APPENDIX II-1 CONTRACT SCHEDULE

ID TASK NAME DURATION START FINISH


SONG DOC FIELD ABANDONMENT PROJECT
1 KEY MILESTONE
1.1 Contract awarded (tentatively)
1.2 Handover of SDA WHP from CLIENT
1.3 Offshore works commencement
2 ENGINEERING
2.1 Well Plugging and Abandonment (Wells P&A)
2.1.1 P&A engineering and design
2.1.2 Dossier approved by MWS/CA
2.2 SDA WHP removal
2.2.1 Topside and Jacket removal engineering and design
2.2.2 Transportation engineering and design
2.2.3 Offload to yard engineering and design
2.2.4 Dossier approved by MWS/CA
3 PROCUREMENT AND SERVICES
3.1 Procurement and Services for P&A wells
3.2 Procurement and Services for SDA WHP removal
4 ONSHORE WORKS AND PREPARATION
4.1 Preparation for P&A wells
4.2 Preparation for SDA WHP removal
4.2.1 Onshore fabrication
Set up crane barge, transportation barge with related equipment & service at the
4.2.2
port
4.2.3 Set up and arrangement for storage yard/workshop
5 OFFSHORE WORKS
5.1 Offshore inspection and survey for engineering (if any)
5.2 Pre-abandonment survey
5.3 Tentative Schedule for P&A wells
5.3.1 Mobilization 5
5.3.2 Batch P&A Well SD-4P & SC-1A together at slot #7 12.8
5.3.3 Batch P&A Well TG-2A & NC-3P together at slot #9 13.8
5.3.4 Batch P&A Well NH-1P & BTG-1A together at slot #6 12.1
5.3.5 P&A Well NH-2P at slot #8 7.5
5.3.6 P&A Well SD‐1P at slot #5 6.6
5.3.7 P&A Well SD-2P at slot #4 6.6
5.3.8 P&A Well NC-1P at slot#3 6.6
5.3.9 P&A Well NC-2P at slot# 2 6.6
5.3.10 P&A Well SD-3P at slot# 1 6.6
5.3.11 ROV as-built survey
5.3.12 Demobilization 5
5.3.13 Tranportation of all cut conductors to shore
5.4 SDA WHP removal
5.4.1 Mobilization
Topside removal (the sequence & number of actitivies will depend on the
5.4.2
methodstatment)
5.4.2.1 Crane barge setup at location
5.4.2.2 Cutting & Lift the topside
5.4.2.3 Seafastening the topside on the transportation barge
5.4.2.4 Transportation to shore base
Jacket/Subsea Template removal (the sequence & number of actitivies will
5.4.3
depend on the methodstatment)
5.4.3.1 Crane barge setup at location
5.4.3.2 Cutting & Lift the jacket piles @ min 3m under seabed
5.4.3.3 Cutting & Lift the jacket part(s)
5.4.3.4 Subsea Template removal
5.4.3.5 Seafastening the removed jacket part(s) on the transportation barge(s)
5.4.3.6 Transportation to shore

1 OF 2
APPENDIX II-1 CONTRACT SCHEDULE

ID TASK NAME DURATION START FINISH


5.4.4 Crane Barge clean up and demobilization
5.4.5 As built survey
5.4.5.1 Survey vessel mobilization
5.4.5.2 Site survey & debris removal
5.4.5.3 Survey vessel Demobilization
OFFLOAD & TRANSPORTATION THE REMOVED ITEMS TO
6
DESIGNATED LOCATION
6.1 Set up barge and trailer/lifting system
6.2 Offload and transport all cut conductors to the designed location
6.3 Offload and transport the removed topside to the designed location
Offload and transport the removed Jacket, piles and Subsea template to the
6.4
designed location
7 JKT AND TOPSIDE STORAGE/ PROJECT COMPLETION
7.1 Storage of the removed items up to 6 months 6 mths
7.2 Option of storage of the removed items to additional 6 months 6 mths
7.3 Final documentation
8 Warranty period 12 mths