You are on page 1of 134

CHECKLIST FOR UNDERGROUND CABLE

LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0388 SYSTEM DK965-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK965-201-01

LOCATION Cable from Joint -bay to RTU 967 & 966 DISCIPLINE ELECTRICAL

CABLE TAG NUMBER DK965-ELP-017/1, DK965-ELP-017/2, DK965-ELP-016/1, DK965-ELP-016/2, DK967-ELP-0001,


DK967-EL-101/7, 36-EE-0521 & 36-EE-0522
CABLE SIZE / TYPE 4C X185 SQMM, 4C X70 SQMM, (2C+E) X 2.5 SQMM,1C X 70SQMM
DRAWING NO. 4172-WLHD-2-64-0002
CABLE SCHEDULE 4172-WLHDT-2-37-0001
APPLICATION / SERVICE LV POWER , LIGHTING AND SMALL POWER & EARTHING CABLES

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

1.3 Check provision of sufficient mechanical protection to existing underground /


above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
Check Excavated material shall be deposited a minimum of 1 meter away from
1.7 the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 1 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0388 SYSTEM DK965-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK965-201-01

LOCATION Cable from Joint -bay to RTU 967 & 966 DISCIPLINE ELECTRICAL

CABLE TAG NUMBER DK965-ELP-017/1, DK965-ELP-017/2, DK965-ELP-016/1, DK965-ELP-016/2, DK967-ELP-0001,


DK967-EL-101/7, 36-EE-0521 & 36-EE-0522
CABLE SIZE / TYPE 4C X185 SQMM, 4C X70 SQMM, (2C+E) X 2.5 SQMM,1C X 70SQMM
DRAWING NO. 4172-WLHD-2-64-0002
CABLE SCHEDULE 4172-WLHDT-2-37-0001
APPLICATION / SERVICE LV POWER , LIGHTING AND SMALL POWER & EARTHING CABLES

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.4 Check for any physical damage of cable

3.5 Check existing cable encountered in the trench shall be realigned to


accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment

3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 2 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0388 SYSTEM DK965-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK965-201-01

LOCATION Cable from Joint -bay to RTU 967 & 966 DISCIPLINE ELECTRICAL

CABLE TAG NUMBER DK965-ELP-017/1, DK965-ELP-017/2, DK965-ELP-016/1, DK965-ELP-016/2, DK967-ELP-0001,


DK967-EL-101/7, 36-EE-0521 & 36-EE-0522
CABLE SIZE / TYPE 4C X185 SQMM, 4C X70 SQMM, (2C+E) X 2.5 SQMM,1C X 70SQMM
DRAWING NO. 4172-WLHD-2-64-0002
CABLE SCHEDULE 4172-WLHDT-2-37-0001
APPLICATION / SERVICE LV POWER , LIGHTING AND SMALL POWER & EARTHING CABLES

SI NO DESCRIPTION OK NOT N/A REMARKS


OK
Check end caps shall be provided at both the ends to prevent ingress of
3.23 moisture after cable laying.

3.24 Check and record cable continuity and insulation resistance test after cable
laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 3 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0417 SYSTEM DK964-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION DK964 To RTU964 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK968-ELP-118
CABLE SIZE / TYPE 2CX4 SQMM/B9
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.A
APPLICATION / SERVICE Power Cable for Coriolis Flowmeter

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 4 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0417 SYSTEM DK964-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION DK964 To RTU964 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK968-ELP-118
CABLE SIZE / TYPE 2CX4 SQMM/B9
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.A
APPLICATION / SERVICE Power Cable for Coriolis Flowmeter

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 5 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0417 SYSTEM DK964-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION DK964 To RTU964 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK968-ELP-118
CABLE SIZE / TYPE 2CX4 SQMM/B9
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.A
APPLICATION / SERVICE Power Cable for Coriolis Flowmeter

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 6 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0424 SYSTEM DK965-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK965-201-01

LOCATION RTU964 To RTU968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK965-ELP-018, 36-EE-0521, 36-EE-0522
CABLE SIZE / TYPE 4C X70 SQMM/B2 & 1C X 70SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.A
APPLICATION / SERVICE LV Power and Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 7 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0424 SYSTEM DK965-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK965-201-01

LOCATION RTU964 To RTU968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK965-ELP-018, 36-EE-0521, 36-EE-0522
CABLE SIZE / TYPE 4C X70 SQMM/B2 & 1C X 70SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.A
APPLICATION / SERVICE LV Power and Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 8 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0424 SYSTEM DK965-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK965-201-01

LOCATION RTU964 To RTU968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK965-ELP-018, 36-EE-0521, 36-EE-0522
CABLE SIZE / TYPE 4C X70 SQMM/B2 & 1C X 70SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.A
APPLICATION / SERVICE LV Power and Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 9 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0416 SYSTEM DK961-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK961-201-01

LOCATION DK961 Wellhead To RTU961 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK960-EL-001/8, DK961-EE-010, DK961-EE-011
CABLE SIZE / TYPE 4C X70 SQMM/B3 & 1C X 70SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power and Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 10 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0416 SYSTEM DK961-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK961-201-01

LOCATION DK961 Wellhead To RTU961 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK960-EL-001/8, DK961-EE-010, DK961-EE-011
CABLE SIZE / TYPE 4C X70 SQMM/B3 & 1C X 70SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power and Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 11 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0416 SYSTEM DK961-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK961-201-01

LOCATION DK961 Wellhead To RTU961 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK960-EL-001/8, DK961-EE-010, DK961-EE-011
CABLE SIZE / TYPE 4C X70 SQMM/B3 & 1C X 70SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power and Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 12 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0430 SYSTEM DK960-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-201-01

LOCATION JCWF Fence Area To RTU960 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-ELP-0048 & DK960-ELP-005
CABLE SIZE / TYPE 4C X50 SQMM/B2 & 4C X25 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power and Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 13 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0430 SYSTEM DK960-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-201-01

LOCATION JCWF Fence Area To RTU960 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-ELP-0048 & DK960-ELP-005
CABLE SIZE / TYPE 4C X50 SQMM/B2 & 4C X25 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power and Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 14 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0430 SYSTEM DK960-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-201-01

LOCATION JCWF Fence Area To RTU960 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-ELP-0048 & DK960-ELP-005
CABLE SIZE / TYPE 4C X50 SQMM/B2 & 4C X25 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power and Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 15 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0442 SYSTEM JCWF-204


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-204-01

LOCATION Duct Bank 13 To 36-JB-003 (Wellhead Main JB) DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-ELP-0045-1 & 36-ELP-0045-2
CABLE SIZE / TYPE 4C X185 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0001, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 16 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0442 SYSTEM JCWF-204


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-204-01

LOCATION Duct Bank 13 To 36-JB-003 (Wellhead Main JB) DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-ELP-0045-1 & 36-ELP-0045-2
CABLE SIZE / TYPE 4C X185 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0001, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 17 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0442 SYSTEM JCWF-204


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-204-01

LOCATION Duct Bank 13 To 36-JB-003 (Wellhead Main JB) DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-ELP-0045-1 & 36-ELP-0045-2
CABLE SIZE / TYPE 4C X185 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0001, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 18 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0440 SYSTEM DK960-204


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-204-01

LOCATION RTU964 To CR32 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench from RTU964 To CR32

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground / Not applicable


1.3 here, as this
above ground utilities crossing the excavated cable route.
check sheet is
1.4 Check cable trench depth and width as per AFC drawing. for the
installation of
cable tiles and
1.5 Check cable trench bottom is flat and sand bedding is correct warning tape
only
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable. cable tiles and
warning tape
only

Page 19 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0440 SYSTEM DK960-204


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-204-01

LOCATION RTU964 To CR32 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1 Not applicable
here, as this
APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench from RTU964 To CR32 check sheet is
for the
NOT installation of
SI NO DESCRIPTION OK OK N/A REMARKS
cable tiles and
warning tape
3.4 Check for any physical damage of cable only

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment Not applicable
here, as this
HV Cables pulling with winch operation shall be not more than maximum check sheet is
3.14 allowable tension in line with cable manufacturer recommendation.
for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 20 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE Not applicable
here, as this
LAYING WORKS check sheet is
for the
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS installation of
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT cable
NO.: tiles
4172and
warning tape
only
RFI NO. 4172-2-RFI-F-0440 SYSTEM DK960-204
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-204-01

LOCATION RTU964 To CR32 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench from RTU964 To CR32

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 21 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0439 SYSTEM DK968-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK968-201-01

LOCATION Dk968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK968-ELP-0001 & DK968-EL-101/7
CABLE SIZE / TYPE 4C X70 SQMM/B2 & (2C+E)X2.5 SQMM/B3
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 22 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0439 SYSTEM DK968-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK968-201-01

LOCATION Dk968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK968-ELP-0001 & DK968-EL-101/7
CABLE SIZE / TYPE 4C X70 SQMM/B2 & (2C+E)X2.5 SQMM/B3
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 23 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0439 SYSTEM DK968-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK968-201-01

LOCATION Dk968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK968-ELP-0001 & DK968-EL-101/7
CABLE SIZE / TYPE 4C X70 SQMM/B2 & (2C+E)X2.5 SQMM/B3
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 24 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0441 SYSTEM DK962-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK962-201-01

LOCATION Duct Bank X15 To RTU Station (DK962 & DK963) DISCIPLINE ELECTRICAL
CABLE TAG NUMBER DK960-ELP-0005
CABLE SIZE / TYPE 4C X25 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power Cable

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 25 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0441 SYSTEM DK962-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK962-201-01

LOCATION Duct Bank X15 To RTU Station (DK962 & DK963) DISCIPLINE ELECTRICAL
CABLE TAG NUMBER DK960-ELP-0005
CABLE SIZE / TYPE 4C X25 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power Cable

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 26 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0441 SYSTEM DK962-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK962-201-01

LOCATION Duct Bank X15 To RTU Station (DK962 & DK963) DISCIPLINE ELECTRICAL
CABLE TAG NUMBER DK960-ELP-0005
CABLE SIZE / TYPE 4C X25 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power Cable

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 27 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0444 SYSTEM DK968-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK968-201-02

LOCATION Inside DK968 Wellhead DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK968-EE-001 & DK968-EE-002
CABLE SIZE / TYPE 1C X 70 SQMM/E
DRAWING NO. DK968--2-64-0002-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 28 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0444 SYSTEM DK968-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK968-201-02

LOCATION Inside DK968 Wellhead DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK968-EE-001 & DK968-EE-002
CABLE SIZE / TYPE 1C X 70 SQMM/E
DRAWING NO. DK968--2-64-0002-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 29 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0444 SYSTEM DK968-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK968-201-02

LOCATION Inside DK968 Wellhead DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK968-EE-001 & DK968-EE-002
CABLE SIZE / TYPE 1C X 70 SQMM/E
DRAWING NO. DK968--2-64-0002-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 30 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0444 SYSTEM DK968-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK968-201-02

LOCATION Inside DK968 Wellhead DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. DK968--2-64-0002-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cable for Field JB/instruments

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground / Not applicable


1.3 here, as this
above ground utilities crossing the excavated cable route.
check sheet is
1.4 Check cable trench depth and width as per AFC drawing. for the
installation of
cable tiles and
1.5 Check cable trench bottom is flat and sand bedding is correct warning tape
only
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable. cable tiles and
warning tape
only

Page 31 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0444 SYSTEM DK968-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK968-201-02

LOCATION Inside DK968 Wellhead DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. DK968--2-64-0002-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1 Not applicable
here, as this
APPLICATION / SERVICE Earthing Cable for Field JB/instruments check sheet is
for the
NOT installation of
SI NO DESCRIPTION OK OK N/A REMARKS
cable tiles and
warning tape
3.4 Check for any physical damage of cable only

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment Not applicable
here, as this
HV Cables pulling with winch operation shall be not more than maximum check sheet is
3.14 allowable tension in line with cable manufacturer recommendation.
for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 32 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE Not applicable
here, as this
LAYING WORKS check sheet is
for the
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS installation of
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT cable
NO.: tiles
4172and
warning tape
only
RFI NO. 4172-2-RFI-F-0444 SYSTEM DK968-201
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK968-201-02

LOCATION Inside DK968 Wellhead DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. DK968--2-64-0002-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cable for Field JB/instruments

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 33 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0578 SYSTEM DK970-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK970-201-01

LOCATION Dk968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK970-ELP-102 & DK970-EL-101/7
CABLE SIZE / TYPE 4C X35 SQMM/B2 & (2C+E)X2.5 SQMM/B3
DRAWING NO. 4172-WLHD-2-64-0002, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001,
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 34 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0578 SYSTEM DK970-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK970-201-01

LOCATION Dk968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK970-ELP-102 & DK970-EL-101/7
CABLE SIZE / TYPE 4C X35 SQMM/B2 & (2C+E)X2.5 SQMM/B3
DRAWING NO. 4172-WLHD-2-64-0002, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001,
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 35 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0578 SYSTEM DK970-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK970-201-01

LOCATION Dk968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK970-ELP-102 & DK970-EL-101/7
CABLE SIZE / TYPE 4C X35 SQMM/B2 & (2C+E)X2.5 SQMM/B3
DRAWING NO. 4172-WLHD-2-64-0002, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001,
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable Refer: 4172-2-
3.24 laying RFI-F-0578

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 36 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0452 SYSTEM DK964-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION Dk964 wellhead DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK964-ELP-102 & DK964-EL-101/7
CABLE SIZE / TYPE 4C X35 SQMM/B2 & (2C+E)X2.5 SQMM/B3
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 37 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0452 SYSTEM DK964-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION Dk964 wellhead DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK964-ELP-102 & DK964-EL-101/7
CABLE SIZE / TYPE 4C X35 SQMM/B2 & (2C+E)X2.5 SQMM/B3
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 38 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0452 SYSTEM DK964-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION Dk964 wellhead DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK964-ELP-102 & DK964-EL-101/7
CABLE SIZE / TYPE 4C X35 SQMM/B2 & (2C+E)X2.5 SQMM/B3
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 39 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0454 SYSTEM DK964-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION RTU968 To RTU964 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench from RTU968 To RTU964

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground / Not applicable


1.3 here, as this
above ground utilities crossing the excavated cable route.
check sheet is
1.4 Check cable trench depth and width as per AFC drawing. for the
installation of
cable tiles and
1.5 Check cable trench bottom is flat and sand bedding is correct warning tape
only
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable. cable tiles and
warning tape
only

Page 40 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0454 SYSTEM DK964-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION RTU968 To RTU964 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1 Not applicable
here, as this
APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench from RTU968 To RTU964 check sheet is
for the
NOT installation of
SI NO DESCRIPTION OK OK N/A REMARKS
cable tiles and
warning tape
3.4 Check for any physical damage of cable only

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment Not applicable
here, as this
HV Cables pulling with winch operation shall be not more than maximum check sheet is
3.14 allowable tension in line with cable manufacturer recommendation.
for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 41 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE Not applicable
here, as this
LAYING WORKS check sheet is
for the
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS installation of
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT cable
NO.: tiles
4172and
warning tape
only
RFI NO. 4172-2-RFI-F-0454 SYSTEM DK964-201
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION RTU968 To RTU964 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench from RTU968 To RTU964

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 42 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0461 SYSTEM JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-205-02

LOCATION JCWF SubStation Area DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-EL-0039/4 & 36-EL-0040/4
CABLE SIZE / TYPE 4C X10 SQMM/B2
DRAWING NO. JCWF-2-67-0002-B
CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting Circuit

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 43 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0461 SYSTEM JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-205-02

LOCATION JCWF SubStation Area DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-EL-0039/4 & 36-EL-0040/4
CABLE SIZE / TYPE 4C X10 SQMM/B2
DRAWING NO. JCWF-2-67-0002-B
CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting Circuit

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 44 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0461 SYSTEM JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-205-02

LOCATION JCWF SubStation Area DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-EL-0039/4 & 36-EL-0040/4
CABLE SIZE / TYPE 4C X10 SQMM/B2
DRAWING NO. JCWF-2-67-0002-B
CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting Circuit

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Shanif Abdulla Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 45 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0459 SYSTEM DK969-201 / DK970-201 /


DK971-201
DK969-201-02 / DK970-201-01 /
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION RTU969 To Dk969, RTU969 To RTU970, RTU971, DISCIPLINE ELECTRICAL


RTU972
CABLE TAG NUMBER DK969-ELP-109, DK969-ELP-110, DK969-ELP-111, DK964-EL-101/7 & DK969-ELP-122
CABLE SIZE / TYPE 4C X 120 SQMM/B2, 4C X 95 SQMM/B2, 4C X 35 SQMM/B2, 2C X 4 SQMM/B9
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3 above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
2.2
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
Check duct bank location and dimensional check-up for the installed ducts along
2.5 the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
Page 46 of 134 GF-4172-QC-EI-FM-0005, Rev. 4
CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0459 SYSTEM DK969-201 / DK970-201 /


DK971-201
DK969-201-02 / DK970-201-01 /
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION RTU969 To Dk969, RTU969 To RTU970, RTU971, DISCIPLINE ELECTRICAL


RTU972
CABLE TAG NUMBER DK969-ELP-109, DK969-ELP-110, DK969-ELP-111, DK964-EL-101/7 & DK969-ELP-122
CABLE SIZE / TYPE 4C X 120 SQMM/B2, 4C X 95 SQMM/B2, 4C X 35 SQMM/B2, 2C X 4 SQMM/B9
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment

3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

Check segregation from power cable, control cable, IS & non IS cables shall be
3.20 provided properly.

3.21 Confirm the bending radius of cables correct

Page 47 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0459 SYSTEM DK969-201 / DK970-201 /


DK971-201
DK969-201-02 / DK970-201-01 /
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION RTU969 To Dk969, RTU969 To RTU970, RTU971, DISCIPLINE ELECTRICAL


RTU972
CABLE TAG NUMBER DK969-ELP-109, DK969-ELP-110, DK969-ELP-111, DK964-EL-101/7 & DK969-ELP-122
CABLE SIZE / TYPE 4C X 120 SQMM/B2, 4C X 95 SQMM/B2, 4C X 35 SQMM/B2, 2C X 4 SQMM/B9
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

Page 48 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0459 SYSTEM DK969-201 / DK970-201 /


DK971-201
DK969-201-02 / DK970-201-01 /
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION RTU969 To Dk969, RTU969 To RTU970, RTU971, DISCIPLINE ELECTRICAL


RTU972
CABLE TAG NUMBER DK969-ELP-109, DK969-ELP-110, DK969-ELP-111, DK964-EL-101/7 & DK969-ELP-122
CABLE SIZE / TYPE 4C X 120 SQMM/B2, 4C X 95 SQMM/B2, 4C X 35 SQMM/B2, 2C X 4 SQMM/B9
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

DATE

Page 49 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0464 SYSTEM DK964-201

REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION RTU964 (Inside) DISCIPLINE ELECTRICAL

DK964-ELP-101,DK964-ELP-102, DK964-ELP-103, DK964-EL-101/1, DK964-EL-101/2, DK964-EL-


CABLE TAG NUMBER 101/7, DK964-ELP-118, DK964-ELP-014
CABLE SIZE / TYPE 4C X 10 SQMM/B3, 4C X 35 SQMM/B2, 2C X 2.5 SQMM/B3, (3C+E) X 2.5 SQMM/B3,
(2C+E) X 2.5 SQMM/B3, 2 X 4 SQMM/B9, 4C X 150 SQMM/B2.
DRAWING NO. DK964-2-64-0001, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

1.3 Check provision of sufficient mechanical protection to existing underground /


above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

Check & ensure cable trench is clean and free from stones, debris & other
1.6 unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Page 50 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0464 SYSTEM DK964-201

REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION RTU964 (Inside) DISCIPLINE ELECTRICAL

DK964-ELP-101,DK964-ELP-102, DK964-ELP-103, DK964-EL-101/1, DK964-EL-101/2, DK964-EL-


CABLE TAG NUMBER 101/7, DK964-ELP-118, DK964-ELP-014
CABLE SIZE / TYPE 4C X 10 SQMM/B3, 4C X 35 SQMM/B2, 2C X 2.5 SQMM/B3, (3C+E) X 2.5 SQMM/B3,
(2C+E) X 2.5 SQMM/B3, 2 X 4 SQMM/B9, 4C X 150 SQMM/B2.
DRAWING NO. DK964-2-64-0001, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5
accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment

3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

Page 51 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0464 SYSTEM DK964-201

REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION RTU964 (Inside) DISCIPLINE ELECTRICAL

DK964-ELP-101,DK964-ELP-102, DK964-ELP-103, DK964-EL-101/1, DK964-EL-101/2, DK964-EL-


CABLE TAG NUMBER 101/7, DK964-ELP-118, DK964-ELP-014
CABLE SIZE / TYPE 4C X 10 SQMM/B3, 4C X 35 SQMM/B2, 2C X 2.5 SQMM/B3, (3C+E) X 2.5 SQMM/B3,
(2C+E) X 2.5 SQMM/B3, 2 X 4 SQMM/B9, 4C X 150 SQMM/B2.
DRAWING NO. DK964-2-64-0001, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Check end caps shall be provided at both the ends to prevent ingress of
3.23
moisture after cable laying.

3.24 Check and record cable continuity and insulation resistance test after cable
laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6 (Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

Page 52 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0464 SYSTEM DK964-201

REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION RTU964 (Inside) DISCIPLINE ELECTRICAL

DK964-ELP-101,DK964-ELP-102, DK964-ELP-103, DK964-EL-101/1, DK964-EL-101/2, DK964-EL-


CABLE TAG NUMBER 101/7, DK964-ELP-118, DK964-ELP-014
CABLE SIZE / TYPE 4C X 10 SQMM/B3, 4C X 35 SQMM/B2, 2C X 2.5 SQMM/B3, (3C+E) X 2.5 SQMM/B3,
(2C+E) X 2.5 SQMM/B3, 2 X 4 SQMM/B9, 4C X 150 SQMM/B2.
DRAWING NO. DK964-2-64-0001, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

DESIGNATION Engineer QC-E

DATE

Page 53 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0467 SYSTEM DK964-201

REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION RTU964 (Inside) DISCIPLINE ELECTRICAL

DK964-ELP-101,DK964-ELP-102, DK964-ELP-103, DK964-EL-101/1, DK964-EL-101/2, DK964-EL-


CABLE TAG NUMBER 101/7, DK964-ELP-118, DK964-ELP-014
CABLE SIZE / TYPE 4C X 10 SQMM/B3, 4C X 35 SQMM/B2, 2C X 2.5 SQMM/B3, (3C+E) X 2.5 SQMM/B3,
(2C+E) X 2.5 SQMM/B3, 2 X 4 SQMM/B9, 4C X 150 SQMM/B2.
DRAWING NO. DK964-2-64-0001, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground / Not applicable


1.3 above ground utilities crossing the excavated cable route. here, as this
check sheet is
1.4 Check cable trench depth and width as per AFC drawing. for the
installation of
cable tiles and
1.5 Check cable trench bottom is flat and sand bedding is correct warning tape
only
Check & ensure cable trench is clean and free from stones, debris & other
1.6 unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 cable tiles and
applicable
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Page 54 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0467 SYSTEM DK964-201

REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION RTU964 (Inside) DISCIPLINE ELECTRICAL

DK964-ELP-101,DK964-ELP-102, DK964-ELP-103, DK964-EL-101/1, DK964-EL-101/2, DK964-EL-


CABLE TAG NUMBER 101/7, DK964-ELP-118, DK964-ELP-014
CABLE SIZE / TYPE 4C X 10 SQMM/B3, 4C X 35 SQMM/B2, 2C X 2.5 SQMM/B3, (3C+E) X 2.5 SQMM/B3,
(2C+E) X 2.5 SQMM/B3, 2 X 4 SQMM/B9, 4C X 150 SQMM/B2.
DRAWING NO. DK964-2-64-0001, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.
Not applicable
3.4 Check for any physical damage of cable here, as this
check sheet is
Check existing cable encountered in the trench shall be realigned to for the
3.5
accommodate the new cable. installation of
cable tiles and
3.6 Check and verify laying arrangement of cable. warning tape
only
3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment

3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

Page 55 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0467 SYSTEM DK964-201

REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION RTU964 (Inside) DISCIPLINE ELECTRICAL

DK964-ELP-101,DK964-ELP-102, DK964-ELP-103, DK964-EL-101/1, DK964-EL-101/2, DK964-EL-


CABLE TAG NUMBER 101/7, DK964-ELP-118, DK964-ELP-014
CABLE SIZE / TYPE 4C X 10 SQMM/B3, 4C X 35 SQMM/B2, 2C X 2.5 SQMM/B3, (3C+E) X 2.5 SQMM/B3,
(2C+E) X 2.5 SQMM/B3, 2 X 4 SQMM/B9, 4C X 150 SQMM/B2.
DRAWING NO. DK964-2-64-0001, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Check end caps shall be provided at both the ends to prevent ingress of
3.23
moisture after cable laying.

3.24 Check and record cable continuity and insulation resistance test after cable
laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6 (Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

Page 56 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0467 SYSTEM DK964-201

REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION RTU964 (Inside) DISCIPLINE ELECTRICAL

DK964-ELP-101,DK964-ELP-102, DK964-ELP-103, DK964-EL-101/1, DK964-EL-101/2, DK964-EL-


CABLE TAG NUMBER 101/7, DK964-ELP-118, DK964-ELP-014
CABLE SIZE / TYPE 4C X 10 SQMM/B3, 4C X 35 SQMM/B2, 2C X 2.5 SQMM/B3, (3C+E) X 2.5 SQMM/B3,
(2C+E) X 2.5 SQMM/B3, 2 X 4 SQMM/B9, 4C X 150 SQMM/B2.
DRAWING NO. DK964-2-64-0001, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

DESIGNATION Engineer QC-E

DATE

Page 57 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0465 SYSTEM DK964-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION DK964 To RTU 964 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. DK968--2-64-0002-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground / Not applicable


1.3 here, as this
above ground utilities crossing the excavated cable route.
check sheet is
1.4 Check cable trench depth and width as per AFC drawing. for the
installation of
cable tiles and
1.5 Check cable trench bottom is flat and sand bedding is correct warning tape
only
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable. cable tiles and
warning tape
only

Page 58 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0465 SYSTEM DK964-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION DK964 To RTU 964 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. DK968--2-64-0002-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1 Not applicable
here, as this
APPLICATION / SERVICE LV Power & Lighting Cables check sheet is
for the
NOT installation of
SI NO DESCRIPTION OK OK N/A REMARKS
cable tiles and
warning tape
3.4 Check for any physical damage of cable only

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment Not applicable
here, as this
HV Cables pulling with winch operation shall be not more than maximum check sheet is
3.14 allowable tension in line with cable manufacturer recommendation.
for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 59 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE Not applicable
here, as this
LAYING WORKS check sheet is
for the
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS installation of
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT cable
NO.: tiles
4172and
warning tape
only
RFI NO. 4172-2-RFI-F-0465 SYSTEM DK964-201
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK964-201-01

LOCATION DK964 To RTU 964 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. DK968--2-64-0002-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 60 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0468 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION DK971 To RTU971 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK971-ELP-001 & DK971-EL101/7
CABLE SIZE / TYPE 4C X 50 SQMM/B2 & (2C+E) X 2.5 SQMM/B3
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 61 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0468 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION DK971 To RTU971 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK971-ELP-001 & DK971-EL101/7
CABLE SIZE / TYPE 4C X 50 SQMM/B2 & (2C+E) X 2.5 SQMM/B3
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 62 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0468 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION DK971 To RTU971 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK971-ELP-001 & DK971-EL101/7
CABLE SIZE / TYPE 4C X 50 SQMM/B2 & (2C+E) X 2.5 SQMM/B3
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 63 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0472 SYSTEM DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01

LOCATION DK972 To RTU972 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK972-ELP-102, DK972-EL101/7 & DK972-ELP-109
CABLE SIZE / TYPE 4C X 25 SQMM/B2, (2C+E) X 2.5 SQMM/B3 & 2C X 4 SQMM/B9
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 64 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0472 SYSTEM DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01

LOCATION DK972 To RTU972 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK972-ELP-102, DK972-EL101/7 & DK972-ELP-109
CABLE SIZE / TYPE 4C X 25 SQMM/B2, (2C+E) X 2.5 SQMM/B3 & 2C X 4 SQMM/B9
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 65 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0472 SYSTEM DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01

LOCATION DK972 To RTU972 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK972-ELP-102, DK972-EL101/7 & DK972-ELP-109
CABLE SIZE / TYPE 4C X 25 SQMM/B2, (2C+E) X 2.5 SQMM/B3 & 2C X 4 SQMM/B9
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 66 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0474 SYSTEM DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01

LOCATION DK966 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK966-ELP-002 & DK966-EL101/7
CABLE SIZE / TYPE 4C X 70 SQMM/B2 & (2C+E) X 2.5 SQMM/B3
DRAWING NO. DK966-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 67 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0474 SYSTEM DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01

LOCATION DK966 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK966-ELP-002 & DK966-EL101/7
CABLE SIZE / TYPE 4C X 70 SQMM/B2 & (2C+E) X 2.5 SQMM/B3
DRAWING NO. DK966-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 68 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0474 SYSTEM DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01

LOCATION DK966 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK966-ELP-002 & DK966-EL101/7
CABLE SIZE / TYPE 4C X 70 SQMM/B2 & (2C+E) X 2.5 SQMM/B3
DRAWING NO. DK966-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 69 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0485 SYSTEM JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-205-02

LOCATION JCWF SubStation Area DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. JCWF-2-67-0002-B
CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground / Not applicable


1.3 here, as this
above ground utilities crossing the excavated cable route.
check sheet is
1.4 Check cable trench depth and width as per AFC drawing. for the
installation of
cable tiles and
1.5 Check cable trench bottom is flat and sand bedding is correct warning tape
only
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable. cable tiles and
warning tape
only

Page 70 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0485 SYSTEM JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-205-02

LOCATION JCWF SubStation Area DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. JCWF-2-67-0002-B
CABLE SCHEDULE JCWF-2-37-0001-B Not applicable
here, as this
APPLICATION / SERVICE Lighting Circuit Cables check sheet is
for the
NOT installation of
SI NO DESCRIPTION OK OK N/A REMARKS
cable tiles and
warning tape
3.4 Check for any physical damage of cable only

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment Not applicable
here, as this
HV Cables pulling with winch operation shall be not more than maximum check sheet is
3.14 allowable tension in line with cable manufacturer recommendation.
for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 71 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE Not applicable
here, as this
LAYING WORKS check sheet is
for the
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS installation of
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT cable
NO.: tiles
4172and
warning tape
only
RFI NO. 4172-2-RFI-F-0485 SYSTEM JCWF-205
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-205-02

LOCATION JCWF SubStation Area DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. JCWF-2-67-0002-B
CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Shanif Abdulla Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 72 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0486 SYSTEM DK971-201 & DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-02 & DK972-201-02
LOCATION RTU971 To DK971 & RTU972 To DK972 DISCIPLINE ELECTRICAL
CABLE TAG NUMBER DK970-EE-0079, DK970-EE-0080, DK969-EE-0079, DK969-EE-0180, DK972-EE-0179, DK972-EE-0180,
DK971-EE-0079, DK971-EE-0080
CABLE SIZE / TYPE 1C X 70 SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

1.3 Check provision of sufficient mechanical protection to existing underground /


above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

Check & ensure cable trench is clean and free from stones, debris & other
1.6 unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.

Page 73 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0486 SYSTEM DK971-201 & DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-02 & DK972-201-02
LOCATION RTU971 To DK971 & RTU972 To DK972 DISCIPLINE ELECTRICAL
CABLE TAG NUMBER DK970-EE-0079, DK970-EE-0080, DK969-EE-0079, DK969-EE-0180, DK972-EE-0179, DK972-EE-0180,
DK971-EE-0079, DK971-EE-0080
CABLE SIZE / TYPE 1C X 70 SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
3.12 or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
Check and confirm cable tag numbers are correct and provided every 5 meter
3.18 intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 74 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0486 SYSTEM DK971-201 & DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-02 & DK972-201-02
LOCATION RTU971 To DK971 & RTU972 To DK972 DISCIPLINE ELECTRICAL
CABLE TAG NUMBER DK970-EE-0079, DK970-EE-0080, DK969-EE-0079, DK969-EE-0180, DK972-EE-0179, DK972-EE-0180,
DK971-EE-0079, DK971-EE-0080
CABLE SIZE / TYPE 1C X 70 SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

Check end caps shall be provided at both the ends to prevent ingress of
3.23 moisture after cable laying.

3.24 Check and record cable continuity and insulation resistance test after cable
laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6 (Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 75 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0479 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-02

LOCATION JCWF To BC12 (RTU970 Route) DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-EE-523, 36-EE-524, 36-EE-525 & 36-EE-526
CABLE SIZE / TYPE 1C X 70 SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 76 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0479 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-02

LOCATION JCWF To BC12 (RTU970 Route) DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-EE-523, 36-EE-524, 36-EE-525 & 36-EE-526
CABLE SIZE / TYPE 1C X 70 SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 77 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0479 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-02

LOCATION JCWF To BC12 (RTU970 Route) DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-EE-523, 36-EE-524, 36-EE-525 & 36-EE-526
CABLE SIZE / TYPE 1C X 70 SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 78 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0498 SYSTEM DK960-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-201-01

LOCATION JCWF Fence Area To JCWF Substation DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-ELP-0048, 36-EE-0525 &36-EE-0526
CABLE SIZE / TYPE 4C X50 SQMM/B2 & 1C X 70 SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 79 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0498 SYSTEM DK960-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-201-01

LOCATION JCWF Fence Area To JCWF Substation DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-ELP-0048, 36-EE-0525 &36-EE-0526
CABLE SIZE / TYPE 4C X50 SQMM/B2 & 1C X 70 SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 80 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0498 SYSTEM DK960-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-201-01

LOCATION JCWF Fence Area To JCWF Substation DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-ELP-0048, 36-EE-0525 &36-EE-0526
CABLE SIZE / TYPE 4C X50 SQMM/B2 & 1C X 70 SQMM/E
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Earthing Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 81 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0502 SYSTEM JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-205-02

LOCATION Joint Bay 01 To RTU969 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-ELP-0045-1 & 36-ELP-0045-2
CABLE SIZE / TYPE 4C x 185 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power Cables from Wellhead Main JB (36-JB-0003) To Wellhead Main DB (DK969-MDB-101)

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 82 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0502 SYSTEM JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-205-02

LOCATION Joint Bay 01 To RTU969 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-ELP-0045-1 & 36-ELP-0045-2
CABLE SIZE / TYPE 4C x 185 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power Cables from Wellhead Main JB (36-JB-0003) To Wellhead Main DB (DK969-MDB-101)

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 83 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0502 SYSTEM JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-205-02

LOCATION Joint Bay 01 To RTU969 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER 36-ELP-0045-1 & 36-ELP-0045-2
CABLE SIZE / TYPE 4C x 185 SQMM/B2
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power Cables from Wellhead Main JB (36-JB-0003) To Wellhead Main DB (DK969-MDB-101)

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 84 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0503 SYSTEM JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-205-02

LOCATION JCWF Plant Area DISCIPLINE ELECTRICAL

CABLE TAG NUMBER 36-EL-0046/10 & 36-ELP-0128/3, 36-EL-0016, 36-EL-0016/14, 36-EL-0045, 36-EL-0045/5, 36-EL-0046
& 36-EL-0046/5
CABLE SIZE / TYPE 4C x 16 SQMM/B2 , 2C+E x 4 SQMM/B3, 3C+E x 6 SQMM/B7, 2C+E x 6 SQMM/B3.
DRAWING NO. JCWF-2-64-0001-C
CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting Circuit Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3 above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
2.2
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
Check duct bank location and dimensional check-up for the installed ducts along
2.5 the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 85 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0503 SYSTEM JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-205-02

LOCATION JCWF Plant Area DISCIPLINE ELECTRICAL

CABLE TAG NUMBER 36-EL-0046/10 & 36-ELP-0128/3, 36-EL-0016, 36-EL-0016/14, 36-EL-0045, 36-EL-0045/5, 36-EL-0046
& 36-EL-0046/5
CABLE SIZE / TYPE 4C x 16 SQMM/B2 , 2C+E x 4 SQMM/B3, 3C+E x 6 SQMM/B7, 2C+E x 6 SQMM/B3.
DRAWING NO. JCWF-2-64-0001-C
CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting Circuit Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.4 Check for any physical damage of cable

3.5 Check existing cable encountered in the trench shall be realigned to


accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment

3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

Check segregation from power cable, control cable, IS & non IS cables shall be
3.20 provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 86 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0503 SYSTEM JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-205-02

LOCATION JCWF Plant Area DISCIPLINE ELECTRICAL

CABLE TAG NUMBER 36-EL-0046/10 & 36-ELP-0128/3, 36-EL-0016, 36-EL-0016/14, 36-EL-0045, 36-EL-0045/5, 36-EL-0046
& 36-EL-0046/5
CABLE SIZE / TYPE 4C x 16 SQMM/B2 , 2C+E x 4 SQMM/B3, 3C+E x 6 SQMM/B7, 2C+E x 6 SQMM/B3.
DRAWING NO. JCWF-2-64-0001-C
CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting Circuit Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.

3.24 Check
laying
and record cable continuity and insulation resistance test after cable

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6 (Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

Check route marker installation on straight routes distances shall not exceeding
4.8 50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 87 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0505 SYSTEM DK966-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK966-201-01

LOCATION RTU966 To DK966 & RTU968 To DK968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground / Not applicable


1.3 here, as this
above ground utilities crossing the excavated cable route.
check sheet is
1.4 Check cable trench depth and width as per AFC drawing. for the
installation of
cable tiles and
1.5 Check cable trench bottom is flat and sand bedding is correct warning tape
only
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable. cable tiles and
warning tape
only

Page 88 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0505 SYSTEM DK966-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK966-201-01

LOCATION RTU966 To DK966 & RTU968 To DK968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1 Not applicable
here, as this
APPLICATION / SERVICE LV Power & Lighting Cables check sheet is
for the
NOT installation of
SI NO DESCRIPTION OK OK N/A REMARKS
cable tiles and
warning tape
3.4 Check for any physical damage of cable only

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment Not applicable
here, as this
HV Cables pulling with winch operation shall be not more than maximum check sheet is
3.14 allowable tension in line with cable manufacturer recommendation.
for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 89 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE Not applicable
here, as this
LAYING WORKS check sheet is
for the
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS installation of
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT cable
NO.: tiles
4172and
warning tape
only
RFI NO. 4172-2-RFI-F-0505 SYSTEM DK966-201
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK966-201-01

LOCATION RTU966 To DK966 & RTU968 To DK968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. 4172-WLHD-2-64-0002, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Shanif Abdulla Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 90 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0509 SYSTEM DK968-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK968-201-01

LOCATION RTU968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK968-ELP-002, DK968-EL-010/1, DK968-EL-010/2 & DK968-ELP-008.
CABLE SIZE / TYPE 2C x 2.5 SQMM/B3 , 3C+E x 2.5 SQMM/B3 & 2Cx 6 SQMM/B9.
DRAWING NO. DK968-2-64-0001-C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Power & Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 91 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0509 SYSTEM DK968-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK968-201-01

LOCATION RTU968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK968-ELP-002, DK968-EL-010/1, DK968-EL-010/2 & DK968-ELP-008.
CABLE SIZE / TYPE 2C x 2.5 SQMM/B3 , 3C+E x 2.5 SQMM/B3 & 2Cx 6 SQMM/B9.
DRAWING NO. DK968-2-64-0001-C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Power & Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 92 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0509 SYSTEM DK968-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK968-201-01

LOCATION RTU968 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK968-ELP-002, DK968-EL-010/1, DK968-EL-010/2 & DK968-ELP-008.
CABLE SIZE / TYPE 2C x 2.5 SQMM/B3 , 3C+E x 2.5 SQMM/B3 & 2Cx 6 SQMM/B9.
DRAWING NO. DK968-2-64-0001-C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Power & Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 93 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0510 SYSTEM DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01

LOCATION Inside DK972 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK972-ELP-102, DK972-EL-101/7 & DK972-ELP-109.
CABLE SIZE / TYPE 4C x 25 SQMM/B2 , 2C+E x 2.5 SQMM/B3 & 2Cx 4 SQMM/B9.
DRAWING NO. DK972-2-64-0002-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Power & Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 94 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0510 SYSTEM DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01

LOCATION Inside DK972 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK972-ELP-102, DK972-EL-101/7 & DK972-ELP-109.
CABLE SIZE / TYPE 4C x 25 SQMM/B2 , 2C+E x 2.5 SQMM/B3 & 2Cx 4 SQMM/B9.
DRAWING NO. DK972-2-64-0002-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Power & Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 95 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0510 SYSTEM DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01

LOCATION Inside DK972 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK972-ELP-102, DK972-EL-101/7 & DK972-ELP-109.
CABLE SIZE / TYPE 4C x 25 SQMM/B2 , 2C+E x 2.5 SQMM/B3 & 2Cx 4 SQMM/B9.
DRAWING NO. DK972-2-64-0002-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Power & Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 96 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0511 SYSTEM DK972-201, DK961-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01, DK961-201-01

LOCATION JCWF Fence to RTU Stations (DK-970,969,972 and DISCIPLINE ELECTRICAL


DK-962,963,960,961)
CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. 4172-WLHD-2-64-0002, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1

APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench fromJCWF Fence to RTU Stations (DK-
970,969,972 and DK-962,963,960,961)

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground / Not applicable


1.3 here, as this
above ground utilities crossing the excavated cable route.
check sheet is
1.4 Check cable trench depth and width as per AFC drawing. for the
installation of
cable tiles and
1.5 Check cable trench bottom is flat and sand bedding is correct warning tape
only
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
2.2 completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 applicable cable tiles and
warning tape
2.5 Check duct bank location and dimensional check-up for the installed ducts along only
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable tiles and
cable.
warning tape
only
Page 97 of 134 GF-4172-QC-EI-FM-0005, Rev. 4
CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0511 SYSTEM DK972-201, DK961-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01, DK961-201-01

LOCATION JCWF Fence to RTU Stations (DK-970,969,972 and DISCIPLINE ELECTRICAL


DK-962,963,960,961)
CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. 4172-WLHD-2-64-0002, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
Not applicable
Cable tile and warning tape for Electrical cable trench fromJCWF Fence to RTU Stationshere,
(DK- as this
APPLICATION / SERVICE 970,969,972 and DK-962,963,960,961) check sheet is
for the
NOT installation of
SI NO DESCRIPTION OK N/A cable REMARKS
tiles and
OK
warning tape
3.4 Check for any physical damage of cable only

Check existing cable encountered in the trench shall be realigned to


3.5
accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment
Not applicable
here, as this
3.14 HV Cables pulling with winch operation shall be not more than maximum check sheet is
allowable tension in line with cable manufacturer recommendation. for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 98 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
Not applicable
LAYING WORKS here, as this
check sheet is
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS for the
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT installation
NO.: 4172 of
cable tiles and
RFI NO. 4172-2-RFI-F-0511 SYSTEM DK972-201,warning tape
DK961-201
only
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01, DK961-201-01

LOCATION JCWF Fence to RTU Stations (DK-970,969,972 and DISCIPLINE ELECTRICAL


DK-962,963,960,961)
CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. 4172-WLHD-2-64-0002, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1

APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench fromJCWF Fence to RTU Stations (DK-
970,969,972 and DK-962,963,960,961)

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

Check route marker installation on straight routes distances shall not exceeding
4.8 50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 99 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0516 SYSTEM DK960-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-201-01

LOCATION JCWF Fence to DK960 Route DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. JCWF-2-64-0001, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1

APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench from JCWF Fence to DK960 Route as per
attached highlighted drawing

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground / Not applicable


1.3 here, as this
above ground utilities crossing the excavated cable route.
check sheet is
1.4 Check cable trench depth and width as per AFC drawing. for the
installation of
cable tiles and
1.5 Check cable trench bottom is flat and sand bedding is correct warning tape
only
Check & ensure cable trench is clean and free from stones, debris & other
1.6 unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 cable tiles and
applicable
warning tape
Check duct bank location and dimensional check-up for the installed ducts along only
2.5 the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable tiles and
cable.
warning tape
only
Page 100 of 134 GF-4172-QC-EI-FM-0005, Rev. 4
CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0516 SYSTEM DK960-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-201-01

LOCATION JCWF Fence to DK960 Route DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. JCWF-2-64-0001, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
Not applicable
Cable tile and warning tape for Electrical cable trench from JCWF Fence to DK960 here,
Route as this
as per
APPLICATION / SERVICE attached highlighted drawing check sheet is
for the
NOT installation of
SI NO DESCRIPTION OK N/A cableREMARKS
tiles and
OK
warning tape
3.4 Check for any physical damage of cable only

3.5 Check existing cable encountered in the trench shall be realigned to


accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment
Not applicable
here, as this
3.14 HV Cables pulling with winch operation shall be not more than maximum check sheet is
allowable tension in line with cable manufacturer recommendation. for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only

3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
Check and confirm cable tag numbers are correct and provided every 5 meter
3.18 intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

Check segregation from power cable, control cable, IS & non IS cables shall be
3.20 provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 101 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE Not applicable
LAYING WORKS here, as this
check sheet is
for the
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT installation
NO.: 4172 of
cable tiles and
warning tape
RFI NO. 4172-2-RFI-F-0516 SYSTEM DK960-201only
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-201-01

LOCATION JCWF Fence to DK960 Route DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. JCWF-2-64-0001, Rev.B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1

APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench from JCWF Fence to DK960 Route as per
attached highlighted drawing

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24
laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

Check route marker installation on straight routes distances shall not exceeding
4.8 50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 102 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0530 SYSTEM DK969-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK969-201-01

LOCATION Inside RTU969 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK969-ELP-102, DK969-EL-101, DK969-EL-101/1, DK969-EL-101/2 & DK969-ELP-117
CABLE SIZE / TYPE 2C x 2.5 SQMM/B3, 2C+E x 4 SQMM/B3. 3C+E x 2.5 SQMM/B3 , 2C x 6 SQMM/B9
DRAWING NO. DK969-2-64-0001-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Power & Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 103 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0530 SYSTEM DK969-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK969-201-01

LOCATION Inside RTU969 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK969-ELP-102, DK969-EL-101, DK969-EL-101/1, DK969-EL-101/2 & DK969-ELP-117
CABLE SIZE / TYPE 2C x 2.5 SQMM/B3, 2C+E x 4 SQMM/B3. 3C+E x 2.5 SQMM/B3 , 2C x 6 SQMM/B9
DRAWING NO. DK969-2-64-0001-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Power & Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 104 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0530 SYSTEM DK969-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK969-201-01

LOCATION Inside RTU969 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK969-ELP-102, DK969-EL-101, DK969-EL-101/1, DK969-EL-101/2 & DK969-ELP-117
CABLE SIZE / TYPE 2C x 2.5 SQMM/B3, 2C+E x 4 SQMM/B3. 3C+E x 2.5 SQMM/B3 , 2C x 6 SQMM/B9
DRAWING NO. DK969-2-64-0001-B
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Power & Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 105 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0531 SYSTEM DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01

LOCATION Inside RTU972 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK972-ELP-101, DK972-ELP-104, DK972-EL-101, DK972-EL-101/1, DK972-EL-101/2 & DK972-ELP-
108.
CABLE SIZE / TYPE 4C x 10 SQMM/B3 , 2C x 2.5 SQMM/B3, 2C+E x 4 SQMM/B3. 3C+E x 2.5 SQMM/B3 , 2C x 6
SQMM/B9
DRAWING NO. DK972-2-64-0001, C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Power & Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 106 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0531 SYSTEM DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01

LOCATION Inside RTU972 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK972-ELP-101, DK972-ELP-104, DK972-EL-101, DK972-EL-101/1, DK972-EL-101/2 & DK972-ELP-
108.
CABLE SIZE / TYPE 4C x 10 SQMM/B3 , 2C x 2.5 SQMM/B3, 2C+E x 4 SQMM/B3. 3C+E x 2.5 SQMM/B3 , 2C x 6
SQMM/B9
DRAWING NO. DK972-2-64-0001, C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Power & Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 107 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0531 SYSTEM DK972-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK972-201-01

LOCATION Inside RTU972 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK972-ELP-101, DK972-ELP-104, DK972-EL-101, DK972-EL-101/1, DK972-EL-101/2 & DK972-ELP-
108.
CABLE SIZE / TYPE 4C x 10 SQMM/B3 , 2C x 2.5 SQMM/B3, 2C+E x 4 SQMM/B3. 3C+E x 2.5 SQMM/B3 , 2C x 6
SQMM/B9
DRAWING NO. DK972-2-64-0001, C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Power & Lighting Circuit Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 108 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0554 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION DK971 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK971-ELP-001 & DK971-EL101/7
CABLE SIZE / TYPE 4C X 50 SQMM/B2 & (2C+E) X 2.5 SQMM/B3
DRAWING NO. DK971-2-64-0002, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 109 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0554 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION DK971 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK971-ELP-001 & DK971-EL101/7
CABLE SIZE / TYPE 4C X 50 SQMM/B2 & (2C+E) X 2.5 SQMM/B3
DRAWING NO. DK971-2-64-0002, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 110 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0554 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION DK971 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK971-ELP-001 & DK971-EL101/7
CABLE SIZE / TYPE 4C X 50 SQMM/B2 & (2C+E) X 2.5 SQMM/B3
DRAWING NO. DK971-2-64-0002, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power & Lighting Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable Refer, 4172-2-RFI-
3.24 laying F-0468

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME J. Rajesh Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 111 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0567 SYSTEM DK965-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK965-201-01

LOCATION Inside DK965 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK965-ELP-001 & DK965-EL-101/7
CABLE SIZE / TYPE 4Cx35 SQ. MM. / B2 & (2C+E) x 2.5 SQ. MM. / B3
DRAWING NO. DK965-2-64-0002, C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power and Lighting

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3
above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

Page 112 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0567 SYSTEM DK965-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK965-201-01

LOCATION Inside DK965 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK965-ELP-001 & DK965-EL-101/7
CABLE SIZE / TYPE 4Cx35 SQ. MM. / B2 & (2C+E) x 2.5 SQ. MM. / B3
DRAWING NO. DK965-2-64-0002, C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power and Lighting

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 113 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0567 SYSTEM DK965-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK965-201-01

LOCATION Inside DK965 DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK965-ELP-001 & DK965-EL-101/7
CABLE SIZE / TYPE 4Cx35 SQ. MM. / B2 & (2C+E) x 2.5 SQ. MM. / B3
DRAWING NO. DK965-2-64-0002, C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE LV Power and Lighting

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 114 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0568 SYSTEM JCWF-204 & JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-204-2 & JCWF-205-02

LOCATION JCWF Substation & Plant Area DISCIPLINE ELECTRICAL

36-EL-0013 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0015 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0017 ((3C+E) x 6
CABLE TAG NUMBER Sq. mm. / B9), 36-EL-0018 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0034 ((2C+E) x 6 Sq. mm. / B3), 36-EL-
0035 ((2C+E) x 6 Sq. mm. / B6), 36-ELP-0119 ((4C+E) x 10 Sq. mm. / B6), 36-ELP-0128 ((2C+E) x 6 Sq.
mm. / B3), 36-ELP-0129 ((2C+E) x 6 Sq. mm. / B2), 36-ELP-0129/2 ((2C+E) x 4 Sq. mm. / B3) 36-ELP-
CABLE SIZE / TYPE 0147 ((2C+E) x 6 Sq. mm. / B3), 36-EL-0037 ((2C+E) x 6 Sq. mm. / B3) & 36-EL-0038 ((2C+E) x 6 Sq.
mm. / B3)

DRAWING NO. JCWF-2-64-0001-C


CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting & Small Power Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground /


1.3 above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
Check duct bank location and dimensional check-up for the installed ducts along
2.5 the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

Page 115 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0568 SYSTEM JCWF-204 & JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-204-2 & JCWF-205-02

LOCATION JCWF Substation & Plant Area DISCIPLINE ELECTRICAL

36-EL-0013 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0015 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0017 ((3C+E) x 6
CABLE TAG NUMBER Sq. mm. / B9), 36-EL-0018 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0034 ((2C+E) x 6 Sq. mm. / B3), 36-EL-
0035 ((2C+E) x 6 Sq. mm. / B6), 36-ELP-0119 ((4C+E) x 10 Sq. mm. / B6), 36-ELP-0128 ((2C+E) x 6 Sq.
mm. / B3), 36-ELP-0129 ((2C+E) x 6 Sq. mm. / B2), 36-ELP-0129/2 ((2C+E) x 4 Sq. mm. / B3) 36-ELP-
CABLE SIZE / TYPE 0147 ((2C+E) x 6 Sq. mm. / B3), 36-EL-0037 ((2C+E) x 6 Sq. mm. / B3) & 36-EL-0038 ((2C+E) x 6 Sq.
mm. / B3)

DRAWING NO. JCWF-2-64-0001-C


CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting & Small Power Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
3.12 or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

Page 116 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0568 SYSTEM JCWF-204 & JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-204-2 & JCWF-205-02

LOCATION JCWF Substation & Plant Area DISCIPLINE ELECTRICAL

36-EL-0013 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0015 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0017 ((3C+E) x 6
CABLE TAG NUMBER Sq. mm. / B9), 36-EL-0018 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0034 ((2C+E) x 6 Sq. mm. / B3), 36-EL-
0035 ((2C+E) x 6 Sq. mm. / B6), 36-ELP-0119 ((4C+E) x 10 Sq. mm. / B6), 36-ELP-0128 ((2C+E) x 6 Sq.
mm. / B3), 36-ELP-0129 ((2C+E) x 6 Sq. mm. / B2), 36-ELP-0129/2 ((2C+E) x 4 Sq. mm. / B3) 36-ELP-
CABLE SIZE / TYPE 0147 ((2C+E) x 6 Sq. mm. / B3), 36-EL-0037 ((2C+E) x 6 Sq. mm. / B3) & 36-EL-0038 ((2C+E) x 6 Sq.
mm. / B3)

DRAWING NO. JCWF-2-64-0001-C


CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting & Small Power Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.

3.24 Check and record cable continuity and insulation resistance test after cable
laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

Page 117 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0568 SYSTEM JCWF-204 & JCWF-205


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM JCWF-204-2 & JCWF-205-02

LOCATION JCWF Substation & Plant Area DISCIPLINE ELECTRICAL

36-EL-0013 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0015 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0017 ((3C+E) x 6
CABLE TAG NUMBER Sq. mm. / B9), 36-EL-0018 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0034 ((2C+E) x 6 Sq. mm. / B3), 36-EL-
0035 ((2C+E) x 6 Sq. mm. / B6), 36-ELP-0119 ((4C+E) x 10 Sq. mm. / B6), 36-ELP-0128 ((2C+E) x 6 Sq.
mm. / B3), 36-ELP-0129 ((2C+E) x 6 Sq. mm. / B2), 36-ELP-0129/2 ((2C+E) x 4 Sq. mm. / B3) 36-ELP-
CABLE SIZE / TYPE 0147 ((2C+E) x 6 Sq. mm. / B3), 36-EL-0037 ((2C+E) x 6 Sq. mm. / B3) & 36-EL-0038 ((2C+E) x 6 Sq.
mm. / B3)

DRAWING NO. JCWF-2-64-0001-C


CABLE SCHEDULE JCWF-2-37-0001-B
APPLICATION / SERVICE Lighting & Small Power Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 118 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0566 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION DK971 (Inside) DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. DK971-2-64-0002, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1

APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench at DK971 Wellhead area (Inside) as per
attached highlighted drawing

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

Check provision of sufficient mechanical protection to existing underground / Not applicable


1.3 here, as this
above ground utilities crossing the excavated cable route.
check sheet is
1.4 Check cable trench depth and width as per AFC drawing. for the
installation of
cable tiles and
1.5 Check cable trench bottom is flat and sand bedding is correct warning tape
only
Check & ensure cable trench is clean and free from stones, debris & other
1.6 unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables. Not applicable
here, as this
2.3 Check and ensure approved cable duct is being installed at site check sheet is
for the
Inside the duct bank Spare sleeves are provided with pulling ropes, where installation of
2.4 cable tiles and
applicable
warning tape
Check duct bank location and dimensional check-up for the installed ducts along only
2.5 the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed. Not applicable
here, as this
3.2 Cable drum placing shall be on solid flat surface check sheet is
for the
Check and ensure that cables shall not contacted with ground while pulling the installation of
3.3 cable tiles and
cable.
warning tape
only
Page 119 of 134 GF-4172-QC-EI-FM-0005, Rev. 4
CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0566 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION DK971 (Inside) DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. DK971-2-64-0002, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
Not applicable
Cable tile and warning tape for Electrical cable trench at DK971 Wellhead area here,
(Inside) as this
as per
APPLICATION / SERVICE attached highlighted drawing check sheet is
for the
NOT installation of
SI NO DESCRIPTION OK N/A cable REMARKS
tiles and
OK
warning tape
3.4 Check for any physical damage of cable only

3.5 Check existing cable encountered in the trench shall be realigned to


accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment
Not applicable
here, as this
3.14 HV Cables pulling with winch operation shall be not more than maximum check sheet is
allowable tension in line with cable manufacturer recommendation. for the
installation of
3.15 Check the cable ends shall be protected against ingress of moisture / dust. cable tiles and
warning tape
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying. only

3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
Check and confirm cable tag numbers are correct and provided every 5 meter
3.18 intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

Check segregation from power cable, control cable, IS & non IS cables shall be
3.20 provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 120 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE Not applicable
LAYING WORKS here, as this
check sheet is
for the
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT installation
NO.: 4172 of
cable tiles and
warning tape
RFI NO. 4172-2-RFI-F-0566 SYSTEM DK971-201only
REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION DK971 (Inside) DISCIPLINE ELECTRICAL


CABLE TAG NUMBER Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
CABLE SIZE / TYPE Not applicable here, as this check sheet is for the installation of cable tiles and warning tape only
DRAWING NO. DK971-2-64-0002, Rev.C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1

APPLICATION / SERVICE Cable tile and warning tape for Electrical cable trench at DK971 Wellhead area (Inside) as per
attached highlighted drawing

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24
laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

Check route marker installation on straight routes distances shall not exceeding
4.8 50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 121 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0572 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION DK971 RTU Station DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK971 -ELP-002 (2C x 2.5 Sq. mm. / B3), DK971 -EL-101 ((2C+E) x 4 Sq. mm. / B3), DK971 -EL-101/1
((3C+E) x 2.5 Sq. mm. / B3), DK971 -EL-101/2 ((3C+E) x 2.5 Sq. mm. / B3) & DK971 -ELP-008 (2C x 6.5
CABLE SIZE / TYPE Sq. mm. / B9).

DRAWING NO. DK971-2-64-0001-C


CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting Circuit Cables & RTU Panel Supply Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

1.3 Check provision of sufficient mechanical protection to existing underground /


above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

Check & ensure cable trench is clean and free from stones, debris & other
1.6 unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4
applicable
Check duct bank location and dimensional check-up for the installed ducts along
2.5 the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.

Page 122 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0572 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION DK971 RTU Station DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK971 -ELP-002 (2C x 2.5 Sq. mm. / B3), DK971 -EL-101 ((2C+E) x 4 Sq. mm. / B3), DK971 -EL-101/1
((3C+E) x 2.5 Sq. mm. / B3), DK971 -EL-101/2 ((3C+E) x 2.5 Sq. mm. / B3) & DK971 -ELP-008 (2C x 6.5
CABLE SIZE / TYPE Sq. mm. / B9).

DRAWING NO. DK971-2-64-0001-C


CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting Circuit Cables & RTU Panel Supply Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.4 Check for any physical damage of cable

3.5 Check existing cable encountered in the trench shall be realigned to


accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
Confirm cables emerging from ground / Stub up cable opening shall be located
3.13 nearest point (underneath gland plate) of field equipment

3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
Check and confirm cable tag numbers are correct and provided every 5 meter
3.18 intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

Check segregation from power cable, control cable, IS & non IS cables shall be
3.20 provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 123 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0572 SYSTEM DK971-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK971-201-01

LOCATION DK971 RTU Station DISCIPLINE ELECTRICAL


CABLE TAG NUMBER DK971 -ELP-002 (2C x 2.5 Sq. mm. / B3), DK971 -EL-101 ((2C+E) x 4 Sq. mm. / B3), DK971 -EL-101/1
((3C+E) x 2.5 Sq. mm. / B3), DK971 -EL-101/2 ((3C+E) x 2.5 Sq. mm. / B3) & DK971 -ELP-008 (2C x 6.5
CABLE SIZE / TYPE Sq. mm. / B9).

DRAWING NO. DK971-2-64-0001-C


CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting Circuit Cables & RTU Panel Supply Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24
laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

4.6 Check colored concrete are provided along the cable route in paved area
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

Check route marker installation on straight routes distances shall not exceeding
4.8 50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 124 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0610 SYSTEM DK967-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK967-201-01

LOCATION DK967 Wellhead Area DISCIPLINE ELECTRICAL


CABLE TAG NUMBER
DK967 -ELP-0001 (4C x70 Sq. mm. / B2) & DK967 -EL-101/7 ((2C+E) x 2.5 Sq. mm. / B3 )
CABLE SIZE / TYPE
DRAWING NO. DK967-2-64-0002-C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting & Small Power Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

1.3 Check provision of sufficient mechanical protection to existing underground /


above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

Check & ensure cable trench is clean and free from stones, debris & other
1.6
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.

Page 125 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0610 SYSTEM DK967-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK967-201-01

LOCATION DK967 Wellhead Area DISCIPLINE ELECTRICAL


CABLE TAG NUMBER
DK967 -ELP-0001 (4C x70 Sq. mm. / B2) & DK967 -EL-101/7 ((2C+E) x 2.5 Sq. mm. / B3 )
CABLE SIZE / TYPE
DRAWING NO. DK967-2-64-0002-C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting & Small Power Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

3.4 Check for any physical damage of cable

Check existing cable encountered in the trench shall be realigned to


3.5 accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
3.12 or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Page 126 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0610 SYSTEM DK967-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK967-201-01

LOCATION DK967 Wellhead Area DISCIPLINE ELECTRICAL


CABLE TAG NUMBER
DK967 -ELP-0001 (4C x70 Sq. mm. / B2) & DK967 -EL-101/7 ((2C+E) x 2.5 Sq. mm. / B3 )
CABLE SIZE / TYPE
DRAWING NO. DK967-2-64-0002-C
CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting & Small Power Cables

NOT
SI NO DESCRIPTION OK OK N/A REMARKS

Check end caps shall be provided at both the ends to prevent ingress of
3.23
moisture after cable laying.

3.24 Check and record cable continuity and insulation resistance test after cable Refer 4172-2-
laying RFI-F-0388

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6 (Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 127 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0588 SYSTEM DK970-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK970-201-01

LOCATION DK970 RTU Station DISCIPLINE ELECTRICAL

CABLE TAG NUMBER DK970 -ELP-102 (4C x35 Sq. mm. / B2), DK970 -ELP-103 ( 2C x 2.5 Sq. mm. / B3), DK970 -EL-101
((2C+E) x 4 Sq. mm. / B3), DK970 -EL-101/1 ((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/2
((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/7 ((2C+E) x 2.5 Sq. mm. / B3 ) & DK970 -ELP-008 (2C x 6
CABLE SIZE / TYPE Sq. mm. / B9.)

DRAWING NO. DK970-2-64-0001-C


CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting & Small Power Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

1.3 Check provision of sufficient mechanical protection to existing underground /


above ground utilities crossing the excavated cable route.

1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

Check & ensure cable trench is clean and free from stones, debris & other
1.6 unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.

2.3 Check and ensure approved cable duct is being installed at site

2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
Check duct bank location and dimensional check-up for the installed ducts along
2.5 the cable route.

2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.
Page 128 of 134 GF-4172-QC-EI-FM-0005, Rev. 4
CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0588 SYSTEM DK970-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK970-201-01

LOCATION DK970 RTU Station DISCIPLINE ELECTRICAL

CABLE TAG NUMBER DK970 -ELP-102 (4C x35 Sq. mm. / B2), DK970 -ELP-103 ( 2C x 2.5 Sq. mm. / B3), DK970 -EL-101
((2C+E) x 4 Sq. mm. / B3), DK970 -EL-101/1 ((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/2
((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/7 ((2C+E) x 2.5 Sq. mm. / B3 ) & DK970 -ELP-008 (2C x 6
CABLE SIZE / TYPE Sq. mm. / B9.)

DRAWING NO. DK970-2-64-0001-C


CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting & Small Power Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.4 Check for any physical damage of cable

3.5 Check existing cable encountered in the trench shall be realigned to


accommodate the new cable.

3.6 Check and verify laying arrangement of cable.

3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.

Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
3.12 or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment

3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.

3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.

3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
Check and confirm cable tag numbers are correct and provided every 5 meter
3.18 intervals

3.19 Check and confirm all cables are laid as per cable schedule / layout

Check segregation from power cable, control cable, IS & non IS cables shall be
3.20 provided properly.

3.21 Confirm the bending radius of cables correct

Page 129 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0588 SYSTEM DK970-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK970-201-01

LOCATION DK970 RTU Station DISCIPLINE ELECTRICAL

CABLE TAG NUMBER DK970 -ELP-102 (4C x35 Sq. mm. / B2), DK970 -ELP-103 ( 2C x 2.5 Sq. mm. / B3), DK970 -EL-101
((2C+E) x 4 Sq. mm. / B3), DK970 -EL-101/1 ((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/2
((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/7 ((2C+E) x 2.5 Sq. mm. / B3 ) & DK970 -ELP-008 (2C x 6
CABLE SIZE / TYPE Sq. mm. / B9.)

DRAWING NO. DK970-2-64-0001-C


CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting & Small Power Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

3.23 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and record cable continuity and insulation resistance test after cable
3.24 laying

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends

4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6
(Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

Page 130 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0588 SYSTEM DK970-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK970-201-01

LOCATION DK970 RTU Station DISCIPLINE ELECTRICAL

CABLE TAG NUMBER DK970 -ELP-102 (4C x35 Sq. mm. / B2), DK970 -ELP-103 ( 2C x 2.5 Sq. mm. / B3), DK970 -EL-101
((2C+E) x 4 Sq. mm. / B3), DK970 -EL-101/1 ((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/2
((3C+E) x 2.5 Sq. mm. / B3 ), DK970 -EL-101/7 ((2C+E) x 2.5 Sq. mm. / B3 ) & DK970 -ELP-008 (2C x 6
CABLE SIZE / TYPE Sq. mm. / B9.)

DRAWING NO. DK970-2-64-0001-C


CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting & Small Power Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

DATE

Page 131 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0644 SYSTEM DK960-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-201-02

LOCATION Inside DK960/ DK961 RTU Station DISCIPLINE ELECTRICAL

CABLE TAG NUMBER DK965-ELP-015, DK965-ELP-002, DK965-ELP-003, DK965-EL-101, DK965-EL-101/1, DK965-EL-101/2 &
DK965-ELP-008

DK960-ELP-006 (2C x 6 Sq. mm. / B9), DK960-ELP-007 (2C x 6 Sq. mm. / B9),
DK960-EL-001 ((2C+E) x 4 Sq. mm. / B3), DK960-EL-001/1 ((3C+E) x 2.5 Sq. mm. / B3),
CABLE SIZE / TYPE DK960-EL-001/2 ((3C+E) x 2.5 Sq. mm. / B3), DK960--ELP-011 (2C x 6 Sq. mm. / B9) &
DK960--ELP-012(2C x 6 Sq. mm. / B9)

DRAWING NO. DK960-2-64-0001, B


CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting and Small Power Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK
1.0 CABLE TRENCH INSPECTION

1.1 Check clearance from civil is obtained for Cable Trench..

1.2 Check & verify cable route as per AFC drawing.

1.3 Check provision of sufficient mechanical protection to existing underground /


above ground utilities crossing the excavated cable route.
1.4 Check cable trench depth and width as per AFC drawing.

1.5 Check cable trench bottom is flat and sand bedding is correct

1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.

1.7 Check Excavated material shall be deposited a minimum of 1 meter away from
the trench.

2.0 CABLE DUCT INSPECTION

2.1 Check clearance from civil is obtained for Cable duct

2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
Inside the duct bank Spare sleeves are provided with pulling ropes, where
2.4 applicable

2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness

3.0 UNDERGROUND CABLE LAYING INSPECTION

3.1 Check and confirm material inspection of cables are completed.

3.2 Cable drum placing shall be on solid flat surface

3.3 Check and ensure that cables shall not contacted with ground while pulling the
cable.
3.4 Check for any physical damage of cable

Page 132 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0644 SYSTEM DK960-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-201-02

LOCATION Inside DK960/ DK961 RTU Station DISCIPLINE ELECTRICAL

CABLE TAG NUMBER DK965-ELP-015, DK965-ELP-002, DK965-ELP-003, DK965-EL-101, DK965-EL-101/1, DK965-EL-101/2 &
DK965-ELP-008

DK960-ELP-006 (2C x 6 Sq. mm. / B9), DK960-ELP-007 (2C x 6 Sq. mm. / B9),
DK960-EL-001 ((2C+E) x 4 Sq. mm. / B3), DK960-EL-001/1 ((3C+E) x 2.5 Sq. mm. / B3),
CABLE SIZE / TYPE DK960-EL-001/2 ((3C+E) x 2.5 Sq. mm. / B3), DK960--ELP-011 (2C x 6 Sq. mm. / B9) &
DK960--ELP-012(2C x 6 Sq. mm. / B9)

DRAWING NO. DK960-2-64-0001, B


CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting and Small Power Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.5 Check existing cable encountered in the trench shall be realigned to


accommodate the new cable.
3.6 Check and verify laying arrangement of cable.
3.7 Check and verify size, type and voltage rating of laid cables.

3.8 Check cables shall be laid in parallel with no twists or crossovers.

3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.

3.10 Check the cleats for single core cables are being spaced not more than 650mm.

3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
3.12 or galvanized steel pipe.

3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
HV Cables pulling with winch operation shall be not more than maximum
3.14 allowable tension in line with cable manufacturer recommendation.

3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
Check the cable passing through the MCT cable shall perpendicular to the frame
3.17 for a minimum distance of 100mm either side of the frame.

3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout

3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.

3.21 Confirm the bending radius of cables correct

3.22 Confirm no over lapping of cables inside trench & underneath of the panels.

Check end caps shall be provided at both the ends to prevent ingress of
3.23 moisture after cable laying.

Page 133 of 134 GF-4172-QC-EI-FM-0005, Rev. 4


CHECKLIST FOR UNDERGROUND CABLE
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172

RFI NO. 4172-2-RFI-F-0644 SYSTEM DK960-201


REPORT NO. GF-4172-QC-EI-FM-0005/ SUB-SYSTEM DK960-201-02

LOCATION Inside DK960/ DK961 RTU Station DISCIPLINE ELECTRICAL

CABLE TAG NUMBER DK965-ELP-015, DK965-ELP-002, DK965-ELP-003, DK965-EL-101, DK965-EL-101/1, DK965-EL-101/2 &
DK965-ELP-008

DK960-ELP-006 (2C x 6 Sq. mm. / B9), DK960-ELP-007 (2C x 6 Sq. mm. / B9),
DK960-EL-001 ((2C+E) x 4 Sq. mm. / B3), DK960-EL-001/1 ((3C+E) x 2.5 Sq. mm. / B3),
CABLE SIZE / TYPE DK960-EL-001/2 ((3C+E) x 2.5 Sq. mm. / B3), DK960--ELP-011 (2C x 6 Sq. mm. / B9) &
DK960--ELP-012(2C x 6 Sq. mm. / B9)

DRAWING NO. DK960-2-64-0001, B


CABLE SCHEDULE 4172-WLHDTYP-2-37-0001, Rev.1
APPLICATION / SERVICE Lighting and Small Power Cables

SI NO DESCRIPTION OK NOT N/A REMARKS


OK

3.24 Check
laying
and record cable continuity and insulation resistance test after cable

4.0 POST-INSTALLATION INSPECTION

4.1 Check sand bedding done after cable laying

4.2 Check and ensure cable duct banks have been sealed properly on both ends
4.3 Check and ensure cable protection tiles are provided

4.4 Check and ensure warning tapes are provided

4.5 Check final backfilling done

Check colored concrete are provided along the cable route in paved area
4.6 (Red concrete for electrical and Green Concrete for instrument)

4.7 Check route marker are provided.

4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.

4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :

ACCEPTED BY GALFAR CONSTR GALFAR QA/QC TPI QATAR PETROLEUM

SIGNATURE

NAME Rajesh J Suresh P R

DESIGNATION Engineer QC-E

DATE

Page 134 of 134 GF-4172-QC-EI-FM-0005, Rev. 4

You might also like