Professional Documents
Culture Documents
LAYING WORKS
CONTRACT NO.: CONTRACT TITLE: EPIC FOR CO2 WATER ALTERNATING GAS
GC19108100 (WAG) INJECTION PILOT PROJECT AT DUKHAN PROJECT NO.: 4172
1.4 Check cable trench depth and width as per AFC drawing.
1.5 Check cable trench bottom is flat and sand bedding is correct
1.6 Check & ensure cable trench is clean and free from stones, debris & other
unwanted materials.
Check Excavated material shall be deposited a minimum of 1 meter away from
1.7 the trench.
2.2 Ensure all the duct banks, crossings and tunnel works (Whichever applicable) are
completed prior to laying of cables.
2.3 Check and ensure approved cable duct is being installed at site
2.4 Inside the duct bank Spare sleeves are provided with pulling ropes, where
applicable
2.5 Check duct bank location and dimensional check-up for the installed ducts along
the cable route.
2.6 Check duct outer edge for sharpness & duct cleanliness
Check and ensure that cables shall not contacted with ground while pulling the
3.3 cable.
3.7 Check and verify size, type and voltage rating of laid cables.
3.9 Check single core cable laid in trefoil formation with non-magnetic clamps.
3.10 Check the cleats for single core cables are being spaced not more than 650mm.
3.11 Confirm cable crossing under the concrete cable shall be protect with uPVC pipe.
3.12 Confirm cable emerging from the soil shall be laid inside Rigid PVC (Schedule 40)
or galvanized steel pipe.
3.13 Confirm cables emerging from ground / Stub up cable opening shall be located
nearest point (underneath gland plate) of field equipment
3.14 HV Cables pulling with winch operation shall be not more than maximum
allowable tension in line with cable manufacturer recommendation.
3.15 Check the cable ends shall be protected against ingress of moisture / dust.
3.16 Check cable transits (MCT) shall be reinstated after the final cable laying.
3.17 Check the cable passing through the MCT cable shall perpendicular to the frame
for a minimum distance of 100mm either side of the frame.
3.18 Check and confirm cable tag numbers are correct and provided every 5 meter
intervals
3.19 Check and confirm all cables are laid as per cable schedule / layout
3.20 Check segregation from power cable, control cable, IS & non IS cables shall be
provided properly.
3.22 Confirm no over lapping of cables inside trench & underneath of the panels.
3.24 Check and record cable continuity and insulation resistance test after cable
laying
4.2 Check and ensure cable duct banks have been sealed properly on both ends
4.3 Check and ensure cable protection tiles are provided
4.8 Check route marker installation on straight routes distances shall not exceeding
50 meter and also provide at every direction change.
4.9 Check substitute material and any finished surface or paving shall be reinstated.
REMARKS / COMMENTS :
SIGNATURE
NAME
DESIGNATION
DATE