The document outlines a 64-day rehabilitation project for an office building from October 4, 2021 to December 30, 2021. It is divided into four main phases: preparation work from October 4-8, roof work from October 11 to December 30, ceiling work from November 2-26, and painting from November 9 to December 24. Each phase contains sub-tasks with assigned durations and projected start and finish dates.
The document outlines a 64-day rehabilitation project for an office building from October 4, 2021 to December 30, 2021. It is divided into four main phases: preparation work from October 4-8, roof work from October 11 to December 30, ceiling work from November 2-26, and painting from November 9 to December 24. Each phase contains sub-tasks with assigned durations and projected start and finish dates.
The document outlines a 64-day rehabilitation project for an office building from October 4, 2021 to December 30, 2021. It is divided into four main phases: preparation work from October 4-8, roof work from October 11 to December 30, ceiling work from November 2-26, and painting from November 9 to December 24. Each phase contains sub-tasks with assigned durations and projected start and finish dates.