LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172
1.2 Check and confirm installation of cable tray / ladder / trunking / conduit
completed and inspected
1.3 Ensure cable tray / ladder / trunking / conduit is clean and free from physical
damage, sharp edge
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
2.7 Confirm aboveground cable entry from stub-up and Crossing shall not
obstruct/block the maintenance access way.
2.8 Check cables shall be laid in cable trays inside the control room to avoid the
direct contact with concrete.
HV Cables pulling with winch operation shall be not more than maximum
2.9 allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
2.12 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and confirm cable tag numbers are correct and provided at the specified
2.13 interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.17 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
Check cables laying in trays / conduit shall not block any walk way /
2.21
maintenance access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable
laying
3.1 Check and ensure duct / wall openings have been sealed properly
3.3 Check MCT installation and Cable transits (MCT) shall be reinstated after the
final cable laying.
REMARKS / COMMENTS :
SIGNATURE
DATE
CABLE SIZE / TYPE (3C+E) x 2.5 SQ.MM. /B7 & (2C+E) x 2.5 SQ.MM. /B3
1.2 Check and confirm installation of cable tray / ladder / trunking / conduit
completed and inspected
1.3 Ensure cable tray / ladder / trunking / conduit is clean and free from physical
damage, sharp edge
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
2.7 Confirm aboveground cable entry from stub-up and Crossing shall not
obstruct/block the maintenance access way.
2.8 Check cables shall be laid in cable trays inside the control room to avoid the
direct contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
CABLE SIZE / TYPE (3C+E) x 2.5 SQ.MM. /B7 & (2C+E) x 2.5 SQ.MM. /B3
2.12 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and confirm cable tag numbers are correct and provided at the specified
2.13 interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.17 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
Check cables laying in trays / conduit shall not block any walk way /
2.21 maintenance access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable
laying
3.1 Check and ensure duct / wall openings have been sealed properly
Check MCT installation and Cable transits (MCT) shall be reinstated after the
3.3 final cable laying.
CABLE SIZE / TYPE (3C+E) x 2.5 SQ.MM. /B7 & (2C+E) x 2.5 SQ.MM. /B3
REMARKS / COMMENTS :
SIGNATURE
DATE
1.2 Check and confirm installation of cable tray / ladder / trunking / conduit
completed and inspected
1.3 Ensure cable tray / ladder / trunking / conduit is clean and free from physical
damage, sharp edge
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
2.7 Confirm aboveground cable entry from stub-up and Crossing shall not
obstruct/block the maintenance access way.
2.8 Check cables shall be laid in cable trays inside the control room to avoid the
direct contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
2.12 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and confirm cable tag numbers are correct and provided at the specified
2.13 interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.17 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
Check cables laying in trays / conduit shall not block any walk way /
2.21 maintenance access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable
laying
3.1 Check and ensure duct / wall openings have been sealed properly
Check MCT installation and Cable transits (MCT) shall be reinstated after the
3.3 final cable laying.
REMARKS / COMMENTS :
SIGNATURE
DATE
APPLICATION / SERVICE 33kV Ring Main Unit (36-RMU-1001) to 33/0.42kV Distribution Transformer (36-TR-1001)
1.2 Check and confirm installation of cable tray / ladder / trunking / conduit
completed and inspected
1.3 Ensure cable tray / ladder / trunking / conduit is clean and free from physical
damage, sharp edge
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
2.7 Confirm aboveground cable entry from stub-up and Crossing shall not
obstruct/block the maintenance access way.
2.8 Check cables shall be laid in cable trays inside the control room to avoid the direct
contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
APPLICATION / SERVICE 33kV Ring Main Unit (36-RMU-1001) to 33/0.42kV Distribution Transformer (36-TR-1001)
2.12 Check end caps shall be provided at both the ends to prevent ingress of moisture
after cable laying.
Check and confirm cable tag numbers are correct and provided at the specified
2.13 interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.17 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
Check cables laying in trays / conduit shall not block any walk way / maintenance
2.21 access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable laying
3.1 Check and ensure duct / wall openings have been sealed properly
Check MCT installation and Cable transits (MCT) shall be reinstated after the final
3.3 cable laying.
APPLICATION / SERVICE 33kV Ring Main Unit (36-RMU-1001) to 33/0.42kV Distribution Transformer (36-TR-1001)
REMARKS / COMMENTS :
SIGNATURE
DATE
APPLICATION / SERVICE Cable from Battery Isolation Box A & B To Battery Bank A & B
1.3 Ensure cable tray / ladder / trunking / conduit is clean and free from physical
damage, sharp edge
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
2.7 Confirm aboveground cable entry from stub-up and Crossing shall not
obstruct/block the maintenance access way.
2.8 Check cables shall be laid in cable trays inside the control room to avoid the direct
contact with concrete.
HV Cables pulling with winch operation shall be not more than maximum
2.9 allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
Check the cable passing through the MCT cable shall perpendicular to the frame
2.11
for a minimum distance of 100mm either side of the frame.
APPLICATION / SERVICE Cable from Battery Isolation Box A & B To Battery Bank A & B
2.12 Check end caps shall be provided at both the ends to prevent ingress of moisture
after cable laying.
Check and confirm cable tag numbers are correct and provided at the specified
2.13 interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.17 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
Check cables laying in trays / conduit shall not block any walk way / maintenance
2.21 access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable laying
3.1 Check and ensure duct / wall openings have been sealed properly
3.3 Check MCT installation and Cable transits (MCT) shall be reinstated after the final
cable laying.
APPLICATION / SERVICE Cable from Battery Isolation Box A & B To Battery Bank A & B
REMARKS / COMMENTS :
SIGNATURE
DATE
APPLICATION / SERVICE Cable from Existing 240V AC UPS DB (31-DB-0064), Feeder 64 & 65 To Operator Workstation PDU-4
& PDU-5
1.3 Ensure cable tray / ladder / trunking / conduit is clean and free from physical
damage, sharp edge
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
2.7 Confirm aboveground cable entry from stub-up and Crossing shall not
obstruct/block the maintenance access way.
2.8 Check cables shall be laid in cable trays inside the control room to avoid the direct
contact with concrete.
HV Cables pulling with winch operation shall be not more than maximum
2.9 allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
APPLICATION / SERVICE Cable from Existing 240V AC UPS DB (31-DB-0064), Feeder 64 & 65 To Operator Workstation PDU-4
& PDU-5
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
APPLICATION / SERVICE Cable from Existing 240V AC UPS DB (31-DB-0064), Feeder 64 & 65 To Operator Workstation PDU-4
& PDU-5
2.12 Check end caps shall be provided at both the ends to prevent ingress of moisture
after cable laying.
Check and confirm cable tag numbers are correct and provided at the specified
2.13 interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.17 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
Check cables laying in trays / conduit shall not block any walk way / maintenance
2.21
access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable laying
3.1 Check and ensure duct / wall openings have been sealed properly
3.3 Check MCT installation and Cable transits (MCT) shall be reinstated after the final
cable laying.
APPLICATION / SERVICE Cable from Existing 240V AC UPS DB (31-DB-0064), Feeder 64 & 65 To Operator Workstation PDU-4
& PDU-5
REMARKS / COMMENTS :
SIGNATURE
DATE
1.3 Ensure cable tray / ladder / trunking / conduit is clean and free from physical
damage, sharp edge
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
2.7 Confirm aboveground cable entry from stub-up and Crossing shall not
obstruct/block the maintenance access way.
Check cables shall be laid in cable trays inside the control room to avoid the
2.8
direct contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
2.12 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
2.13 Check and confirm cable tag numbers are correct and provided at the specified
interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.17 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
Check cables laying in trays / conduit shall not block any walk way /
2.21 maintenance access of any process area.
2.22 Check
laying
and record cable continuity and insulation resistance test after cable
3.1 Check and ensure duct / wall openings have been sealed properly
3.3 Check MCT installation and Cable transits (MCT) shall be reinstated after the
final cable laying.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK N/A REMARKS
OK
1.2 Check and confirm installation of cable tray / ladder / trunking / conduit
completed and inspected
Ensure cable tray / ladder / trunking / conduit is clean and free from physical
1.3 damage, sharp edge
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
2.7 Confirm aboveground cable entry from stub-up and Crossing shall not
obstruct/block the maintenance access way.
Check cables shall be laid in cable trays inside the control room to avoid the
2.8 direct contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
Check the cable passing through the MCT cable shall perpendicular to the frame
2.11 for a minimum distance of 100mm either side of the frame.
NOT
SI NO DESCRIPTION OK N/A REMARKS
OK
2.12 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
2.13 Check and confirm cable tag numbers are correct and provided at the specified
interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.17 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
Check cables laying in trays / conduit shall not block any walk way /
2.21 maintenance access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable
laying
3.1 Check and ensure duct / wall openings have been sealed properly
3.3 Check MCT installation and Cable transits (MCT) shall be reinstated after the
final cable laying.
NOT
SI NO DESCRIPTION OK N/A REMARKS
OK
REMARKS / COMMENTS :
SIGNATURE
DATE
1.3 Ensure cable tray / ladder / trunking / conduit is clean and free from physical
damage, sharp edge
1.4 Check cable drum placing shall be on solid flat surface
2.0 ABOVEGROUND CABLE LAYING INSPECTION
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
Confirm aboveground cable entry from stub-up and Crossing shall not
2.7 obstruct/block the maintenance access way.
2.8 Check cables shall be laid in cable trays inside the control room to avoid the
direct contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
2.12 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and confirm cable tag numbers are correct and provided at the specified
2.13 interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.17 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
Check cables laying in trays / conduit shall not block any walk way /
2.21 maintenance access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable
laying
3.1 Check and ensure duct / wall openings have been sealed properly
Check MCT installation and Cable transits (MCT) shall be reinstated after the
3.3 final cable laying.
REMARKS / COMMENTS :
SIGNATURE
DATE
36-EL-0013 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0015 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0017 ((3C+E) x 6
CABLE TAG NUMBER Sq. mm. / B9), 36-EL-0018 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0034 ((2C+E) x 6 Sq. mm. / B3), 36-EL-
0035 ((2C+E) x 6 Sq. mm. / B6), 36-ELP-0119 ((4C+E) x 10 Sq. mm. / B6), 36-ELP-0128 ((2C+E) x 6 Sq.
mm. / B3), 36-ELP-0129 ((2C+E) x 6 Sq. mm. / B2), 36-ELP-0129/2 ((2C+E) x 4 Sq. mm. / B3) 36-ELP-
0147 ((2C+E) x 6 Sq. mm. / B3), 36-EL-0037 ((2C+E) x 6 Sq. mm. / B3) & 36-EL-0038 ((2C+E) x 6 Sq.
CABLE SIZE / TYPE mm. / B3)
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.2 Check and confirm installation of cable tray / ladder / trunking / conduit
completed and inspected
Ensure cable tray / ladder / trunking / conduit is clean and free from physical
1.3 damage, sharp edge
1.4 Check cable drum placing shall be on solid flat surface
2.0 ABOVEGROUND CABLE LAYING INSPECTION
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
2.7 Confirm aboveground cable entry from stub-up and Crossing shall not
obstruct/block the maintenance access way.
Check cables shall be laid in cable trays inside the control room to avoid the
2.8 direct contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
36-EL-0013 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0015 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0017 ((3C+E) x 6
CABLE TAG NUMBER Sq. mm. / B9), 36-EL-0018 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0034 ((2C+E) x 6 Sq. mm. / B3), 36-EL-
0035 ((2C+E) x 6 Sq. mm. / B6), 36-ELP-0119 ((4C+E) x 10 Sq. mm. / B6), 36-ELP-0128 ((2C+E) x 6 Sq.
mm. / B3), 36-ELP-0129 ((2C+E) x 6 Sq. mm. / B2), 36-ELP-0129/2 ((2C+E) x 4 Sq. mm. / B3) 36-ELP-
0147 ((2C+E) x 6 Sq. mm. / B3), 36-EL-0037 ((2C+E) x 6 Sq. mm. / B3) & 36-EL-0038 ((2C+E) x 6 Sq.
CABLE SIZE / TYPE mm. / B3)
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
Check end caps shall be provided at both the ends to prevent ingress of
2.12 moisture after cable laying.
2.13 Check and confirm cable tag numbers are correct and provided at the specified
interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
Check segregation from power cable, control cable, IS & non IS cables shall be
2.17
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
2.21 Check cables laying in trays / conduit shall not block any walk way /
maintenance access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable
laying
3.1 Check and ensure duct / wall openings have been sealed properly
36-EL-0013 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0015 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0017 ((3C+E) x 6
CABLE TAG NUMBER Sq. mm. / B9), 36-EL-0018 ((3C+E) x 6 Sq. mm. / B9), 36-EL-0034 ((2C+E) x 6 Sq. mm. / B3), 36-EL-
0035 ((2C+E) x 6 Sq. mm. / B6), 36-ELP-0119 ((4C+E) x 10 Sq. mm. / B6), 36-ELP-0128 ((2C+E) x 6 Sq.
mm. / B3), 36-ELP-0129 ((2C+E) x 6 Sq. mm. / B2), 36-ELP-0129/2 ((2C+E) x 4 Sq. mm. / B3) 36-ELP-
0147 ((2C+E) x 6 Sq. mm. / B3), 36-EL-0037 ((2C+E) x 6 Sq. mm. / B3) & 36-EL-0038 ((2C+E) x 6 Sq.
CABLE SIZE / TYPE mm. / B3)
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.3 Check MCT installation and Cable transits (MCT) shall be reinstated after the
final cable laying.
REMARKS / COMMENTS :
SIGNATURE
DATE
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
Confirm aboveground cable entry from stub-up and Crossing shall not
2.7 obstruct/block the maintenance access way.
2.8 Check cables shall be laid in cable trays inside the control room to avoid the
direct contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
Check end caps shall be provided at both the ends to prevent ingress of
2.12 moisture after cable laying.
Check and confirm cable tag numbers are correct and provided at the specified
2.13 interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.16 Confirm the bending radius of cables correct.
2.17 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
2.21 Check cables laying in trays / conduit shall not block any walk way /
maintenance access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable
laying
3.1 Check and ensure duct / wall openings have been sealed properly
3.3 Check MCT installation and Cable transits (MCT) shall be reinstated after the
final cable laying.
REMARKS / COMMENTS :
SIGNATURE
DATE
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
Confirm aboveground cable entry from stub-up and Crossing shall not
2.7 obstruct/block the maintenance access way.
2.8 Check cables shall be laid in cable trays inside the control room to avoid the
direct contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
Check end caps shall be provided at both the ends to prevent ingress of
2.12 moisture after cable laying.
2.13 Check and confirm cable tag numbers are correct and provided at the specified
interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.17 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
2.21 Check cables laying in trays / conduit shall not block any walk way /
maintenance access of any process area.
Check and record cable continuity and insulation resistance test after cable
2.22 laying
3.1 Check and ensure duct / wall openings have been sealed properly
3.3 Check MCT installation and Cable transits (MCT) shall be reinstated after the
final cable laying.
REMARKS / COMMENTS :
SIGNATURE
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.2 Check and confirm installation of cable tray / ladder / trunking / conduit
completed and inspected
Ensure cable tray / ladder / trunking / conduit is clean and free from physical
1.3 damage, sharp edge
1.4 Check cable drum placing shall be on solid flat surface
2.0 ABOVEGROUND CABLE LAYING INSPECTION
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
2.7 Confirm aboveground cable entry from stub-up and Crossing shall not
obstruct/block the maintenance access way.
Check cables shall be laid in cable trays inside the control room to avoid the
2.8 direct contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
2.12 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
2.13 Check and confirm cable tag numbers are correct and provided at the specified
interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
Check segregation from power cable, control cable, IS & non IS cables shall be
2.17
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
2.21 Check cables laying in trays / conduit shall not block any walk way /
maintenance access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable
laying
3.1 Check and ensure duct / wall openings have been sealed properly
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
Check MCT installation and Cable transits (MCT) shall be reinstated after the
3.3 final cable laying.
REMARKS / COMMENTS :
SIGNATURE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
DATE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.3 Ensure cable tray / ladder / trunking / conduit is clean and free from physical
damage, sharp edge
1.4 Check cable drum placing shall be on solid flat surface
2.0 ABOVEGROUND CABLE LAYING INSPECTION
2.1 Check and confirm material inspection of cables are completed
2.2 Check for any physical damage of cables
2.3 Check and verify laying arrangement of cables
2.4 Check cables shall be laid in parallel with no twists or crossovers.
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
2.7 Confirm aboveground cable entry from stub-up and Crossing shall not
obstruct/block the maintenance access way.
Check cables shall be laid in cable trays inside the control room to avoid the
2.8 direct contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
2.12 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
2.13 Check and confirm cable tag numbers are correct and provided at the specified
interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.16 Confirm the bending radius of cables correct.
Check segregation from power cable, control cable, IS & non IS cables shall be
2.17 provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
2.20 Ensure cables are dressed / clipped with regard to neatness.
Check cables laying in trays / conduit shall not block any walk way /
2.21 maintenance access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable
laying
3.1 Check and ensure duct / wall openings have been sealed properly
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
3.3 Check MCT installation and Cable transits (MCT) shall be reinstated after the
final cable laying.
REMARKS / COMMENTS :
SIGNATURE
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
DATE
LOCATION JCWF Plant Area (Nitrogen Shelter and Shelter for DISCIPLINE Electrical
Instrument Air Package)
CABLE TAG NUMBER 36-EL-0014/1, 36-EL-0015/4, 36-EL-0015/5, 36-EL-0015/6, 36-EL-0015/7, 36-EL-0015/8, 36-EL-
0015/9 ((3C+E) x 2.5 Sq.mm.) &
36-EL-0034/3, 36-EL-0034/4, 36-EL-0035/6, 36-EL-0035/7, 36-EL-0035/8, 36-EL-0035/9 ((2C+E) x
CABLE SIZE / TYPE 2.52.5 Sq.mm.)
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
1.2 Check and confirm installation of cable tray / ladder / trunking / conduit
completed and inspected
1.3 Ensure cable tray / ladder / trunking / conduit is clean and free from physical
damage, sharp edge
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
Confirm aboveground cable entry from stub-up and Crossing shall not
2.7
obstruct/block the maintenance access way.
2.8 Check cables shall be laid in cable trays inside the control room to avoid the
direct contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
LOCATION JCWF Plant Area (Nitrogen Shelter and Shelter for DISCIPLINE Electrical
Instrument Air Package)
CABLE TAG NUMBER 36-EL-0014/1, 36-EL-0015/4, 36-EL-0015/5, 36-EL-0015/6, 36-EL-0015/7, 36-EL-0015/8, 36-EL-
0015/9 ((3C+E) x 2.5 Sq.mm.) &
36-EL-0034/3, 36-EL-0034/4, 36-EL-0035/6, 36-EL-0035/7, 36-EL-0035/8, 36-EL-0035/9 ((2C+E) x
CABLE SIZE / TYPE 2.52.5 Sq.mm.)
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
2.11 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
LOCATION JCWF Plant Area (Nitrogen Shelter and Shelter for DISCIPLINE Electrical
Instrument Air Package)
CABLE TAG NUMBER 36-EL-0014/1, 36-EL-0015/4, 36-EL-0015/5, 36-EL-0015/6, 36-EL-0015/7, 36-EL-0015/8, 36-EL-
0015/9 ((3C+E) x 2.5 Sq.mm.) &
36-EL-0034/3, 36-EL-0034/4, 36-EL-0035/6, 36-EL-0035/7, 36-EL-0035/8, 36-EL-0035/9 ((2C+E) x
CABLE SIZE / TYPE 2.52.5 Sq.mm.)
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
2.12 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
2.13 Check and confirm cable tag numbers are correct and provided at the specified
interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
Check segregation from power cable, control cable, IS & non IS cables shall be
2.17 provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
2.21 Check cables laying in trays / conduit shall not block any walk way /
maintenance access of any process area.
2.22 Check and record cable continuity and insulation resistance test after cable
laying
3.1 Check and ensure duct / wall openings have been sealed properly
Check MCT installation and Cable transits (MCT) shall be reinstated after the
3.3 final cable laying.
LOCATION JCWF Plant Area (Nitrogen Shelter and Shelter for DISCIPLINE Electrical
Instrument Air Package)
CABLE TAG NUMBER 36-EL-0014/1, 36-EL-0015/4, 36-EL-0015/5, 36-EL-0015/6, 36-EL-0015/7, 36-EL-0015/8, 36-EL-
0015/9 ((3C+E) x 2.5 Sq.mm.) &
36-EL-0034/3, 36-EL-0034/4, 36-EL-0035/6, 36-EL-0035/7, 36-EL-0035/8, 36-EL-0035/9 ((2C+E) x
CABLE SIZE / TYPE 2.52.5 Sq.mm.)
NOT
SI NO DESCRIPTION OK OK N/A REMARKS
REMARKS / COMMENTS :
SIGNATURE
DATE
APPLICATION / SERVICE Cables from 36-A-7001-G-01 To 36-CB-1001-73 at JCWF Substation EDG Room
1.2 Check and confirm installation of cable tray / ladder / trunking / conduit
completed and inspected
1.3 Ensure cable tray / ladder / trunking / conduit is clean and free from physical
damage, sharp edge
2.5 Check single core cable laid in trefoil formation with non-magnetic clamps.
2.6 Check the cleats for single core cables are being spaced not more than 650mm.
2.7 Confirm aboveground cable entry from stub-up and Crossing shall not
obstruct/block the maintenance access way.
Check cables shall be laid in cable trays inside the control room to avoid the
2.8
direct contact with concrete.
2.9 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
2.10 Check the cable ends shall be protected against ingress of moisture / dust.
Check the cable passing through the MCT cable shall perpendicular to the frame
2.11 for a minimum distance of 100mm either side of the frame.
APPLICATION / SERVICE Cables from 36-A-7001-G-01 To 36-CB-1001-73 at JCWF Substation EDG Room
2.12 Check end caps shall be provided at both the ends to prevent ingress of
moisture after cable laying.
Check and confirm cable tag numbers are correct and provided at the specified
2.13 interval.
2.14 Check and verify size, type and rating of laid cables.
2.15 Check and confirm all cables are laid as per cable schedule / layout.
2.17 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
2.18 Check and ensure cable clamp / cleat installed as per AFC drawing.
2.19 Check PVC coated SS tie is used for cable dressing in outdoor areas.
Check cables laying in trays / conduit shall not block any walk way /
2.21 maintenance access of any process area.
2.22 Check
laying
and record cable continuity and insulation resistance test after cable
3.1 Check and ensure duct / wall openings have been sealed properly
3.3 Check MCT installation and Cable transits (MCT) shall be reinstated after the
final cable laying.
APPLICATION / SERVICE Cables from 36-A-7001-G-01 To 36-CB-1001-73 at JCWF Substation EDG Room
REMARKS / COMMENTS :
SIGNATURE
DATE