Chainage Span LHS/RHS Fabrication Supply Assembly Torquing Launching Bracing Lowering

309 43 mtr LHS Done Done 04/Mar/22 06/Mar/22 07/Mar/22 10/Mar/22 12/Mar/22
309 43 mtr RHS Done Done 07/Mar/22 09/Mar/22 10/Mar/22 13/Mar/22 15/Mar/22
293 30 mtr LHS Done 07/Mar/22 09/Mar/22 11/Mar/22 13/Mar/22 15/Mar/22 17/Mar/22
293 30 mtr LHS Done 07/Mar/22 10/Mar/22 12/Mar/22 15/Mar/22 17/Mar/22 19/Mar/22
293 43 mtr LHS 12/Mar/22 17/Mar/22 21/Mar/22 24/Mar/22 26/Mar/22 29/Mar/22 31/Mar/22
293 30 mtr RHS 08/Mar/22 11/Mar/22 13/Mar/22 15/Mar/22 17/Mar/22 19/Mar/22 21/Mar/22
293 30 mtr RHS 08/Mar/22 11/Mar/22 13/Mar/22 15/Mar/22 17/Mar/22 19/Mar/22 21/Mar/22
293 43 mtr RHS 20/Mar/22 25/Mar/22 27/Mar/22 31/Mar/22 03/Apr/22 05/Apr/22 07/Apr/22