TIME S

16 Dec '19 23 Dec '19 30 Dec '19 06 Jan '20


No. Working Job Duration
S S R K J S M S S R K J S M S S R K J S M S S R K J S
1 Chain Grate 17 Days
2 Steam Drum
Erection 1 Day
Pipe line 15 Days
Pengelasan 15 Days
3 Refractory 12 Days
4 Economizer
Erection Economizer + accesories 4 days
Fabrication ducting out steam drum to Economizer 9 days
Fabrication ducting out economizer to air preheater 9 days
5 Fabrication Air Preheater 10 days
Ducting air preheater to multi cyclone 10 days
6 FDF motor gearbox inveler 3 days
Fabrication ducting out FDF to air preheater 6 days
fabrication ducting out air preheater to chain grate 13 days
7 Multi Cyclone Erection 2 days
fabrication ducting multi cyclone to water scruber 9 days
8 Water Scruber Erection 3 day
fabrication ducting water scruber to chimney 11 days
9 FABRICATION CHIMNEY 13 days
fabrication ducting chimney to IDF
10 IDF motor gearbox inveler 3 days
11 ELEKTRICAL+ INSTRUMENT 14 days
12 Plat form + HAN REAL 12 days
13 Water Tank and Pipe Line
Fabrication and Erection 10 days
14 FWP (Feed Water Pump) and Pipe Line 7 days
15 Softener Tank and Pipe Line 12 days
16 Steam Header and Accessoris 8 days
17 Pre Heating Furnace 7 days
18 Commisioning and Flushing 7 days
SCHEDULE INSTAL BOILER CHAIN GRATE THAISAN 30 T/H PROJECT PT. BEST GRESIK

13 Jan '20 20 Jan '20 27 Jan '20 03 Feb '20 10 Feb '20 17 Feb '20 24 Feb '20
M S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S R
02 Mar '20 09 Mar '20
K J S M S S R K J S M S S R K J S M

Time Proggres

Time Off