7 Canal Residence

Project Start Date 1/22/2024 (Monday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Project Lead 22 Jan 2024 29 Jan 2024 5 Feb 2024 12 Feb 2024 19 Feb 2024 26 Feb 2024 4 Mar 2024 11 Mar 2024
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
% WORK
WBS TASK START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE DAYS
1 Substructure-Basement -02-Level--12-Pour-02 - -
Fix steel of Remaining Columns and
1.1 Mon 1/29/24 Wed 1/31/24 1 0% 3
Shear walls
Pour Concrete of Columns and Shear
1.2 Tue 1/30/24 Tue 1/30/24 4 0% 1
Wall Phase-1
Fix Formwork for Remaining Columns
1.3 Thu 2/01/24 Sat 2/03/24 3 0% 2
and shear wall
Pour Concrete of Columns and Shear
1.4 Sat 2/03/24 Sat 2/03/24 1 0% 0
Wall Phase-2
1.5 Shuttering for Beams Pour-1 Mon 1/29/24 Wed 1/31/24 2 0% 3
1.6 Set formwork for Slab Pour-1 Wed 1/31/24 Fri 2/02/24 2 0% 3
1.7 Fix formwork for Beams Pour-2 Sat 2/03/24 Mon 2/05/24 2 0% 1
1.8 Set formwork for Slab Pour-2 Tue 2/06/24 Fri 2/09/24 2 0% 4
Fix Steel of Slab and Beams Pour 1&
1.9 Sat 2/10/24 Mon 2/12/24 1 0% 1
Pour-2
1.10 Pour Concrete of Slab Tue 2/13/24 Tue 2/13/24 1 0% 1