ID TaskTask Name Duration Start Finish Predecessors Resource Names

Mode
14 Nov '2128 Nov '2112 Dec '2126 Dec '2109 Jan '2223 Jan '2206 Feb '2220 Feb '2206 Mar '2220 Mar '2203 Apr '2217 Apr '2201 May '2215 May '22
M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T
1 Biaya umum 79 days 01 Dec '21 21 Mar '22 BIAYA UMUM
2 I. Pekerjaan Persiapan 6 days 01 Dec '21 08 Dec '21
3 1.1 Pembersihan Lapangan 4 days 01 Dec '21 06 Dec '21 P[200%] P[200%]

4 1.2 Membuat Gudang 2 days 07 Dec '21 08 Dec '21 3 P[200%];TK[200%];Material Gudang/los kerja[1] P[200%];TK[200%];Material Gudang/los kerja[1]

5 1.3 Pembuatan Bowplank 1 day 07 Dec '21 07 Dec '21 3 Bowplank[1];P[200%];TK[200%] Bowplank[1];P[200%];TK[200%]

6 II. Pekerjaan Pondasi 18 days 07 Dec '21 30 Dec '21


7 2.1 Menggali Tanah 6 days 07 Dec '21 14 Dec '21 5SS P[400%] P[400%]

8 2.2 Anstampang 5 days 08 Dec '21 14 Dec '21 7FS-5 days Aanstampang[1];P[200%] Aanstampang[1];P[200%]

9 2.3 Pemasangan batu kali 7 days 14 Dec '21 22 Dec '21 8FS-1 day P[200%];Pas batu kali[1];TB[200%] P[200%];Pas batu kali[1];TB[200%]

10 2.4 Timbunan kembali 6 days 23 Dec '21 30 Dec '21 9 P[200%] P[200%]

11 III. Pekerjaan Beton 33 days 16 Dec '21 31 Jan '22


12 3.1 Merangkai Besi 3 days 16 Dec '21 20 Dec '21 4FS+5 days Merangkai Besi[1];P[200%];TBS Merangkai Besi[1];P[200%];TBS

13 3.2 Mengecor Sloof 5 days 23 Dec '21 29 Dec '21 9;12 P[200%];TB[200%];TBS[200%];Mencor Sloof[1] P[200%];TB[200%];TBS[200%];Mencor Sloof[1]

14 3.3 Mengecor kolom 14 days 03 Jan '22 20 Jan '22 13FS+2 daysMencor kolom[1];P[200%];TB[200%];TBS[200%] Mencor kolom[1];P[200%];TB[200%];TBS[200%]

15 3.4 Mengecor Ring Balok 7 days 21 Jan '22 31 Jan '22 14;17 Memasang bata[1];P[200%];TB[200%] Memasang bata[1];P[200%];TB[200%]

16 IV. Pekerjaan Dinding 24 days 30 Dec '21 01 Feb '22


17 4.1 Memasang bata 14 days 30 Dec '21 18 Jan '22 13 Memasang bata[1];P[400%];TB[200%] Memasang bata[1];P[400%];TB[200%]

18 4.2 Plesteran 10 days 19 Jan '22 01 Feb '22 17 P[400%];Plesteran[1];TB[200%] P[400%];Plesteran[1];TB[200%]

19 V. Pekerjaan Atap 15 days 01 Feb '22 21 Feb '22


20 5.1 Kuda-kuda 7 days 01 Feb '22 09 Feb '22 15 Memasang kuda-kuda[1];P[400%];TK[300%] Memasang kuda-kuda[1];P[400%];TK[300%]

21 5.2 Gording, rusuk, reng 4 days 10 Feb '22 15 Feb '22 20 P[400%];TK[300%];Gording rusuk dan reng[1] P[400%];TK[300%];Gording rusuk dan reng[1]

22 5.3 Seng dan Talang 4 days 16 Feb '22 21 Feb '22 21 P[400%];Seng dan talang[1];TK[200%] P[400%];Seng dan talang[1];TK[200%]

23 VI. Pekerjaan Plafond 5 days 22 Feb '22 28 Feb '22


24 6.1 Memasang Rangka 3 days 22 Feb '22 24 Feb '22 22 Memasang rangka[1];P[200%];TK[200%] Memasang rangka[1];P[200%];TK[200%]

25 6.2 Memasang Penutup Triplek 3 days 24 Feb '22 28 Feb '22 24FS-1 day Memasang penutup triplek[1];P[200%];TK[200%] Memasang penutup triplek[1];P[200%];TK[200%

26 VII. Pekerjaan Lantai 49 days 31 Dec '21 09 Mar '22


27 7.1 Timbunan Lantai 3 days 31 Dec '21 04 Jan '22 10 P[200%];Timbunan Lantai[1] P[200%];Timbunan Lantai[1]

28 7.2 Memasang Kramik 7 days 01 Mar '22 09 Mar '22 25;27 Memasang keramik dan tegel[1];P[200%];TB[200%] Memasang keramik dan tegel[1];P[200%];T

29 VIII. Pekerjaan Cat 8 days 10 Mar '22 21 Mar '22


30 8.1 Mengecat Dinding 4 days 16 Mar '22 21 Mar '22 18;31 P[200%];TC[200%];Mencat dinding[1] P[200%];TC[200%];Mencat dinding[1

31 8.2 Mengecat Plafond 4 days 10 Mar '22 15 Mar '22 25;28 Mencat Plafond[1];P;TC Mencat Plafond[1];P;TC

Task Project Summary Manual Task Start-only Deadline

Project: Quiz 14.mpp Split Inactive Task Duration-only Finish-only Progress

Date: 05 Dec '21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone