Professional Documents
Culture Documents
Months --> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Weeks--> 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
# Activities
1 Basic Engineering
a Layout Preparation & Finalisation
b Approval: CCOE Approval/DM’s NOC/ EC Clearance, Factory License
c Layouts (Fuel Farm & Hydrant), P&IDs, GA Drawings for Civil/ Mechanical/ Electrical/
Instrumentation/integration etc for Tendering
d BOQ for Tendering
3 Engineering
a. Submission of GFC Drawings
b. Approval of GFC Drawings
4 Procurement
a Steel Plates for Tanks (Product + Fire Water & Structural Steel
b Pumps Motor Sets (Hydrant, Fire Water)
c Filteration Units
d Pipelines (Product & Fire).
e Motorized Valves and ROSOV
f Electrical Works Transformer, DG Sets and bulk Items
b Mechanical Work
· Tank (Product Tank [AG & UG] and Fire Water tanks)
d Electrical Work
1 Basic Engineering
a Layout Preparation & Finalisation
b Approval: CCOE Approval/DM’s NOC/ EC Clearance, Factory License
c Layouts (Fuel Farm & Hydrant), P&IDs, GA Drawings for Civil/ Mechanical/
Electrical/ Instrumentation/integration etc for Tendering
d BOQ for Tendering
3 Engineering
a. Submission of GFC Drawings
b. Approval of GFC Drawings
4 Procurement
a Long lead item (Pipes)
b DBB Valve, Pit Boxes, Pit Valve, Gate Valve etc.
c Short Lead Items (Flanges, Fittings)
d E&I Bulk Items
5 Civil Works
a Trench Marketing
b Excavation of Trench
c Pipeline Trench Sand Pre-Padding (300MM)
d Pipe Stringing and Welding
e Pipe Lowering in streatches
f Sand Post Padding (300MM)
g Trench Backfilling, Pit Box Fixing and Apron Construction
6 E&I Works
a Cable Pulling and Termination insiode Valve Chamber
b Installation, Testing and Commissioning of ESB System