You are on page 1of 10

Handover Rep

Department Name SF Pro

Discipline Name E&

Handed Over by Ibrahim

Taken Over by Ali M

Date 23.11
Report
SF Projects

E&I

Ibrahim Khaleel

Ali Mufleh

23.11.2022
Rotaion Day Date Sr

Day 1 10/11/22
1
2
3
4
Day 2 11/11/22

1
2
3
4
Day 3 12/11/22

1
2
3
4
5
Day 4 13/11/22

1
2
3
Day 5 14/11/22

1
2
3

Day 6 15/11/22
1
2
3
Day 7 16/11/22

1
2
3
Day 8 17/11/22

1
2
3
4
Day 9 18/11/22

1
2
3
4
Day 10 19/11/22

1
2
3
Day 11 20/11/22

1
2
3
4
5
Day 12 21/11/22

1
2
3
4
Day 13 22/11/22

1
2
3
Day 14 23/11/22

1
2
3
Tasks / Activites

Testing of G22-01 is continue


Functionality test of FGS is ongoing
MOC #57 is published for Configure fault alarm as pre VONK C&E fire zone 01
MAR of Fire optic cable for 11kV power supply form DS2 to FOC Substation project have been reviewed and discussed with AO

Function test was completed for FGS (Zone 1 Substation and Zone 2 Wel pad).
MOC #49,50,51,52 and 57 completed
MOC#58 is published for Logic change on Intertrip A/B/C/D activation based on KBR engineering response on TQ MGP1-E18-A
An email sent to Firas regarding the alternative cables of non founded cables from the list you highlighted.

MOC#58 has been closed


G22-01 Off-Line Test has been completed
MOCs have been closed, scand and shared with team
Inspection for alternative cables at CPF1 warehouse with Firas for NODS project
Two RFIs have been signed at TPS disel tanks projects for Flame detectors and bimetal thermometers

Documents reviewed and comments on transmittal SSEP-SAA-EXPANSION-EAH-ANT-T-0149 and submitted for SAA project
Documents reviewed ( transmittal SSEP-SAA-EXPANSION-EAH-ANT-T-0152 ) and submitted as code A for SAA project
Document SSEP-SAA-20220002021-L22-00001_001 Expansion of existing Intergrated control and safety System submitted as c

Documents reviewed and comments on transmittal SSEP-SAA-EXPANSION-EAH-ANT-T-0154 and submitted for SAA project
E20-02 Well pad site visit
Study well head control panel vender document and compare it with P&ID for tomorrow instalation inspection
Asked FOC substaion telecom doc from CJI (Li) and FCC Vender document for PAGA system and fire alarm system to make sure
through FCC Telecom room)

Site visit to check the installation of generators and WHCP at E20-2 Well Pad
An email sent to Hasan-Almatrood about the WHCP at E20-2, the tags are not updated according to the last P&ID drawings.
Documents reviewed and comments on transmittal SSEP-SAA-EXPANSION-EAH-ANT-T-0155 and submitted for SAA project

Inspect and sign RFI # FOCP-SD1-CJI-TA-RFI-0003 for check the pre-embedded protecting conduit installation work for FAS, LA
Working on transmittal SSEP-SAA-EXPANSION-EAH-ANT-T-0161 for SAA project
Site visit to FCC main street ligting poles, some cables got cutted and stoled, report to Hasan Al-Matrood

Site visit to NODS project with Abdulla from Etlalat regarding the instruments cable route, red line mark up have been done to
Attend meeting with Jamshaid and BOC engineer Mr. Maithem regarding emerson bill of materials delay of delivery for NODS
Documents reviewed and comments on transmittal SSEP-SAA-EXPANSION-EAH-ANT-T-0161 and submitted for SAA project
Documents reviewed and comments on transmittal WIPP-CWT-DOC-AOS-T-0666 and submitted for WIP project

Attend meeting with Waleed and IT team lead Munqith to discuss how to review the telcome doc for SD project. Munqith will
working on transmittal WIPP-CWT-DOC-AOS-T-0692 for WIP project
Transmittal WIPP-CWT-DOC-AOS-T-0675 were recived from DCC to review
Search for DCS matreials with maintenace team at the warehouse, "backup'' in case the materials requested by emerson engin

:
working on transmittal WIPP-CWT-DOC-AOS-T-0692 Loop diagram for WIP project
An Email sent to project team & Mr Xu, ask them to conduct a meeting regarding Well pads Off- Line test. Responding to Mr. X
Discuss the Instrument materials data sheets with Aymen for SAA project. Aymen is the new instrument engineer and will help

working on transmittal WIPP-CWT-DOC-AOS-T-0692 Loop diagram for WIP project


Site visit to Well pad E20-2 and TPS area with Muhanned
Prepare PPT for Off-line test meeting and arrange all hard copy MOCs in one dossier
Sent meeting request Email on 23/11/2022 to Well pad project team
due to the difficulties in the path of instruments cable route at NODS project we need to identify the way of excavation from t

Documents reviewed and comments on transmittal WIPP-CWT-DOC-AOS-T-0692 and submitted as Code C for WIP project
Site survey at CPF1 NODS project to check the instruments cables route with ETLALAT engineer/ confrim which part will be un
another site survey needs, to check the area near the substaion and which cable tray will be used. Red line mark up will be sub
Revise a TQ for replacing semicondoctor Toxic gas detector by electro-chemical type sensor that sent by ETLALAT

Going with Firas to inspect the electrical and instrument cables for Well pads project at CPF1 Warehouse. We ask them to arra
Respond and agreed to a TQ regarding toxic gas detector that submitted by ETLALAT. They need update the approved data sh
Working on the PPT for tomorrow presentation and print out all the TQs for the Offline test.

Attended MC Inspection of Diesel tank area at TPS and wrote some punch list submitted to QA/QC Lead
Sent the presentation of the Off-line test by email to project team
Review and comment on transmittal WMIL-ALM-YAM-AOS-T-0041 for (Incinerator Project)
Status

Closed
Closed
Closed
Closed

Closed
Closed
Closed
Closed

Closed
Closed
Closed
Open
Closed

Closed
Closed
Closed

Closed
Closed
Closed
Closed

Closed
Closed
Closed

Closed
Closed
Closed

Closed
Closed
Closed
Closed

Closed

Open
Closed

Closed
Closed

Closed

Closed
ance team and Etlalat Company.

Closed
Open

Closed

Closed
Closed

Closed
Closed
Closed
Remarks

needs another search for previous cables (turn out that the cables Firas inspect not match the MTO)
Pending till receive Terniation and Cable list to confirem the MTO

m and Etlalat Company.

EHA need to confirm the alternative cable route entry

You might also like