Follow-up work program for Bole International Airport runway porous Asphalt overlay Project

Calender Days
Item
Activity Description Nov-08 Dec-08 Jan-09
No
28 29 30 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 Mix Design Submission

2 Mix Design Approval

3 Trial Section Paving

4
Trial Section Testing and Approval

5 Mobilization of Paving Machinery

6 Porous Asphalt Concrete Paving

7 Runway Marking

8 Cleaning, Clearing and Handover

CRBC Addis Engineering PLC Follow_up Work Programme


Follow-up work program for Bole International Airport runway porous Asphalt overlay Project

Item Dec-08 Jan-09


Activity Description
No
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 Mobilization of Paving Machinery

2 Spraying RC-70

3 Paving Porous Asphalt

4
Runway Marking

5 Cleaning, Clearing and Handover

6 Open to traffic

CRBC Addis Engineering PLC Follow_up Work Programme