SEQUENCE AND CONSTRUCTION PHASE ACTIVITY OF THE PROJECT

STORAGE TANK CAPACITY 50.000 KL (5 X 10.000 KL)


LOCATION : CIREBON- WEST JAVA

2021 - 2022 - 2023


NO. DESCRIPTION M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 REMARKS
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
1 PRE SURVEY
1 Banch Marking
2 Plan Lay Out
3 Access Road & Jetty Temporary

2 ENGINEERING
1 Basic and Detail Engineering Design

3 SOIL INVESTIGASI & BATHIMETRY


1 Study Soil Investigasi
2 Bathimatry

4 PROCUREMENT ACTIVITY
1 Long Lead Item
For Civil, Piping & Mechanical, E & I, & Accessories

5 CUTTING & FILLING


1 Cutting
2 Filling
3 Land Seatling

6 CIVIL WORK
1 Tank Foudation
- Piling
- Concrete
- Curing
2 Jetty
- Piling (Platform, Breasting & Mooring Dolpin & etc)
- Concrete (Platform, Bresting & Mooring Dolpin & etc)
- Curing

7 MECHANICAL WORK
1 Tank Erection
2 MLA Erection
3 Pump Erection
4 Piping Associated Erection

8 ELECTRICAL
1 Installation

9 INSTRUMENT
1 Installation

10 PRE COMMISIIONING & COMMISSIONING


1 Pre commissioning
2 Commissioning

LEGEND :
1 ACCUMULATIVE PROGRESS
2 PROGRESS PLAN (WEEKLY & MONTHLY)
JAKARTA, 15 OKTOBER 2021

MENYETUJUI, DISIAPKAN :
PT TAESUNG TECH INDONESIA PT PETRO TNC INTERNATIONAL

LIM JAE HA NADILLA SARI WIRIAWANPUTRI


DIREKTUR UTAMA KOMISARIS