RONNEL CESISTA FABIA

BSCE – 5B
Project Name: Proposed 3 Bedroom Residential Date Starts: September 20, 2019
Area: 84.25 sq. m Date Finish: December 01, 2019
NO. NODES ACTIVITY NUMBER OF DURATION DESCRIPTION
WORKERS (DAYS)
1 A 3 5 Site Setting and Clearing
2 B 3 5 Layout and Fabrication of Steel Rebar
3 C 2 3 Excavation ,Demolition and Earthworks
4 D 3 4 Installation of Footing Rebar and
Framework
5 E 3 7 Concrete Pouring for Footing
6 F 3 5 Installation of Tie Beam Rebar and
Framework
7 G 3 5 Installation of Formwork for Tie Beam
8 H 3 7 Concrete Pouring for Tie Beam
9 I 3 4 Installation of Column Rebar and
Framework
10 J 4 8 Installation of Formwork for Column
11 K 5 7 Concrete Pouring for Column
12 L 3 5 Installation of Roof Beam Rebar and
Framework
13 M 4 7 Installation of Formwork for Roof Beam
14 N 3 7 Concrete Pouring for Roof Beam
15 O 3 5 Backfill and Compaction
16 P 4 12 Laying of CHB
17 Q 3 4 Finishing of CHB Joints
18 R 5 9 Plumbing Works and Installation of Septic
Tank
19 S 3 6 Fabrication of Trusses
20 T 3 6 Installation of Scaffolding
21 U 3 5 Installation of Trusses
22 V 3 8 Installation of Gutter and Roofing
23 W 2 5 Electrical Works
24 X 2 6 Installation of Doors and Windows
25 Y 5 9 Plastering
26 Z 5 10 Installation of Floor Slab Rebar and
Framework
27 A’ 3 7 Concrete Pouring for Floor Slab
28 B’ 2 2 Ceiling
29 C’ 3 8 Installation of Bowl, Lavatory, Faucet, and
Waterline
30 D’ 5 9 Painting
31 E’ 6 30 Tiles Work
32 F’ 5 10 Cleaning
Total Cost: Php. 2,445,518.97
COMPUTATION
SITE SETTING AND CLEARING
Duration = 5 days for 3 men
FABRICATION OF STEEL BAR
Duration = 5 days for 3 men
EXCAVATION
Volume = 1(1)(1)(15)+0.4(0.5)(51) = 25.20 cu.m
Duration = 25.20cu.m / (0.61cu.m./hrs) (8hrs/day)
Duration = 5.164 days for 1 man
Duration = 3 days for 2 men
CONCRETING OF FOOTING
Volume = 0.2(1)(1)(15)+0.2(0.4)(69.50) = 8.56 cu.m
Duration = 8.56cu.m / (0.42cu.m/day)
Duration = 20.381 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF TIE BEAM
Volume = 0.2(0.4)(63.25) = 5.06 cu.m
Duration = 5.06cu.m / (0.25cu.m/day)
Duration = 20.24 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF REINFORCE FLOORING
Volume = 86.25sq.m (0.1m) = 8.625 cu.m
Duration = 8.625cu.m / (0.42cu.m/day)
Duration = 20.536 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF COLUMN
Volume = 0.3(0.4)(4.8)(15) = 8.64 cu.m
Duration = 8.64 cu.m / (0.25cu.m/day)
Duration = 34.56 days for 1 man
Duration = 7 days for 5 men

CONCRETING OF ROOF BEAM


Volume = 0.2(0.4)(63.25) = 5.06 cu.m
Duration = 5.06cu.m / (0.25cu.m/day)
Duration = 20.24 days for 1 man
Duration = 7 days for 3 men
INSTALLATION OF REBAR FOR FOOTING
Mass of Rebar = 980 kg
Duration = 980kg (9hrs/100kg) / (8hrs/day)
Duration = 11.025 days for 1 man
Duration = 4 days for 3 men
INSTALLATION OF REBAR FOR TIE BEAM
Mass of Rebar = 1210 kg
Duration = 1210kg (9hrs/100kg) / (8hrs/day)
Duration = 13.6125 days for 1 man
Duration = 5 days for 3 men
INSTALLATION OF REBAR FOR FLOORING
Mass of Rebar = 4390 kg
Duration = 4390kg (9hrs/100kg) / (8hrs/day)
Duration = 49.3875 days for 1 man
Duration = 10 days for 5 men
INSTALLATION OF REBAR FOR COLUMN
Mass of Rebar = 910 kg
Duration = 910kg (9hrs/100kg) / (8hrs/day)
Duration = 10.2375 days for 1 man
Duration = 4 days for 3 men
INSTALLATION OF REBAR FOR ROOF BEAM
Mass of Rebar = 1210 kg
Duration = 1210kg (9hrs/100kg) / (8hrs/day)
Duration = 13.6125 days for 1 man
Duration = 5 days for 3 men

INSTALLATION OF FORMWORKS FOR TIE BEAM


Surface Area = (0.2+0.4)(63.25) = 37.95 sq.m
Duration = 37.95sq.m (2.8manhours/sq.m) / (8hrs/day)
Duration = 13.2825 days for 1 man
Duration = 5 days for 3 men
INSTALLATION OF FORMWORKS FOR COLUMN
Surface Area = 2(0.3+0.4)(4.8)(15) = 100.80 sq.m
Duration = 100.80sq.m (2.5manhours/sq.m) / (8hrs/day)
Duration = 31.50 days for 1 man
Duration = 8 days for 4 men
INSTALLATION OF FORMWORKS FOR ROOF BEAM
Surface Area = 2(0.2+0.4)(63.25) = 75.90 sq.m
Duration = 75.90sq.m (3.01manhours/sq.m) / (8hrs/day)
Duration = 28.557 days for 1 man
Duration = 7 days for 4 men
REMOVING OF FORMWORKS FOR TIE BEAM
Surface Area = 2(0.2+0.4)(63.25) = 75.90 sq.m
Duration = 75.90sq.m (2.8manhours/sq.m) / (8hrs/day)
Duration = 26.565 days for 1 man
Duration = 7 days for 4 men
REMOVING OF FORMWORKS FOR COLUMN
Surface Area = 2(0.3+0.4)(4.8)(15) = 100.80 sq.m
Duration = 100.80sq.m (2.5manhours/sq.m) / (8hrs/day)
Duration = 31.50 days for 1 man
Duration = 8 days for 4 men
REMOVING OF FORMWORKS FOR ROOF BEAM
Surface Area = 2(0.2+0.4)(63.25) = 75.90 sq.m
Duration = 75.90sq.m (3.01manhours/sq.m) / (8hrs/day)
Duration = 28.557 days for 1 man
Duration = 7 days for 4 men

BACKFILL AND COMPACTION


Volume = 0.9(86.25)+25.20-13.164 = 89.661 cu.m
Duration = 89.661cu.m (1.34manhours) / (8hrs/day)
Duration = 15.018 days for 1 man
Duration = 5 days for 3 men
LAYING OF CHB
No. of Pieces = 184.75sq.m (12.5pcs/sq.m) = 2309.375 pcs. Say 2310 pcs.
Duration = 2310pcs. / (50pcs./day)
Duration = 46.2 days for 1 man
Duration = 12 days for 4 men
FINISHING OF CHB JOINTS
No. of Pieces = 184.75sq.m (12.5pcs/sq.m) = 2309.375 pcs. Say 2310 pcs.
Duration = 2310pcs. / (210pcs./day)
Duration = 11 days for 1 man
Duration = 4 days for 3 men
INSTALLATION OF SCAFFOLDING
Duration = 6 days for 3 men
FABRICATION OF TRUSS
Mass of Truss = 2,160 kg
Duration = 2,160kg / (120kg/day)
Duration = 18 days for 1 man
Duration = 6 days for 3 men
INSTALLATION OF CEILING
Surface Area = 84.25 sq.m
Duration = 84.25sq.m / (22.5sq.m/day)
Duration = 3.744 days for 1 man
Duration = 2 days for 2 men
INSTALLATION OF TRUSS
No. of Sets = 20 sets
Duration = 20sets / (1.333sets/day)
Duration = 15 days for 1 men
Duration = 5 days 3 men

INSTALLATION OF G.I. SHEETS


No. of Sheets = 122.045sq.m. / (1.71sq.m effective size/Sheets) = 71.37 say 72 sheets
Duration = 72sheets / (5.5sheets/day)
Duration = 13.091 days for 1 man
Duration = 5 days for 3 men
INSTALLATION OF GUTTER AND DOWNSPOUT
Duration = 3 days for 3 men
PLUMBING WORKS
Duration = 3 days for 5 men
INSTALLATION OF WATERLINE
Duration = 2 days for 3 men
INSTALLATION OF WATER CLOSET
No. of Sets = 2 sets
Duration = 2sets / (0.5set W.C./2days)
Duration = 8 days for 1 man
Duration = 3 days for 3 man
INSTALLATION OF LAVATORY
No. of Sets = 3 sets
Duration = 3sets / (0.5set/1.5days)
Duration = 9 days for 1 man
Duration = 3 days for 3 men
INSTALLATION OF SEPTIC TANK
Duration = 6 days for 5 men
INSTALLATION OF DOOR AND WINDOW JAMB
No. of Board Feet = 54 Brd.Ft.
Duration = 54Brd.Ft. / (40Brd.Ft./day)
Duration = 1.35 days for 1 man
Duration = 1 days for 2 man
INSTALLATION OF DOORS
No. of Sets = 7 pcs
Duration = 7pcs / (2pcs/day)
Duration = 3.5 days for 1 man
Duration = 2 days for 2 men

INSTALLATION OF WINDOWS
No. of Sets = 9 pcs
Duration = 9pcs / (2pcs/day)
Duration = 4.5 days for 1 man
Duration = 3 days for 2 men
ELECTRICAL WORKS
Duration = 5 days for 2 men
PLASTERING BOTH SIDES
Surface Area = 180 sq.m
Duration = 180sq.m / (4sq.m/day)
Duration = 45 days for 1 man
Duration = 9 days for 5 men
PAINTING BOTH SIDES
Surface Area = 180 sq.m
Duration = 180 sq.m / (4sq.m./day)
Duration = 45 days for 1 man
Duration = 9 days for 5 men
INSTALLATION OF TILES
No. of Tiles = (84.25sq.m+66sq.m) / (0.023226sq.m/pc) = 6,469 pcs
Duration = 6,469pcs. / (36pcs./day)
Duration = 179.69s days for 1 man
Duration = 30 days for 6 men
FINAL CLEANING
Duration = 10 days for 5 men