You are on page 1of 1

RRE Innovations, Inc.

Bill of Materials

Project: MRT 7, Station No. 10, Mindanao Ave. Station - Sewage Treatment Plant
Location: Regalado Highway, Novaliches, Quezon City
Concessionaire: SMC Mass Rail Transit 7 Inc.
Subject:

PROJECT WORK SCHEDULES


For: S.T.P. PUMP CONTROL ROOM : CIVIL WORKS

MONTH 1 MONTH 2 MONTH3 MONTH 4 MONTH 5


CONTRACT WEIGHT NO. OF START
WORK DESCRIPTION END DATE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
AMOUNT % DAYS DATE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150
PRELIMINARIES
Mobilization / Demobilization 3
Temporary Facilities 3
I.
Progress Report 150
Equipment Deliveries 5

PPE / Coordination / Communication 150


PROCESS DESIGN & ENGINEERING
II. Engineer's Report 9
Detailed Drawing / As-built Plan 12
CIVIL WORKS (STP RC UG TANK)
Earthworks: Excavation, Backfill, & Leveling 4
Gravel bedding / Lean concreting 3
Dewatering 3
1st Lift Rebar Fab. & Install. (Base Slab) 5
1st Lift Rebar Fab. & Install. (Perimeter Walls) 6
1st Lift Rebar Fab. & Install. (Partition Walls) 3
Installation of Waterstopper 1
1st Lift Formworks 4
1st Lift Shuttering Supports & Braces 3
1st Lift Concrete Pouring 1
1st Lift Dismantling of Formworks 4
2nd Lift Rebar Fab. & Install. (Perimeter Walls) 5
2nd Lift Rebar Fab. & Install. (Partition Walls) 4
III.
2nd Lift Formworks 5
Block-outs & Sleeves 1
2nd Lift Shuttering Supports & Braces 4
2nd Lift Concrete Pouring 1
2nd Lift Dismantling of Formworks 4
3rd Lift Rebar Fab. & Install. (Beam) 4
3rd Lift Formworks (Beam & Slabs) 4
3rd Lift Centering & Staging 4
3rd Lift Rebar Fab. & Install. (Slabs) 7
Installation of Block-out for Manholes 2
3rd Lift Concrete Pouring 1
3rd Lift Dismantling of Formworks 4
Fabrication of Manhole Covers 1
Application of Cementitious Waterproofing Compound 3
CIVIL WORKS (STP PUMP CONTROL RM.)
Rebar Fab. & Install. (Columns) 3
Formworks (Columns) 3
Shuttering (Columns) 2
Rebar Fab. & Install. (Beams) 3
Formworks (Beams & Roof Slabs) 3
Centering & Staging (Beam & Roof Slabs) 2
IV.
Rebar Fab. & Install. (Roof Slabs) 3
Concrete pouring (Columns, Beams & Roof Slabs) 1
Dismantling of Formworks (Columns, Beams & Slabs) 3
Laying-out of CHB 3
Plastering of Masonry Wall 4
Installation of Louver Doors & Windows 2
Painting Works 3
MECHANICAL WORKS
V. Piping, Vavles, & Fittings / Consumables 49
Platforms / Supports / Metal Works 49
ELECTRICAL WORKS
VI. Rounging-ins, & Wiring / Consumables 41
Lighting, Outlets, & Switches 5
INSTRUMENTATION & CONTROL
Control Panel (Fabrication & Installation) 13
VII.
Automation Switches 5
Start-up / Dry-run 1
EQUIPMENT SUPPLY & INSTALLATION
2 units Root Blowers 5
2 units Transfer Pumps 4
2 units Decanter Pumps 4
1 unit Submersible Mixer 1
1 unit Retrun Activated Sludge Pump 2
VIII. 2 units Effluent Pumps 4
2 units Feed Pumps 3
2 sets Dosing Pumps w/ Chem. Tanks 3
1 set FRP Tank w/ Anoinic Elements 6
1 set FRP Tank w/ ACF 6
8 units Coarse Bubble Diffusers 3
16 units Fine Bubble Diffusers 3
TESTING & COMMISSIONING
Plant Start-Up 3
IX.
Testing & Commissioning 60
Operation & Maintenance Manual 3