Professional Documents
Culture Documents
Sub-contractor Name:
Wet Visible Magnetic Particle Test Procedure for Piping & Pipline
This procedures is to be reviewed and approved by NDE Level-III. NDE Level-III to be certified in accordance to ASNT
or ACCP or ISO 9712 or PCN
Magnetic Particle Inspection Test Procedure
Document No : B-QAC-PRO-210-39161
Revision A
Revision History
Revision Changes
Holds
Hold No. Location Description
SARPI Page 2 of 12
Magnetic Particle Inspection Test Procedure
Document No : B-QAC-PRO-210-39161
Revision A
Contents
REVISION HISTORY 2
CONTENTS 3
ABBREVIATIONS 4
1 INTRODUCTION 5
2 PURPOSE OF THE DOCUMENT 5
3 SCOPE OF DOCUMENT 5
4 DEFINITIONS 6
5 REFERENCE DOCUMENTS 6
5.1 Project Specifications 6
5.2 Codes 6
5.2.1 Algerian Codes and Standards 6
5.2.2 International Codes and Standards 7
6 RESPONSIBILITY 8
6.1 Construction representative: 8
6.2 QA/QC Coordinator 8
6.3 QC Engineer: 8
6.4 NDT Welding Inspector 9
7 EXECUTION TECHNIQUE 9
7.1 Surface preparation 9
7.2 Magnetizing Equipment 9
7.2.1 Yoke 9
7.2.2 Lifting power of yoke 9
7.3 Magnetic Particle Materials 10
7.3.1 Examination medium 10
7.3.2 Suspension medium 10
7.3.3 Particle color 10
7.4 Magnetizing Field Adequacy and Direction 10
7.5 Magnetic Particle Examination Procedure 10
7.6 Interpretation of the indications 11
7.7 Acceptance Criteria. 11
7.8 Demagnetization 11
7.9 Recording 12
7.10 Qualification of the personnel 12
8 LIST OF VERIFYING DOCUMENTS 12
Sub-contractor to mention the all essential variable as per Table T-721 of Article-7, ASME BPVC SEC V ED 2019 and mention
. number of this procedure against each variable.
applicable paragraph
SARPI Page 3 of 12
Magnetic Particle Inspection Test Procedure
Document No : B-QAC-PRO-210-39161
Revision A
Abbreviations
SC Sub-Contractor
CR Construction Representative
RT Radiographic Examination
1 INTRODUCTION
SARPI hereafter referred as Subcontractor will execute the (Gathering Pipelines,
Wellheads & Manifolds MEI Works) Subcontract on behalf of PETROFAC referred
hereafter as Contractor.
Whereas the Groupement ISARENE, hereinafter collectively referred to as “client” or
“COMPANY” have awarded Petrofac a Contract for EPCC of Ain Tsila Development
(hereinafter referred to as the “Contract” or “Main Contract”).
SARPI Page 5 of 12
Magnetic Particle Inspection Test Procedure
Document No : B-QAC-PRO-210-39161
Revision A
4 DEFINITIONS
The terms and definitions as used within this document are listed below.
“shall” or “must” indicates that the specified action is mandatory (i.e. must be done by
the specified action party)
5 REFERENCE DOCUMENTS
Add :
5.1 Project Specifications 1) Approved ITP for Pipeline
A-PLE-SPE-200-30010 - Pipeline Construction Specification 2) Approved ITP of Piping
Algerian LPG Pipeline Règles de Sécurité pour les Canalisations de Transport D’Hydrocarbures
Liquides liquéfies sous pression (Safety Regulations for the Transport by
Regulations
Pipeline of Hydrocarbons Liquefied Under Pressure)
SARPI Page 6 of 12
Magnetic Particle Inspection Test Procedure
Document No : B-QAC-PRO-210-39161
Revision A
SARPI Page 7 of 12
Magnetic Particle Inspection Test Procedure
Document No : B-QAC-PRO-210-39161
Revision A
6 RESPONSIBILITY
Responsibilities of project personnel related to this procedure are described as below.
6.3 QC Engineer:
The Quality Control Engineer shall be responsible for the following:
Review all relevant documentations, test reports, calibration certificates issued by
parties involved such as surveyor, QC inspectors and submit the records to the
Contractor/COMPANY as required.
Review all material certificate with Project Requirements
Organize and allocate inspection works to the Quality Control Inspectors.
Accompany Contractor & COMPANY representative if required, carrying out
inspections and release hold points.
Sign and obtain signatures from Contractor & COMPANY on the various forms
and verifying documents as required.
Coordination with construction representatives.
Ensure as built information is recorded in ITR.
NCR’s if any Non-conformance observed and to follow up with Construction
representative to provide timely and appropriate root cause, Correction, and
corrective action.
Review / monitor non-conformance reports and track disposition and close out.
SARPI Page 8 of 12
Magnetic Particle Inspection Test Procedure
Document No : B-QAC-PRO-210-39161
Revision A
least 4.5 kg at the maximum pole spacing, with contact similar to what will be
used during the examination.
(c) Each direct current or permanent magnetic yoke shall have a lifting power of
at least 18 kg at the maximum pole spacing, with contact similar to what will be
used during the examination.
(d) Each weight shall be weighed with a scale from a reputable manufacturer and
stenciled with the applicable nominal weight prior to first use. A weight need only
be verified again if damaged in a manner that could have caused potential loss of
material.
SARPI Page 10 of 12
Magnetic Particle Inspection Test Procedure
Document No : B-QAC-PRO-210-39161
Revision A
7.7 Acceptance Criteria. Acceptance criteria will be as per ASME B31.3 for
Piping and API 1104 for Pipeline
Magnetic particle indications are caused by the attraction of the test media to
surface or near-surface discontinuities in the area under test. However, all such
indications are not necessarily imperfections, since excessive roughness,
magnetic permeability variations, etc., may produce nonrelevant indications.
Inadvertent accumulation of particles not related to magnetic attraction is
classified as a false indication.
Indications shall be verified as being relevant, nonrelevant, or false. Additional
surface preparation and/or other test methods may be used as needed to verify
the relevance of an indication.
An indication of an imperfection may be larger than the imperfection that causes
it; however, the size of the indication is the basis for acceptance evaluation. Only
indications that have any dimension greater than 1.5 mm (1∕16 in.) shall be
considered relevant. Add : Repair work can be started only after approved repair
procedure by Petrofac & COMPANY.
7.8 Demagnetization
When the presence of residual magnetism within the piece could interfere with
subsequent processing or usage, the piece shall be demagnetized.
Demagnetization shall always be performed on parts, which are to be welded
after the magnetic examination has been performed to prevent arc blow.
Demagnetization with yoke :
Alternating-current yokes may be used for local demagnetization by placing the
poles on the surface, moving them around the area, and slowly with drawing the
AC yoke while it is still energized.
Sub-contractor to mention Demagnetization requirement, which shall be done to remove
residual magnetism after completion of the test. Residual magnetism shall not be
exceeding 2.5mT.
Sub-Contractor to mention Post Cleaning requirements :
SARPI Page 11 of 12
-
Post cleaning is Mandatory for all surface including white paint if used to enhance color contrast . It shall be conducted as
soon as practical using a process that does not adversely affect the part
Magnetic Particle Inspection Test Procedure
Document No : B-QAC-PRO-210-39161
Revision A
7.9 Recording
The following data shall be recorded and, if so required, certified:
- Information for the identification of the item
- Demagnetization apparatuses, powders and technique utilized
- control parameters, such as the distance of the points, the intensity of the
current, etc
- Surface condition of the controlled zones
- Description of the possible indications found
- Acceptability judgment
- Norms and qualification level of the operators
The personnel who perform the magnetic particle examination shall be qualified
at least as level I according to the prescriptions ASNT/SNT-TC-1A or equivalent
standard.
The personnel, who interpret the test results, shall be qualified as level II or level
III.
A qualification certificate for each examiner shall be valid and available at site
during the project implementation. NDE Personnel shall hold current Level-2 certification (or
equivalent), specifc to weld testing for the appropriate NDE
methods to any of the following standrads as minimum
8 LIST OF VERIFYING DOCUMENTS - CSWIP (TWI, UK), - BGAS-CSWIP (TWI,UK)
- PCN (BINDT, UK), - ACCP (ASNT), -ASNT-SNT-TC-1A
Project ITR
No. ITR Number Description
Number
MAGNETIC PARTICLE INSPECTION
1 ITR-W-0109X 2045-ITR-021
REPORT
Add : All NDT personnel shall be examined to ensure that they have
natural or corrected near-distance acuity in at least one eye such that each Sub-contractor to attach the PT report format
individual is capable of reading Jaeger Number 1 test chart or equivalent at
a distance of not less than 12 in. NDT personnel for all methods shall
demonstrate the ability to differentiate among the colors used in the
method. all Vision examinations shall be administered at least annually.
Sub-contractor to mention Light Intensity Requirements as per para T-777.1, Article-7, ASME BPVC SEC V ED 2019
-
Surface discontinuities are indicated by accumulations of magnetic particles which should contrast with the examination
surface. The color of the magnetic particles shall be different than the color of the examination surface. Illumination (natural
or supplemental white light) of the examination surface is required for the evaluation of indications. The minimum light
intensity shall be 100 fc (1 076 lx). The light intensity, natural or supplemental white light source, shall be measured with a
white light meter prior to the evaluation of indications, shall be measured with a calibrated white light meter prior to the
evaluation of indications. light meter to be calibrated yearly.
SARPI Page 12 of 12