RONNEL CESISTA FABIA

BSCE – 5B
Project Name: Proposed 3 Bedroom Residential Date Starts: September 30, 2019
Area: 84.25 sq. m Date Finish: March 9, 2020
NO. TOTAL ACTIVITY NUMBER OF DURATION DESCRIPTION
FLOAT WORKERS (DAYS)
1 0 A 3 5 Site Setting and Clearing

2 0 B 3 3 Layout and Fabrication of Steel Rebar

3 0 C 2 3 Excavation ,Demolition and Earthworks


4 0 D 3 4 Installation of Footing Rebar and Framework

5 0 E 3 7 Concrete Pouring for Footing

6 5 F 3 5 Installation of Tie Beam Rebar and Framework

7 5 G 3 5 Installation of Formwork for Tie Beam

8 5 H 3 7 Concrete Pouring for Tie Beam

9 0 I 3 4 Installation of Column Rebar and Framework

10 0 J 4 8 Installation of Formwork for Column

11 0 K 5 7 Concrete Pouring for Column

12 0 L 3 5 Installation of Roof Beam Rebar and Framework

13 0 M 4 7 Installation of Formwork for Roof Beam

14 8 N 3 7 Concrete Pouring for Roof Beam

15 0 O 4 15 Removing for Formworks for Column and Tie


Beam
16 0 P 3 5 Backfill and Compaction

17 1 Q 4 12 Laying of CHB
18 1 R 3 4 Finishing of CHB Joints

19 12 S 5 9 Plumbing Works and Installation of Septic Tank

20 12 T 4 7 Removing of Formworks form for Roof Beam

21 0 U 3 6 Fabrication of Trusses

22 0 V 3 6 Installation of Scaffolding

23 0 W 3 5 Installation of Trusses

24 0 X 3 8 Installation of Gutter and Roofing and Ceiling Joist

25 7 Y 2 5 Electrical Works

26 28 Z 2 6 Installation of Doors and Windows


27 7 A’ 5 9 Plastering

28 0 B’ 5 10 Installation of Floor Slab Rebar and Framework

29 0 C’ 3 7 Concrete Pouring for Floor Slab

30 7 D’ 2 4 Installation of Ceiling

31 0 E’ 3 8 Installation of Water Closet, Lavatory, Faucet, and


Waterline
32 7 F’ 5 9 Painting

33 0 G’ 6 30 Tiles Work

34 0 H’ 5 10 Cleaning

Total Cost: Php. 2,445,518.97


RONNEL CESISTA FABIA
BSCE – 5B
Project Name: Proposed 3 Bedroom Residential Date Starts: September 30, 2019
Area: 84.25 sq. m Date Finish: March 9, 2020
NO. ACTIVITY EARLY EARLY LATEST LATEST TOTAL FREE CRITICAL
START FINISH START FINISH FLOAT FLOAT PATH
1 A 0 5 0 5 0 0 CP

2 B 5 8 5 8 0 0 CP

3 C 5 8 5 8 0 0 CP
4 D 8 12 8 12 0 0 CP

5 E 16 23 16 23 0 0 CP

6 F 16 21 21 26 5 0 -

7 G 21 26 26 31 5 0 -

8 H 38 45 43 50 5 0 -

9 I 12 16 12 16 0 0 CP

10 J 23 31 23 31 0 0 CP

11 K 31 38 31 38 0 0 CP

12 L 38 43 38 43 0 0 CP

13 M 43 50 43 50 0 0 CP

14 N 50 57 58 65 8 0 -

15 O 50 65 50 65 0 0 CP

16 P 65 70 65 70 0 0 CP

17 Q 70 82 71 83 1 0 -
18 R 82 86 83 87 1 0 -

19 S 65 74 77 86 12 0 -

20 T 74 81 86 93 12 0 -

21 U 70 76 70 76 0 0 CP

22 V 76 82 76 82 0 0 CP

23 W 82 87 82 87 0 0 CP

24 X 87 95 87 95 0 0 CP

25 Y 86 91 93 98 7 0 -

26 Z 86 92 114 120 28 0 -
27 A’ 91 100 98 107 7 0 -

28 B’ 95 105 95 105 0 0 CP

29 C’ 105 112 105 112 0 0 CP

30 D’ 100 104 107 111 7 0 -

31 E’ 112 120 112 120 0 0 CP

32 F’ 104 113 111 120 7 0 -

33 G’ 120 150 120 150 0 0 CP

34 H’ 150 160 150 160 0 0 CP

COMPUTATION
SITE SETTING AND CLEARING
Duration = 5 days for 3 men
FABRICATION OF STEEL BAR
Duration = 5 days for 3 men
EXCAVATION
Volume = 1(1)(1)(15)+0.4(0.5)(51) = 25.20 cu.m
Duration = 25.20cu.m / (0.61cu.m./hrs) (8hrs/day)
Duration = 5.164 days for 1 man
Duration = 3 days for 2 men
CONCRETING OF FOOTING
Volume = 0.2(1)(1)(15)+0.2(0.4)(69.50) = 8.56 cu.m
Duration = 8.56cu.m / (0.42cu.m/day)
Duration = 20.381 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF TIE BEAM
Volume = 0.2(0.4)(63.25) = 5.06 cu.m
Duration = 5.06cu.m / (0.25cu.m/day)
Duration = 20.24 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF REINFORCE FLOORING
Volume = 86.25sq.m (0.1m) = 8.625 cu.m
Duration = 8.625cu.m / (0.42cu.m/day)
Duration = 20.536 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF COLUMN
Volume = 0.3(0.4)(4.8)(15) = 8.64 cu.m
Duration = 8.64 cu.m / (0.25cu.m/day)
Duration = 34.56 days for 1 man
Duration = 7 days for 5 men

CONCRETING OF ROOF BEAM


Volume = 0.2(0.4)(63.25) = 5.06 cu.m
Duration = 5.06cu.m / (0.25cu.m/day)
Duration = 20.24 days for 1 man
Duration = 7 days for 3 men
INSTALLATION OF REBAR FOR FOOTING
Mass of Rebar = 980 kg
Duration = 980kg (9hrs/100kg) / (8hrs/day)
Duration = 11.025 days for 1 man
Duration = 4 days for 3 men
INSTALLATION OF REBAR FOR TIE BEAM
Mass of Rebar = 1210 kg
Duration = 1210kg (9hrs/100kg) / (8hrs/day)
Duration = 13.6125 days for 1 man
Duration = 5 days for 3 men
INSTALLATION OF REBAR FOR FLOORING
Mass of Rebar = 4390 kg
Duration = 4390kg (9hrs/100kg) / (8hrs/day)
Duration = 49.3875 days for 1 man
Duration = 10 days for 5 men
INSTALLATION OF REBAR FOR COLUMN
Mass of Rebar = 910 kg
Duration = 910kg (9hrs/100kg) / (8hrs/day)
Duration = 10.2375 days for 1 man
Duration = 4 days for 3 men
INSTALLATION OF REBAR FOR ROOF BEAM
Mass of Rebar = 1210 kg
Duration = 1210kg (9hrs/100kg) / (8hrs/day)
Duration = 13.6125 days for 1 man
Duration = 5 days for 3 men

INSTALLATION OF FORMWORKS FOR TIE BEAM


Surface Area = (0.2+0.4)(63.25) = 37.95 sq.m
Duration = 37.95sq.m (2.8manhours/sq.m) / (8hrs/day)
Duration = 13.2825 days for 1 man
Duration = 5 days for 3 men
INSTALLATION OF FORMWORKS FOR COLUMN
Surface Area = 2(0.3+0.4)(4.8)(15) = 100.80 sq.m
Duration = 100.80sq.m (2.5manhours/sq.m) / (8hrs/day)
Duration = 31.50 days for 1 man
Duration = 8 days for 4 men
INSTALLATION OF FORMWORKS FOR ROOF BEAM
Surface Area = 2(0.2+0.4)(63.25) = 75.90 sq.m
Duration = 75.90sq.m (3.01manhours/sq.m) / (8hrs/day)
Duration = 28.557 days for 1 man
Duration = 7 days for 4 men
REMOVING OF FORMWORKS FOR TIE BEAM
Surface Area = 2(0.2+0.4)(63.25) = 75.90 sq.m
Duration = 75.90sq.m (2.8manhours/sq.m) / (8hrs/day)
Duration = 26.565 days for 1 man
Duration = 7 days for 4 men
REMOVING OF FORMWORKS FOR COLUMN
Surface Area = 2(0.3+0.4)(4.8)(15) = 100.80 sq.m
Duration = 100.80sq.m (2.5manhours/sq.m) / (8hrs/day)
Duration = 31.50 days for 1 man
Duration = 8 days for 4 men
REMOVING OF FORMWORKS FOR ROOF BEAM
Surface Area = 2(0.2+0.4)(63.25) = 75.90 sq.m
Duration = 75.90sq.m (3.01manhours/sq.m) / (8hrs/day)
Duration = 28.557 days for 1 man
Duration = 7 days for 4 men

BACKFILL AND COMPACTION


Volume = 0.9(86.25)+25.20-13.164 = 89.661 cu.m
Duration = 89.661cu.m (1.34manhours) / (8hrs/day)
Duration = 15.018 days for 1 man
Duration = 5 days for 3 men
LAYING OF CHB
No. of Pieces = 184.75sq.m (12.5pcs/sq.m) = 2309.375 pcs. Say 2310 pcs.
Duration = 2310pcs. / (50pcs./day)
Duration = 46.2 days for 1 man
Duration = 12 days for 4 men
FINISHING OF CHB JOINTS
No. of Pieces = 184.75sq.m (12.5pcs/sq.m) = 2309.375 pcs. Say 2310 pcs.
Duration = 2310pcs. / (210pcs./day)
Duration = 11 days for 1 man
Duration = 4 days for 3 men
INSTALLATION OF SCAFFOLDING
Duration = 6 days for 3 men
FABRICATION OF TRUSS
Mass of Truss = 2,160 kg
Duration = 2,160kg / (120kg/day)
Duration = 18 days for 1 man
Duration = 6 days for 3 men
INSTALLATION OF CEILING
Surface Area = 84.25 sq.m
Duration = 84.25sq.m / (22.5sq.m/day)
Duration = 3.744 days for 1 man
Duration = 2 days for 2 men
INSTALLATION OF CEILING JOIST
No. of Board Feet = 84.25sq.m (4Brd.Ft./sq.m) = 337 Brd.Ft.
Duration = 337Brd.Ft. / (80Brd.Ft./day)
Duration = 4.2125 days for 1 man
Duration = 2 days for 2 men

INSTALLATION OF TRUSS
No. of Sets = 20 sets
Duration = 20sets / (1.333sets/day)
Duration = 15 days for 1 men
Duration = 5 days 3 men
INSTALLATION OF G.I. SHEETS
No. of Sheets = 122.045sq.m. / (1.71sq.m effective size/Sheets) = 71.37 say 72 sheets
Duration = 72sheets / (5.5sheets/day)
Duration = 13.091 days for 1 man
Duration = 5 days for 3 men
INSTALLATION OF GUTTER AND DOWNSPOUT
Duration = 3 days for 3 men
PLUMBING WORKS
Duration = 3 days for 5 men
INSTALLATION OF WATERLINE
Duration = 2 days for 3 men
INSTALLATION OF WATER CLOSET
No. of Sets = 2 sets
Duration = 2sets / (0.5set W.C./2days)
Duration = 8 days for 1 man
Duration = 3 days for 3 man
INSTALLATION OF LAVATORY
No. of Sets = 3 sets
Duration = 3sets / (0.5set/1.5days)
Duration = 9 days for 1 man
Duration = 3 days for 3 men
INSTALLATION OF SEPTIC TANK
Duration = 6 days for 5 men
INSTALLATION OF DOOR AND WINDOW JAMB
No. of Board Feet = 54 Brd.Ft.
Duration = 54Brd.Ft. / (40Brd.Ft./day)
Duration = 1.35 days for 1 man
Duration = 1 days for 2 man

INSTALLATION OF DOORS
No. of Sets = 7 pcs
Duration = 7pcs / (2pcs/day)
Duration = 3.5 days for 1 man
Duration = 2 days for 2 men
INSTALLATION OF WINDOWS
No. of Sets = 9 pcs
Duration = 9pcs / (2pcs/day)
Duration = 4.5 days for 1 man
Duration = 3 days for 2 men
ELECTRICAL WORKS
Duration = 5 days for 2 men
PLASTERING BOTH SIDES
Surface Area = 180 sq.m
Duration = 180sq.m / (4sq.m/day)
Duration = 45 days for 1 man
Duration = 9 days for 5 men
PAINTING BOTH SIDES
Surface Area = 180 sq.m
Duration = 180 sq.m / (4sq.m./day)
Duration = 45 days for 1 man
Duration = 9 days for 5 men
INSTALLATION OF TILES
No. of Tiles = (84.25sq.m+66sq.m) / (0.023226sq.m/pc) = 6,469 pcs
Duration = 6,469pcs. / (36pcs./day)
Duration = 179.69s days for 1 man
Duration = 30 days for 6 men
FINAL CLEANING
Duration = 10 days for 5 men