ID Task Task Name Duration Start Finish Qtr 4, 2021 Qtr 1, 2022

Mode Sep Oct Nov Dec Jan


1 PEKERJAAN REHABILITASI GEDUNG OK 64 days Mon 04/10/21 Thu 30/12/21
2 Mulai 0 days Mon 04/10/21 Mon 04/10/21 04/10
3 I. PEKERJAAN PERSIAPAN 5 days Mon 04/10/21 Fri 08/10/21
4 Pek. Bongkar pasang alat OK 5 days Mon 04/10/21 Fri 08/10/21
5 II.PEKERJAAN ATAP 59 days Mon 11/10/21 Thu 30/12/21
6 Pek. Bongkar Atap 20 days Mon 11/10/21 Fri 05/11/21 Pekerja[50%]
7 Pek. Bongkar Listplank 2 days Mon 11/10/21 Tue 12/10/21 Pekerja[30%]
8 Pek. Pasang Atap 30 days Mon 08/11/21 Fri 17/12/21 Pekerja[60%]
9 Pek. Pasang Nok 9 days Mon 20/12/21 Thu 30/12/21 Pekerja[20%]
10 Pek. Listplank 4 days Fri 17/12/21 Wed 22/12/21 Pekerja[20%]
11 Pek. Talang Air 3 days Fri 17/12/21 Tue 21/12/21 Pekerja[20%]
12 III.PEKERJAAN PLAFOND 19 days Tue 02/11/21 Fri 26/11/21
13 Pek. Plafond OKA 1,2 10 days Tue 02/11/21 Mon 15/11/21
14 Pek. Bongkar Plafond 2 days Tue 02/11/21 Wed 03/11/21 Pekerja[20%]
15 Pek. Pasang Plafond gypsum 7 days Thu 04/11/21 Fri 12/11/21 Pekerja[20%]
16 Pek. Listprofil 1 day Mon 15/11/21 Mon 15/11/21 Pekerja[20%]
17 Pek. Plafond OKA 3,4 9 days Tue 16/11/21 Fri 26/11/21
18 Pek. Bongkar Plafond 1 day Tue 16/11/21 Tue 16/11/21 Pekerja[20%]
19 Pek. Pasang Plafond gypsum 7 days Wed 17/11/21 Thu 25/11/21 Pekerja[20%]
20 Pek. Listprofil 1 day Fri 26/11/21 Fri 26/11/21 Pekerja[20%]
21 IV. PEKERJAAN CAT 34 days Tue 09/11/21 Fri 24/12/21
22 Pek. Cat Plafond 13 days Tue 09/11/21 Thu 25/11/21 Pekerja[20%]
23 Pek. Cat Listplank 2 days Thu 23/12/21 Fri 24/12/21 Pekerja[10%]
24 Selesai 0 days Fri 24/12/21 Fri 24/12/21 24/12

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Time Schedule Rehab G
Summary Manual Summary Rollup Progress
Date: Wed 29/09/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1