CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172
LOCATION Cable from Joint -bay to RTU 967 & 966 DISCIPLINE ELECTRICAL
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
Check Excavated material shall be deposited a minimum of 1 meter away from
1.7 the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
LOCATION Cable from Joint -bay to RTU 967 & 966 DISCIPLINE ELECTRICAL
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
LOCATION Cable from Joint -bay to RTU 967 & 966 DISCIPLINE ELECTRICAL
3.24 Check and record cable continuity and insulation resistance test after cable
laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable. cable tiles and
warning tape
only
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment Not applicable
here, as this
HV Cables pulling with winch operation shall be not more than maximum check sheet is
3.14 allowable tension in line with cable manufacturer recommendation.
for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
LOCATION Duct Bank X15 To RTU Station (DK962 & DK963) DISCIPLINE ELECTRICAL
CABLE TAG NUMBER DK960-ELP-0005
CABLE SIZE / TYPE 4C X25 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power Cable
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
LOCATION Duct Bank X15 To RTU Station (DK962 & DK963) DISCIPLINE ELECTRICAL
CABLE TAG NUMBER DK960-ELP-0005
CABLE SIZE / TYPE 4C X25 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power Cable
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
LOCATION Duct Bank X15 To RTU Station (DK962 & DK963) DISCIPLINE ELECTRICAL
CABLE TAG NUMBER DK960-ELP-0005
CABLE SIZE / TYPE 4C X25 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power Cable
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable. cable tiles and
warning tape
only
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment Not applicable
here, as this
HV Cables pulling with winch operation shall be not more than maximum check sheet is
3.14 allowable tension in line with cable manufacturer recommendation.
for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable Refer: 4172-2-
3.24 laying RFI-F-0578
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable. cable tiles and
warning tape
only
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment Not applicable
here, as this
HV Cables pulling with winch operation shall be not more than maximum check sheet is
3.14 allowable tension in line with cable manufacturer recommendation.
for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
2.2
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
Check duct bank location and dimensional check-up for the installed ducts along
2.5 the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
Page 46 of 134 GF-4172-QC-EI-FM-0005, Rev. 4
CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
Check segregation from power cable, control cable, IS & non IS cables shall be
3.20 provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
Check & ensure cable trench is clean and free from stones, debris & other
1.6 unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment
3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
Check end caps shall be provided at both the ends to prevent ingress of
3.23
moisture after cable laying.
3.24 Check and record cable continuity and insulation resistance test after cable
laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6 (Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 cable tiles and
applicable
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.
Not applicable
3.4 Check for any physical damage of cable here, as this
check sheet is
Check existing cable encountered in the trench shall be realigned to for the
3.5
accommodate the new cable. installation of
cable tiles and
3.6 Check and verify laying arrangement of cable. warning tape
only
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment
3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
Check end caps shall be provided at both the ends to prevent ingress of
3.23
moisture after cable laying.
3.24 Check and record cable continuity and insulation resistance test after cable
laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6 (Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable. cable tiles and
warning tape
only
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment Not applicable
here, as this
HV Cables pulling with winch operation shall be not more than maximum check sheet is
3.14 allowable tension in line with cable manufacturer recommendation.
for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable. cable tiles and
warning tape
only
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment Not applicable
here, as this
HV Cables pulling with winch operation shall be not more than maximum check sheet is
3.14 allowable tension in line with cable manufacturer recommendation.
for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
Check & ensure cable trench is clean and free from stones, debris & other
1.6 unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
3.12 or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
Check and confirm cable tag numbers are correct and provided every 5 meter
3.18 intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
Check end caps shall be provided at both the ends to prevent ingress of
3.23 moisture after cable laying.
3.24 Check and record cable continuity and insulation resistance test after cable
laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6 (Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
NAME Suresh P R
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
NAME Suresh P R
DATE
CABLE TAG NUMBER 36-EL-0046/10 & 36-ELP-0128/3, 36-EL-0016, 36-EL-0016/14, 36-EL-0045, 36-EL-0045/5, 36-EL-0046
& 36-EL-0046/5
CABLE SIZE / TYPE 4C x 16 SQMM/B2 , 2C+E x 4 SQMM/B3, 3C+E x 6 SQMM/B7, 2C+E x 6 SQMM/B3.
DRAWING NO. JCWF-2-64-0001-C
CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting Circuit Cables
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
2.2
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
Check duct bank location and dimensional check-up for the installed ducts along
2.5 the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
CABLE TAG NUMBER 36-EL-0046/10 & 36-ELP-0128/3, 36-EL-0016, 36-EL-0016/14, 36-EL-0045, 36-EL-0045/5, 36-EL-0046
& 36-EL-0046/5
CABLE SIZE / TYPE 4C x 16 SQMM/B2 , 2C+E x 4 SQMM/B3, 3C+E x 6 SQMM/B7, 2C+E x 6 SQMM/B3.
DRAWING NO. JCWF-2-64-0001-C
CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting Circuit Cables
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment
3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
Check segregation from power cable, control cable, IS & non IS cables shall be
3.20 provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
CABLE TAG NUMBER 36-EL-0046/10 & 36-ELP-0128/3, 36-EL-0016, 36-EL-0016/14, 36-EL-0045, 36-EL-0045/5, 36-EL-0046
& 36-EL-0046/5
CABLE SIZE / TYPE 4C x 16 SQMM/B2 , 2C+E x 4 SQMM/B3, 3C+E x 6 SQMM/B7, 2C+E x 6 SQMM/B3.
DRAWING NO. JCWF-2-64-0001-C
CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting Circuit Cables
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
3.24 Check
laying
and record cable continuity and insulation resistance test after cable
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6 (Red concrete for electrical and Green Concrete for instrument)
Check route marker installation on straight routes distances shall not exceeding
4.8 50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
NAME Suresh P R
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable. cable tiles and
warning tape
only
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment Not applicable
here, as this
HV Cables pulling with winch operation shall be not more than maximum check sheet is
3.14 allowable tension in line with cable manufacturer recommendation.
for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench fromJCWF Fence to RTU Stations (DK-
970,969,972 and DK-962,963,960,961)
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
2.2 completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable tiles and
cable.
warning tape
only
Page 97 of 134 GF-4172-QC-EI-FM-0005, Rev. 4
CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment
Not applicable
here, as this
3.14 HV Cables pulling with winch operation shall be not more than maximum check sheet is
allowable tension in line with cable manufacturer recommendation. for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench fromJCWF Fence to RTU Stations (DK-
970,969,972 and DK-962,963,960,961)
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)
Check route marker installation on straight routes distances shall not exceeding
4.8 50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench from JCWF Fence to DK960 Route as per
attached highlighted drawing
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 cable tiles and
applicable
warning tape
Check duct bank location and dimensional check-up for the installed ducts along only
2.5 the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable tiles and
cable.
warning tape
only
Page 100 of 134 GF-4172-QC-EI-FM-0005, Rev. 4
CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment
Not applicable
here, as this
3.14 HV Cables pulling with winch operation shall be not more than maximum check sheet is
allowable tension in line with cable manufacturer recommendation. for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only
3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
Check and confirm cable tag numbers are correct and provided every 5 meter
3.18 intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
Check segregation from power cable, control cable, IS & non IS cables shall be
3.20 provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench from JCWF Fence to DK960 Route as per
attached highlighted drawing
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24
laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)
Check route marker installation on straight routes distances shall not exceeding
4.8 50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable Refer, 4172-2-RFI-
3.24 laying F-0468
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
36-EL-0013 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0015 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0017 ((3C+E) x 6
CABLE TAG NUMBER Sq. mm. / B9), 36-EL-0018 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0034 ((2C+E) x 6 Sq. mm. / B3), 36-EL-
0035 ((2C+E) x 6 Sq. mm. / B6), 36-ELP-0119 ((4C+E) x 10 Sq. mm. / B6), 36-ELP-0128 ((2C+E) x 6 Sq.
mm. / B3), 36-ELP-0129 ((2C+E) x 6 Sq. mm. / B2), 36-ELP-0129/2 ((2C+E) x 4 Sq. mm. / B3) 36-ELP-
CABLE SIZE / TYPE 0147 ((2C+E) x 6 Sq. mm. / B3), 36-EL-0037 ((2C+E) x 6 Sq. mm. / B3) & 36-EL-0038 ((2C+E) x 6 Sq.
mm. / B3)
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
Check duct bank location and dimensional check-up for the installed ducts along
2.5 the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
36-EL-0013 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0015 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0017 ((3C+E) x 6
CABLE TAG NUMBER Sq. mm. / B9), 36-EL-0018 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0034 ((2C+E) x 6 Sq. mm. / B3), 36-EL-
0035 ((2C+E) x 6 Sq. mm. / B6), 36-ELP-0119 ((4C+E) x 10 Sq. mm. / B6), 36-ELP-0128 ((2C+E) x 6 Sq.
mm. / B3), 36-ELP-0129 ((2C+E) x 6 Sq. mm. / B2), 36-ELP-0129/2 ((2C+E) x 4 Sq. mm. / B3) 36-ELP-
CABLE SIZE / TYPE 0147 ((2C+E) x 6 Sq. mm. / B3), 36-EL-0037 ((2C+E) x 6 Sq. mm. / B3) & 36-EL-0038 ((2C+E) x 6 Sq.
mm. / B3)
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
3.12 or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
36-EL-0013 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0015 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0017 ((3C+E) x 6
CABLE TAG NUMBER Sq. mm. / B9), 36-EL-0018 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0034 ((2C+E) x 6 Sq. mm. / B3), 36-EL-
0035 ((2C+E) x 6 Sq. mm. / B6), 36-ELP-0119 ((4C+E) x 10 Sq. mm. / B6), 36-ELP-0128 ((2C+E) x 6 Sq.
mm. / B3), 36-ELP-0129 ((2C+E) x 6 Sq. mm. / B2), 36-ELP-0129/2 ((2C+E) x 4 Sq. mm. / B3) 36-ELP-
CABLE SIZE / TYPE 0147 ((2C+E) x 6 Sq. mm. / B3), 36-EL-0037 ((2C+E) x 6 Sq. mm. / B3) & 36-EL-0038 ((2C+E) x 6 Sq.
mm. / B3)
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
3.24 Check and record cable continuity and insulation resistance test after cable
laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
36-EL-0013 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0015 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0017 ((3C+E) x 6
CABLE TAG NUMBER Sq. mm. / B9), 36-EL-0018 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0034 ((2C+E) x 6 Sq. mm. / B3), 36-EL-
0035 ((2C+E) x 6 Sq. mm. / B6), 36-ELP-0119 ((4C+E) x 10 Sq. mm. / B6), 36-ELP-0128 ((2C+E) x 6 Sq.
mm. / B3), 36-ELP-0129 ((2C+E) x 6 Sq. mm. / B2), 36-ELP-0129/2 ((2C+E) x 4 Sq. mm. / B3) 36-ELP-
CABLE SIZE / TYPE 0147 ((2C+E) x 6 Sq. mm. / B3), 36-EL-0037 ((2C+E) x 6 Sq. mm. / B3) & 36-EL-0038 ((2C+E) x 6 Sq.
mm. / B3)
SIGNATURE
DATE
APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench at DK971 Wellhead area (Inside) as per
attached highlighted drawing
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 cable tiles and
applicable
warning tape
Check duct bank location and dimensional check-up for the installed ducts along only
2.5 the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable tiles and
cable.
warning tape
only
Page 119 of 134 GF-4172-QC-EI-FM-0005, Rev. 4
CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment
Not applicable
here, as this
3.14 HV Cables pulling with winch operation shall be not more than maximum check sheet is
allowable tension in line with cable manufacturer recommendation. for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only
3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
Check and confirm cable tag numbers are correct and provided every 5 meter
3.18 intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
Check segregation from power cable, control cable, IS & non IS cables shall be
3.20 provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench at DK971 Wellhead area (Inside) as per
attached highlighted drawing
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24
laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)
Check route marker installation on straight routes distances shall not exceeding
4.8 50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
Check & ensure cable trench is clean and free from stones, debris & other
1.6 unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4
applicable
Check duct bank location and dimensional check-up for the installed ducts along
2.5 the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment
3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
Check and confirm cable tag numbers are correct and provided every 5 meter
3.18 intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
Check segregation from power cable, control cable, IS & non IS cables shall be
3.20 provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24
laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)
Check route marker installation on straight routes distances shall not exceeding
4.8 50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
Check & ensure cable trench is clean and free from stones, debris & other
1.6
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
3.12 or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
Check end caps shall be provided at both the ends to prevent ingress of
3.23
moisture after cable laying.
3.24 Check and record cable continuity and insulation resistance test after cable Refer 4172-2-
laying RFI-F-0388
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6 (Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
DATE
CABLE TAG NUMBER DK970 -ELP-102 (4C x35 Sq. mm. / B2), DK970 -ELP-103 ( 2C x 2.5 Sq. mm. / B3), DK970 -EL-101
((2C+E) x 4 Sq. mm. / B3), DK970 -EL-101/1 ((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/2
((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/7 ((2C+E) x 2.5 Sq. mm. / B3 ) & DK970 -ELP-008 (2C x 6
CABLE SIZE / TYPE Sq. mm. / B9.)
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
Check & ensure cable trench is clean and free from stones, debris & other
1.6 unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
Check duct bank location and dimensional check-up for the installed ducts along
2.5 the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.
Page 128 of 134 GF-4172-QC-EI-FM-0005, Rev. 4
CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172
CABLE TAG NUMBER DK970 -ELP-102 (4C x35 Sq. mm. / B2), DK970 -ELP-103 ( 2C x 2.5 Sq. mm. / B3), DK970 -EL-101
((2C+E) x 4 Sq. mm. / B3), DK970 -EL-101/1 ((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/2
((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/7 ((2C+E) x 2.5 Sq. mm. / B3 ) & DK970 -ELP-008 (2C x 6
CABLE SIZE / TYPE Sq. mm. / B9.)
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
3.12 or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
Check and confirm cable tag numbers are correct and provided every 5 meter
3.18 intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
Check segregation from power cable, control cable, IS & non IS cables shall be
3.20 provided properly.
CABLE TAG NUMBER DK970 -ELP-102 (4C x35 Sq. mm. / B2), DK970 -ELP-103 ( 2C x 2.5 Sq. mm. / B3), DK970 -EL-101
((2C+E) x 4 Sq. mm. / B3), DK970 -EL-101/1 ((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/2
((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/7 ((2C+E) x 2.5 Sq. mm. / B3 ) & DK970 -ELP-008 (2C x 6
CABLE SIZE / TYPE Sq. mm. / B9.)
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
CABLE TAG NUMBER DK970 -ELP-102 (4C x35 Sq. mm. / B2), DK970 -ELP-103 ( 2C x 2.5 Sq. mm. / B3), DK970 -EL-101
((2C+E) x 4 Sq. mm. / B3), DK970 -EL-101/1 ((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/2
((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/7 ((2C+E) x 2.5 Sq. mm. / B3 ) & DK970 -ELP-008 (2C x 6
CABLE SIZE / TYPE Sq. mm. / B9.)
DATE
CABLE TAG NUMBER DK965-ELP-015, DK965-ELP-002, DK965-ELP-003, DK965-EL-101, DK965-EL-101/1, DK965-EL-101/2 &
DK965-ELP-008
DK960-ELP-006 (2C x 6 Sq. mm. / B9), DK960-ELP-007 (2C x 6 Sq. mm. / B9),
DK960-EL-001 ((2C+E) x 4 Sq. mm. / B3), DK960-EL-001/1 ((3C+E) x 2.5 Sq. mm. / B3),
CABLE SIZE / TYPE DK960-EL-001/2 ((3C+E) x 2.5 Sq. mm. / B3), DK960--ELP-011 (2C x 6 Sq. mm. / B9) &
DK960--ELP-012(2C x 6 Sq. mm. / B9)
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.
3.4 Check for any physical damage of cable
CABLE TAG NUMBER DK965-ELP-015, DK965-ELP-002, DK965-ELP-003, DK965-EL-101, DK965-EL-101/1, DK965-EL-101/2 &
DK965-ELP-008
DK960-ELP-006 (2C x 6 Sq. mm. / B9), DK960-ELP-007 (2C x 6 Sq. mm. / B9),
DK960-EL-001 ((2C+E) x 4 Sq. mm. / B3), DK960-EL-001/1 ((3C+E) x 2.5 Sq. mm. / B3),
CABLE SIZE / TYPE DK960-EL-001/2 ((3C+E) x 2.5 Sq. mm. / B3), DK960--ELP-011 (2C x 6 Sq. mm. / B9) &
DK960--ELP-012(2C x 6 Sq. mm. / B9)
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
3.12 or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
Check end caps shall be provided at both the ends to prevent ingress of
3.23 moisture after cable laying.
CABLE TAG NUMBER DK965-ELP-015, DK965-ELP-002, DK965-ELP-003, DK965-EL-101, DK965-EL-101/1, DK965-EL-101/2 &
DK965-ELP-008
DK960-ELP-006 (2C x 6 Sq. mm. / B9), DK960-ELP-007 (2C x 6 Sq. mm. / B9),
DK960-EL-001 ((2C+E) x 4 Sq. mm. / B3), DK960-EL-001/1 ((3C+E) x 2.5 Sq. mm. / B3),
CABLE SIZE / TYPE DK960-EL-001/2 ((3C+E) x 2.5 Sq. mm. / B3), DK960--ELP-011 (2C x 6 Sq. mm. / B9) &
DK960--ELP-012(2C x 6 Sq. mm. / B9)
3.24 Check
laying
and record cable continuity and insulation resistance test after cable
4.2 Check and ensure cable duct banks have been sealed properly on both ends
4.3 Check and ensure cable protection tiles are provided
Check colored concrete are provided along the cable route in paved area
4.6 (Red concrete for electrical and Green Concrete for instrument)
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :