Name Duration Start Finish Predecessors Baseline Cost

1 Project 22 days 4 / 1 / 2 1 8 : 0 0 A M 2/2/21 5:00 PM Rs.58000.00


2 A 5 days 4/1/21 8:00 AM 8/1/21 5:00 PM Rs.10000.00
3 B 4 days 11/1/21 8:00 AM 14/1/21 5:00 PM 2 Rs.4000.00
4 C 10 days 18/1/21 8:00 AM 29/1/21 5:00 PM 3 Rs.30000.00
5 D 2 days 1/2/21 8:00 AM 2/2/21 5:00 PM 4;6 Rs.4000.00
6 E 5 days 11/1/21 8:00 AM 15/1/21 5:00 PM 2 Rs.10000.00

Endterm - page1
3 Jan 21 10 Jan 21 17 Jan 21 24 Jan 21 31 Jan 21 7 Feb 21 14 Feb 21
Free Slack Total Slack Resource Names
F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F

0 days 0 days
0 days 1 day Roy Roy

1 day 1 day joy joy

0 days 0 days jim;Roy jim;Roy

0 days 0 days Roy Roy

10 days 10 days Roy Roy

Endterm - page2
4 Feb 21 21 Feb 21 28 Feb 21 7 Mar 21 14 Mar 21 21 Mar 21 28 Mar 21 4 Apr 21 11 Apr 21 18 Apr 21 25 Apr 21
M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T W

Endterm - page3
25 Apr 21 2 May 21 9 May 21 16 May 21 23 May 21 30 May 21 6 Jun 21 13 Jun 21 20 Jun 21 27 Jun 21 4 Ju
S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M T WT F S S M

Endterm - page4
1 4 Jul 21 11 Jul 21
WT F S S M T WT F S S M T W

Endterm - page5

You might also like