Fill in all of the white cells with the necessary information.

Project Name ROB AT 68+680

Customer Name/Location PATEL INFRA / HISAR

Estimated Project Start Date 1-Mar-22

Estimated Project End Date 10-Apr-22

Project Manager Name Mr. R K Srivastava

Project Team Members, Task Groups & Stakeholders

Sr. No. Name & Designation Contact


1 Mr. R K Srivastava (GM technical)
2 Mr. Gaurav Sood (Manager Marketing)
3 Mr. J P Singh (Sr. GM)
4 Mr. Rakesh Sharma (PPC)
5 Mr. Sameer Goel (Site Engineer)
6 Mr. Gurnam (Contractor)
7
8
9
10
ROB AT 68+680

PATEL INFRA / HISAR

1-Mar-22 1-Mar-22

10-Apr-22 10-Apr-22

Mr. R K Srivastava

Holidays/Time Off Projects

Date Holiday
Planning
IMPORTANT NOTICE:
It is very important that tasks are entered with unique names. If task names are repeated, the data will not carry over correc
differently.
Task Owner must be selected from Drop Down list only, otherwise systems will not accept any entry

Project Task Information

Sr. NO. Project Task Estimated Start


Date
1 Assembly of S1 43 mtr LHS Span 1-Mar-22
2 Torquing of S1 43 mtr LHS Span 5-Mar-22
3 Launching of S1 43 mtr LHS Span 7-Mar-22
4 Bracing of S1 43 mtr LHS Span 9-Mar-22
5 Lowering of S1 43 mtr LHS Span 11-Mar-22
6 Assembly of S2 43 mtr RHS Span 5-Mar-22
7 Torquing of S2 43 mtr RHS Span 8-Mar-22
8 Launching of S2 43 mtr RHS Span 10-Mar-22
9 Bracing of S2 43 mtr RHS Span 12-Mar-22
10 Lowering of S2 43 mtr RHS Span 15-Mar-22
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
ted, the data will not carry over correctly. Make sure to name each task

cept any entry

mation

Estimated Task Owner


Completion Date (MUST USE DROP DOWN MENU)
4-Mar-22
6-Mar-22
8-Mar-22
10-Mar-22
12-Mar-22
7-Mar-22
9-Mar-22
11-Mar-22
13-Mar-22
16-Mar-22
Work Schedule Monitoring
GANTT CHART LEGEND
HOLIDAY/VACATION/NO WORK
PLANNED PROJECT WORK DAY
SCHEDULE FOR FABRICATION, SUPPLY & ERECTION
TASK COMPLETED
CONSTRUCTION OF EIGHT LANE VADODARA-KIM EXPRESSWAY (PHASE IA PKG 3)
BRIDGE OVER GAS PIPE LINE AT CH 309+074.653 COMPLETION STATUS LEGEND

TASK COMPLETED AHEAD OF SCHEDULE


TASK COMPLETED BEHIND SCHEDULE

Project Task Information WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12 WEEK 13 WEEK 14 WEEK 15

Estimated Actual 28-Feb-22 7-Mar-22 14-Mar-22 21-Mar-22 28-Mar-22 4-Apr-22 11-Apr-22 18-Apr-22 25-Apr-22 2-May-22 9-May-22 16-May-22 23-May-22 30-May-22 6-Jun-22
Sr. No. Estimated Actual Start
Project Task Completion Completion Comments
Start Date Date 28 1 2 3 4 5 7 8 9 10 11 12 14 15 16 17 18 19 21 22 23 24 25 26 28 29 30 31 1 2 4 5 6 7 8 9 11 12 13 14 15 16 18 19 20 21 22 23 25 26 27 28 29 30 2 3 4 5 6 7 9 10 11 12 13 14 16 17 18 19 20 21 23 24 25 26 27 28 30 31 1 2 3 4 6 7 8 9 10 11
Date Date
M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S M T W T F S

1 Assembly of S1 43 mtr LHS Span 1-Mar-22 4-Mar-22 X X X X


2 Torquing of S1 43 mtr LHS Span 5-Mar-22 6-Mar-22 X
3 Launching of S1 43 mtr LHS Span 7-Mar-22 8-Mar-22 X X
4 Bracing of S1 43 mtr LHS Span 9-Mar-22 10-Mar-22 X X
5 Lowering of S1 43 mtr LHS Span 11-Mar-22 12-Mar-22 X X
6 Assembly of S2 43 mtr RHS Span 5-Mar-22 7-Mar-22 X X
7 Torquing of S2 43 mtr RHS Span 8-Mar-22 9-Mar-22 X X
8 Launching of S2 43 mtr RHS Span 10-Mar-22 11-Mar-22 X X
9 Bracing of S2 43 mtr RHS Span 12-Mar-22 13-Mar-22 X
10 Lowering of S2 43 mtr RHS Span 15-Mar-22 16-Mar-22 X X
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Issue Log

Date Issue Responsible


Action Taken
Reporting

Running and Pending Task Status Overall Progress Status Total Time Left
10%
5%

Task is running behind


schedule
Task is behind schedule and Task complete
not started yet Total Time Consumed
Not started Yet
Task is running on time Total time left
Under Process
Task is scheduled for this
time frame

90% 95%
100%

Task Number Task Owner Task to be completed Task Status Due on On Going Status

1 Assembly of S1 43 mtr LHS Span NOT STARTED YET 4-Mar-22 Task is behind schedule and not started yet
2 Torquing of S1 43 mtr LHS Span NOT STARTED YET 6-Mar-22 Task is scheduled for this time frame
3 Launching of S1 43 mtr LHS Span NOT STARTED YET 8-Mar-22 Task is scheduled for this time frame
4 Bracing of S1 43 mtr LHS Span NOT STARTED YET 10-Mar-22 Task is scheduled for this time frame
5 Lowering of S1 43 mtr LHS Span NOT STARTED YET 12-Mar-22 Task is scheduled for this time frame
6 Assembly of S2 43 mtr RHS Span NOT STARTED YET 7-Mar-22 Task is scheduled for this time frame
7 Torquing of S2 43 mtr RHS Span NOT STARTED YET 9-Mar-22 Task is scheduled for this time frame
8 Launching of S2 43 mtr RHS Span NOT STARTED YET 11-Mar-22 Task is scheduled for this time frame
9 Bracing of S2 43 mtr RHS Span NOT STARTED YET 13-Mar-22 Task is scheduled for this time frame
10 Lowering of S2 43 mtr RHS Span NOT STARTED YET 16-Mar-22 Task is scheduled for this time frame
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30