[2 Storey 8 Classroom School Building] Project Schedule

[JJP Construction]

Project Start Date 1/24/2022 (Monday) Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21
Project Lead Engr. J. Pagal 24 Jan 2022 31 Jan 2022 7 Feb 2022 14 Feb 2022 21 Feb 2022 28 Feb 2022 7 Mar 2022 14 Mar 2022 21 Mar 2022 28 Mar 2022 4 Apr 2022 11 Apr 2022 18 Apr 2022 25 Apr 2022 2 May 2022 9 May 2022 16 May 2022 23 May 2022 30 May 2022 6 Jun 2022 13 Jun 2022
DATE 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
PREDECESSO
TASK DESCRIPTION AMOUNT START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
R
A Clearing the site START Mon 1/24/22 Mon 1/31/22 8 1 1 1 1 1 1 1 1
B Construction of field office A Tue 2/01/22 Mon 2/07/22 7 1 1 1 1 1 1 1
C Delivery of materials B Tue 2/08/22 Mon 2/14/22 7 1 1 1 1 1 1 1
D Stalking and batter boards A Tue 2/01/22 Mon 2/07/22 7 1 1 1 1 1 1 1
E Excavation D Tue 2/08/22 Wed 2/16/22 9 1 1 1 1 1 1 1 1 1
F Cutting and assembling of reinforcements D Tue 2/08/22 Thu 2/17/22 10 1 1 1 1 1 1 1 1 1 1
G Positioning steel reinforcements E Thu 2/17/22 Wed 3/02/22 14 1 1 1 1 1 1 1 1 1 1 1 1 1 1
H Form works for footing-column F Fri 2/18/22 Sat 2/26/22 9 1 1 1 1 1 1 1 1 1
I Pouring of footing G Thu 3/03/22 Wed 3/09/22 7 1 1 1 1 1 1 1
J Back filling and compaction, slab on fill I Thu 3/10/22 Wed 3/16/22 7 1 1 1 1 1 1 1
K Electrical, plumbing and water pipe connections G Thu 3/03/22 Wed 3/09/22 7 1 1 1 1 1 1 1
L Pouring of columns J Thu 3/17/22 Fri 3/25/22 9 1 1 1 1 1 1 1 1 1
M GF CHB laying L Sat 3/26/22 Fri 4/08/22 14 1 1 1 1 1 1 1 1 1 1 1 1 1 1
N Beams and slabs forms & reinforcing and various piping installations M Sat 4/09/22 Mon 4/18/22 10 1 1 1 1 1 1 1 1 1 1
O Pouring of 2F beams and slabs N Tue 4/19/22 Mon 4/25/22 7 1 1 1 1 1 1 1
P 2F CHB laying, column, roof beam O Mon 4/25/22 Sun 5/08/22 14 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Q Roof framing and roofing sheet P Sun 5/08/22 Mon 5/16/22 9 1 1 1 1 1 1 1 1 1
R Construction of stairways and installation of corridor railings P Sun 5/08/22 Sat 5/14/22 7 1 1 1 1 1 1 1
S Plastering and tile works P Sun 5/08/22 Sat 5/21/22 14 1 1 1 1 1 1 1 1 1 1 1 1 1 1
T Plumbing and drainage system Q Tue 5/17/22 Fri 5/20/22 4 1 1 1 1
U Installation of electrical wiring and fixtures S Sun 5/22/22 Sat 5/28/22 7 1 1 1 1 1 1 1
V Installation of plumbing fixtures U Sun 5/29/22 Thu 6/02/22 5 1 1 1 1 1
W Painting and installation of writing boards S Sun 5/22/22 Sat 6/04/22 14 1 1 1 1 1 1 1 1 1 1 1 1 1 1
X Final work and cleaning W Sun 6/05/22 Tue 6/14/22 10 1 1 1 1 1 1 1 1 1 1
TOTAL COST 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 3 3 3 3 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 1 1 1 1 1 1 4 3 3 3 3 3 3 2 2 2 2 2 2 1 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1