You are on page 1of 3

PROJECT NAME : Supply and Install of Fiber Optic Structured Cabling for Existing Rosslare Access Control System

ontrol System Legends:


LOCATION : Km 22 E Service Rd, Cupang, Muntinlupa, 1771 Metro Manila Planning Delayed Target Date of Completion
SUBJECT : Construction Schedule / Project Timeline Ongoing Completed Stop Resume

CONSTRUCTION SCHEDULE
DURATION IN NUMBER OF DAYS
WORK WEEK 37 WORK WEEK 38 WORK WEEK 39 WORK WEEK 40 WORK WEEK 41 WORK WEEK 42 WORK WEEK 43 WORK WEEK 44 WORK WEEK 45
Item ACTIVITIES SEPTEMBER OCTOBER NOVEMBER
9 10 11 12 13 14 16 17 18 19 20 21 23 24 25 26 27 28 30 1 2 3 4 5 7 8 9 10 11 12 14 15 16 17 18 19 21 22 23 24 25 26 28 29 30 31 1 2 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54

I. GENERAL REQUIREMENTS
Meetings
STATUS:
WSO Training (Safety Requirement)
STATUS:
Mobilization
STATUS:
Delivery of Materials
STATUS:
Processing of Daily Permits
STATUS:
II. INSTALLATION OF FIBER OPTIC CABLE STRUCTURED CABLING SYSTEM
IDF 1 Area 6 Warehouse
1 ROUGHING INS INSTALLATION (A6 WH Vault to IDF 1)
STATUS:
2 CABLE PULLING OF UTP CAT6 DATA CABLES (A6 WH Vault to IDF 1)
STATUS:
3 ROUGHING INS INSTALLATION (IDF 1 TO A5 SECURITY ROOM)
STATUS:
4 CABLE PULLING OF FIBER OPTIC CABLES (IDF 1 TO A5 SECURITY ROOM)
STATUS:
5 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (TO ACS PANEL)
STATUS:
IDF 2 Area 6 Shipping
1 ROUGHING INS INSTALLATION (From Shipping, CCTV to IDF 2)
STATUS:
2 CABLE PULLING OF UTP CAT6 DATA CABLES (From Shipping, CCTV to IDF 2)
STATUS:
3 ROUGHING INS INSTALLATION (FROM IDF 2 TO A5 SECURITY ROOM)
STATUS:
4 CABLE PULLING OF FIBER OPTIC CABLES (FROM IDF 2 TO A5 SECURITY ROOM)
STATUS:
5 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (TO ACS PANEL)
STATUS:
IDF 3 Area 1 Backdoor
1 ROUGHING INS INSTALLATION (From A1 Backdoor to IDF 3)
STATUS:
2 CABLE PULLING OF UTP CAT6 DATA CABLES (From A1 Backdoor to IDF 3)
STATUS:
3 ROUGHING INS INSTALLATION (IDF 3 TO A5 SECURITY ROOM)
STATUS:
4 CABLE PULLING OF FIBER OPTIC CABLES (IDF 3 TO A5 SECURITY ROOM)
STATUS:
5 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (TO ACS PANEL)
STATUS:
IDF 4 Area 4
1 ROUGHING INS INSTALLATION (From A4 Lobby, Satellite Diebank, Kitting, CLF Entrance to IDF 4)
STATUS:
2 CABLE PULLING OF UTP CAT6 DATA CABLES (From A4 Lobby, Satellite Diebank, Kitting, CLF Entrance to IDF 4)
STATUS:
3 ROUGHING INS INSTALLATION (FROM IDF 4 TO A5 SECURITY ROOM)
STATUS:
4 CABLE PULLING OF FIBER OPTIC CABLES (IDF 4 TO A5 SECURITY ROOM)
STATUS:
5 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (TO ACS PANEL)
STATUS:
IDF 5 Area 5
1 ROUGHING INS INSTALLATION (From A5 Diebank, A4 Gowning, A5 Managers, EOL, A5 Gowning to IDF 5)
STATUS:
2 CABLE PULLING OF UTP CAT6 DATA CABLES (From A5 Diebank, A4 Gowning, A5 Managers, EOL, A5 Gowning to IDF 5)
STATUS:
3 ROUGHING INS INSTALLATION (FROM IDF 5 GOING TO A5 SECURITY ROOM)
STATUS:
4 CABLE PULLING OF FIBER OPTIC CABLES (IDF 5 TO A5 SECURITY ROOM)
STATUS:
5 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (TO ACS PANEL)
STATUS:
IDF 6 Area 5 Near CCTV Room
1 ROUGHING INS INSTALLATION (From A5 Garbage to IDF 6)
STATUS:
2 CABLE PULLING OF UTP CAT6 DATA CABLES (From A5 Garbage to IDF 6)
STATUS:
3 ROUGHING INS INSTALLATION (FROM IDF 6 GOING TO A5 SECURITY ROOM)
STATUS:
4 CABLE PULLING OF FIBER OPTIC CABLES (IDF 6 TO A5 SECURITY ROOM)
STATUS:
5 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (TO ACS PANEL)
STATUS:
IDF 7 A5 2nd Floor
1 ROUGHING INS INSTALLATION (A5 ACS Panels to IDF 7)
STATUS:
2 CABLE PULLING OF UTP CAT6 DATA CABLES (A5 ACS Panels to IDF 7)
STATUS:
3 ROUGHING INS INSTALLATION (From IDF 7 to A5 CCTV Room)
STATUS:
4 CABLE PULLING OF FIBER OPTIC CABLES (From IDF 7 to A5 CCTV Room)
STATUS:
5 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (From ACS Panel to IDF 7)
STATUS:

III. PROGRAMMING, TESTING, COMMISSIONING AND HAND-OVER

1 PROGRAMMING, COMMISSIONING & TESTING

2 END-USER TRAINING AND HAND-OVER

Prepared By: Submitted By: Noted By:

Engr. Jacqueline E. Lanot Engr. Edward Bryan L. Gañon


Project In Charge Engineer Sales Engineer BOM and Design Head

Engr. Lord Jerome R. Dojillo Karleen Ann P. Esclavosa


Note: BOM & Design Engineer Branch Manager
6 working days per week. (Sundays are restdays)
Initial Gantt Chart only.
PROJECT NAME : Supply and Install of Fiber Optic Structured Cabling for Existing Rosslare Access Control System Legends:
LOCATION : Special Economic Processing Zone, 119 North Science Avenue, Laguna Technopark, Biñan, 4024 Laguna Planning Delayed Date of Completion
SUBJECT : Construction Schedule / Project Timeline Ongoing Completed Stop

CONSTRUCTION SCHEDULE
DURATION IN NUMBER OF DAYS
Item ACTIVITIES WEEK 37 WEEK 38 WEEK 39 WEEK 40 WEEK 41
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

I. GENERAL REQUIREMENTS
Meetings
WSO Training (Safety Requirement)
Mobilization
Delivery of Materials
Processing of Daily Permits
II. INSTALLATION OF FIBER OPTIC CABLE STRUCTURED CABLING SYSTEM
IDF 1 New Shipping
1 ROUGHING INS INSTALLATION (From WIP Panel to IDF 1)

2 CABLE PULLING OF UTP CAT6 DATA CABLES (From WIP, North Ground and Old Shipping to IDF 1)

3 TERMINATION OF UTP CAT6 (FROM ACS PANEL TO IDF 1)


IDF 2 Area 6 South Ground
1 ROUGHING INS INSTALLATION (From IDF 2 to New CCTV Room)

2 CABLE PULLING OF UTP CAT6 DATA CABLES (South Ground to IDF 2)

3 CABLE PULLING OF FIBER OPTIC CABLES (From IDF 2 to New CCTV Room)

4 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (TO ACS PANEL TO IDF 2)
IDF 3 IFX
1 ROUGHING INS INSTALLATION (From North 1st Level to Hallway Near Test Hardware)

2 CABLE PULLING OF UTP CAT6 DATA CABLES (From North 1st level and IFX Server to IDF 3)

3 CABLE PULLING OF FIBER OPTIC CABLES (From IDF 3 to NewCCTV Room)

4 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (TO ACS PANEL TO IDF 3)
IDF 4 MLF EOL
1 ROUGHING INS INSTALLATION (From MLF Packing to MLF EOL)

2 ROUGHING INS INSTALLATION (From IDF 4 to SMD Hallway)

3 CABLE PULLING OF UTP CAT6 DATA CABLES (From MLF Packing, MLF EOL and Security Control to IDF 4)

4 CABLE PULLING OF FIBER OPTIC CABLES (From IDF 4 to New CCTV Room)

5 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (TO ACS PANEL TO IDF 4)
IDF 5 Diebank
1 ROUGHING INS INSTALLATION (From MLF Kitting to IDF 5)

2 CABLE PULLING OF UTP CAT6 DATA CABLES (From MLF Kitting, Diebank, FC EOL and MLF FOL to IDF 5 )

3 ROUGHING INS INSTALLATION (From IDF 5 to Hallway outside MLF Packing)

4 CABLE PULLING OF FIBER OPTIC CABLES (From IDF 5 to New CCTV Room)

5 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (TO ACS PANEL TO IDF 5)
IDF 6 Data Center
1 ROUGHING INS INSTALLATION (From Cavmems to IDF 6 Data Center)

2 CABLE PULLING OF UTP CAT6 DATA CABLES (From Cavmems and Data Center to IDF 6)

3 ROUGHING INS INSTALLATION (From IDF 6 to New CCTV Room)

4 CABLE PULLING OF FIBER OPTIC CABLES (From IDF 6 to New CCTV Room)

5 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (TO ACS PANEL TO IDF 6)
IDF 7 FGS
1 ROUGHING INS INSTALLATION (From FGS going to New CCTV Room)

2 CABLE PULLING OF UTP CAT6 DATA CABLES (From FGS Panel to IDF 7)

3 CABLE PULLING OF FIBER OPTIC CABLES (From IDF 7 to New CCTV Room)

4 TERMINATION OF FIBER OPTIC CABLE AND UTP CAT6 (TO ACS PANEL)

III. PROGRAMMING, TESTING, COMMISSIONING AND HAND-OVER

1 PROGRAMMING, COMMISSIONING & TESTING

2 END-USER TRAINING AND HAND-OVER

Prepared By: Submitted By: Noted By:

Engr. Jacqueline E. Lanot Engr. Edward Bryan L. Gañon


Engr. Rafael C. Hernandez Sales Engineer BOM and Design Head
Project In Charge Engineer
Engr. Lord Jerome R. Dojillo Karleen Ann P. Esclavosa
Note: BOM & Design Engineer Branch Manager
6 working days per week. (Sundays is restday)
Initial Gantt Chart only.