Request For Quotation (RFQ) Iss. Dep.

: Procurement
Zouk and Jiyeh O&M #: M-PRFQ-03
Week # 13 ID: 28/04/2012
March 27, 2017 RD: 20/01/2016
RFQ #: RFQ-PP-170327-02 Type: Power Plant
# Part # Description Qty Unit
Performance Test for Jiyeh 78 MW Power Plant as
below description:
Power Output, Auxiliary power consumption, Heat
Rate of the plant, Efficiency of diesel engine, steam
turbine, heat waste recovery boilers, steam
condensor performance and steam turbine
auxiliaries (boiler feed pumps, condensate pumps,
heat exchangers, etc…)
1 N/A 1 N/A
The test shall be asessed based on the following
standards
1. Diesel engines and generators according to ASME
PTC 17
2. Steam turbine and generator according to ASME
PTC 6.2
3. HRSG according to ASME PTC 4.4
4. Condensor according to ASME PTC 30.1
Performance Test for Zouk 194 MW Power Plant as
below description:
Power Output, Auxiliary power consumption, Heat
Rate of the plant, Efficiency of diesel engine, steam
turbine, heat waste recovery boilers, steam
condensor performance and steam turbine
auxiliaries (boiler feed pumps, condensate pumps,
heat exchangers, etc…)
2 N/A 1 N/A
The test shall be asessed based on the following
standards
1. Diesel engines and generators according to ASME
PTC 17
2. Steam turbine and generator according to ASME
PTC 6.2
3. HRSG according to ASME PTC 4.4
4. Condensor according to ASME PTC 30.1
3
4
5
6
# Remarks
Jiyeh Plant consists of 4 x MAN 18V48/60B diesel engines running on HFO, 4 x WHRB and 1 MAN STG (Type
1
MARC DCC 2-C00) of capacity 6.3MW and all their auxiliaries
Zouk Plant consists of 10 x MAN 18V48/60B diesel engines running on HFO, 10 x WHRB and 1 MAN STG (Type
2
MARC DCC 4-C00) of capacity 15.76 MW and all their auxiliaries
3
4
5
6
Comments:
Prepared By: AFM

Issued By: YKM