Professional Documents
Culture Documents
BSCE – 5B
Project Name: Proposed 3 Bedroom Residential Date Starts: September 30, 2019
Area: 84.25 sq. m Date Finish: March 9, 2020
NO. TOTAL ACTIVITY NUMBER OF DURATION DESCRIPTION
FLOAT WORKERS (DAYS)
1 0 A 3 5 Site Setting and Clearing
17 1 Q 4 12 Laying of CHB
18 1 R 3 4 Finishing of CHB Joints
21 0 U 3 6 Fabrication of Trusses
22 0 V 3 6 Installation of Scaffolding
23 0 W 3 5 Installation of Trusses
25 7 Y 2 5 Electrical Works
30 7 D’ 2 4 Installation of Ceiling
33 0 G’ 6 30 Tiles Work
34 0 H’ 5 10 Cleaning
2 B 5 8 5 8 0 0 CP
3 C 5 8 5 8 0 0 CP
4 D 8 12 8 12 0 0 CP
5 E 16 23 16 23 0 0 CP
6 F 16 21 21 26 5 0 -
7 G 21 26 26 31 5 0 -
8 H 38 45 43 50 5 0 -
9 I 12 16 12 16 0 0 CP
10 J 23 31 23 31 0 0 CP
11 K 31 38 31 38 0 0 CP
12 L 38 43 38 43 0 0 CP
13 M 43 50 43 50 0 0 CP
14 N 50 57 58 65 8 0 -
15 O 50 65 50 65 0 0 CP
16 P 65 70 65 70 0 0 CP
17 Q 70 82 71 83 1 0 -
18 R 82 86 83 87 1 0 -
19 S 65 74 77 86 12 0 -
20 T 74 81 86 93 12 0 -
21 U 70 76 70 76 0 0 CP
22 V 76 82 76 82 0 0 CP
23 W 82 87 82 87 0 0 CP
24 X 87 95 87 95 0 0 CP
25 Y 86 91 93 98 7 0 -
26 Z 86 92 114 120 28 0 -
27 A’ 91 100 98 107 7 0 -
28 B’ 95 105 95 105 0 0 CP
COMPUTATION
SITE SETTING AND CLEARING
Duration = 5 days for 3 men
FABRICATION OF STEEL BAR
Duration = 5 days for 3 men
EXCAVATION
Volume = 1(1)(1)(15)+0.4(0.5)(51) = 25.20 cu.m
Duration = 25.20cu.m / (0.61cu.m./hrs) (8hrs/day)
Duration = 5.164 days for 1 man
Duration = 3 days for 2 men
CONCRETING OF FOOTING
Volume = 0.2(1)(1)(15)+0.2(0.4)(69.50) = 8.56 cu.m
Duration = 8.56cu.m / (0.42cu.m/day)
Duration = 20.381 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF TIE BEAM
Volume = 0.2(0.4)(63.25) = 5.06 cu.m
Duration = 5.06cu.m / (0.25cu.m/day)
Duration = 20.24 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF REINFORCE FLOORING
Volume = 86.25sq.m (0.1m) = 8.625 cu.m
Duration = 8.625cu.m / (0.42cu.m/day)
Duration = 20.536 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF COLUMN
Volume = 0.3(0.4)(4.8)(15) = 8.64 cu.m
Duration = 8.64 cu.m / (0.25cu.m/day)
Duration = 34.56 days for 1 man
Duration = 7 days for 5 men
INSTALLATION OF TRUSS
No. of Sets = 20 sets
Duration = 20sets / (1.333sets/day)
Duration = 15 days for 1 men
Duration = 5 days 3 men
INSTALLATION OF G.I. SHEETS
No. of Sheets = 122.045sq.m. / (1.71sq.m effective size/Sheets) = 71.37 say 72 sheets
Duration = 72sheets / (5.5sheets/day)
Duration = 13.091 days for 1 man
Duration = 5 days for 3 men
INSTALLATION OF GUTTER AND DOWNSPOUT
Duration = 3 days for 3 men
PLUMBING WORKS
Duration = 3 days for 5 men
INSTALLATION OF WATERLINE
Duration = 2 days for 3 men
INSTALLATION OF WATER CLOSET
No. of Sets = 2 sets
Duration = 2sets / (0.5set W.C./2days)
Duration = 8 days for 1 man
Duration = 3 days for 3 man
INSTALLATION OF LAVATORY
No. of Sets = 3 sets
Duration = 3sets / (0.5set/1.5days)
Duration = 9 days for 1 man
Duration = 3 days for 3 men
INSTALLATION OF SEPTIC TANK
Duration = 6 days for 5 men
INSTALLATION OF DOOR AND WINDOW JAMB
No. of Board Feet = 54 Brd.Ft.
Duration = 54Brd.Ft. / (40Brd.Ft./day)
Duration = 1.35 days for 1 man
Duration = 1 days for 2 man
INSTALLATION OF DOORS
No. of Sets = 7 pcs
Duration = 7pcs / (2pcs/day)
Duration = 3.5 days for 1 man
Duration = 2 days for 2 men
INSTALLATION OF WINDOWS
No. of Sets = 9 pcs
Duration = 9pcs / (2pcs/day)
Duration = 4.5 days for 1 man
Duration = 3 days for 2 men
ELECTRICAL WORKS
Duration = 5 days for 2 men
PLASTERING BOTH SIDES
Surface Area = 180 sq.m
Duration = 180sq.m / (4sq.m/day)
Duration = 45 days for 1 man
Duration = 9 days for 5 men
PAINTING BOTH SIDES
Surface Area = 180 sq.m
Duration = 180 sq.m / (4sq.m./day)
Duration = 45 days for 1 man
Duration = 9 days for 5 men
INSTALLATION OF TILES
No. of Tiles = (84.25sq.m+66sq.m) / (0.023226sq.m/pc) = 6,469 pcs
Duration = 6,469pcs. / (36pcs./day)
Duration = 179.69s days for 1 man
Duration = 30 days for 6 men
FINAL CLEANING
Duration = 10 days for 5 men