ID Task Name Duration Start Finish October 2021 November 2021

13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26
0 Project1 39 days Wed 9/29/21Mon 11/22/21

1 1 Langsir Material 1 day Wed 9/29/21 Wed 9/29/21

6 Orang Man Power


2 2 Pasar Begel Talang12 days Thu 9/30/21 Fri 10/15/21

4 Orang Man Power


3 3 Pasang talang 12 days Wed 10/6/21 Thu 10/21/21

15 orang Man Power


4 4 Produksi atap 17 days Wed 10/6/21 Thu 10/28/21

15 orang Man Power


5 5 Pasang Atap 25 days Fri 10/8/21 Thu 11/11/21

6 orang man Power


6 6 Finish 10 days Tue 11/9/21 Mon 11/22/21