framework
13 M 4 7 Installation of Formwork for Roof Beam
14 N 3 7 Concrete Pouring for Roof Beam
15 O 3 5 Backfill and Compaction
16 P 4 12 Laying of CHB
17 Q 3 4 Finishing of CHB Joints
18 R 5 9 Plumbing Works and Installation of Septic
Tank
19 S 3 6 Fabrication of Trusses
20 T 3 6 Installation of Scaffolding
21 U 3 5 Installation of Trusses
22 V 3 8 Installation of Gutter and Roofing
23 W 2 5 Electrical Works
24 X 2 6 Installation of Doors and Windows
25 Y 5 9 Plastering
26 Z 5 10 Installation of Floor Slab Rebar and
Framework
27 A’ 3 7 Concrete Pouring for Floor Slab
28 B’ 2 2 Ceiling
29 C’ 3 8 Installation of Bowl, Lavatory, Faucet, and
Waterline
30 D’ 5 9 Painting
31 E’ 6 30 Tiles Work
32 F’ 5 10 Cleaning
Total Cost: Php. 2,445,518.97
COMPUTATION
SITE SETTING AND CLEARING
Duration = 5 days for 3 men
FABRICATION OF STEEL BAR
Duration = 5 days for 3 men
EXCAVATION
Volume = 1(1)(1)(15)+0.4(0.5)(51) = 25.20 cu.m
Duration = 25.20cu.m / (0.61cu.m./hrs) (8hrs/day)
Duration = 5.164 days for 1 man
Duration = 3 days for 2 men
CONCRETING OF FOOTING
Volume = 0.2(1)(1)(15)+0.2(0.4)(69.50) = 8.56 cu.m
Duration = 8.56cu.m / (0.42cu.m/day)
Duration = 20.381 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF TIE BEAM
Volume = 0.2(0.4)(63.25) = 5.06 cu.m
Duration = 5.06cu.m / (0.25cu.m/day)
Duration = 20.24 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF REINFORCE FLOORING
Volume = 86.25sq.m (0.1m) = 8.625 cu.m
Duration = 8.625cu.m / (0.42cu.m/day)
Duration = 20.536 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF COLUMN
Volume = 0.3(0.4)(4.8)(15) = 8.64 cu.m
Duration = 8.64 cu.m / (0.25cu.m/day)
Duration = 34.56 days for 1 man
Duration = 7 days for 5 men
INSTALLATION OF WINDOWS
No. of Sets = 9 pcs
Duration = 9pcs / (2pcs/day)
Duration = 4.5 days for 1 man
Duration = 3 days for 2 men
ELECTRICAL WORKS
Duration = 5 days for 2 men
PLASTERING BOTH SIDES
Surface Area = 180 sq.m
Duration = 180sq.m / (4sq.m/day)
Duration = 45 days for 1 man
Duration = 9 days for 5 men
PAINTING BOTH SIDES
Surface Area = 180 sq.m
Duration = 180 sq.m / (4sq.m./day)
Duration = 45 days for 1 man
Duration = 9 days for 5 men
INSTALLATION OF TILES
No. of Tiles = (84.25sq.m+66sq.m) / (0.023226sq.m/pc) = 6,469 pcs
Duration = 6,469pcs. / (36pcs./day)
Duration = 179.69s days for 1 man
Duration = 30 days for 6 men
FINAL CLEANING
Duration = 10 days for 5 men