PROJECT LOOK AHEAD WK 30-31

ITEM DESCRIPTION LOCATION TARGET REL WT QTY START END DURATION MANPOWER ACCOMPLISHMENT

1 Ceiling Works GL D-F/4-5 0.17% 252sqm 4-Apr 11-Apr 7days 3 30.00%


2 Formworks and Rebar Installation of Stairs GL A-B/7-8 0.09% 4-Apr 11-Apr 7days 5 100.00%
3 Earthfill and Compaction GL D-F/1-5 0.14% 300 cum 4-Apr 11-Apr 7days 5 0.00%
4 Masonry (Ground to 3rd Floor) GL D-F/1-7 0.42% 400 sqm 4-Apr 11-Apr 7days 15 100.00%
5 Electrical Roughing-ins & Wire Installation GL D-F/1-10 0.15% 4-Apr 11-Apr 7days 8 76.00%
6 Sewer Pipe Line Roughing-ins GL D-F/1-7 0.15% 4-Apr 11-Apr 7days 5 73.53%
7 Waterline Installation and Roughing-ins GL D-F/1-7 4-Apr 11-Apr 7days 5
8 Truss Installation GL D-F/1-7 0.91% 4-Apr 11-Apr 7days 8 20.50%
9 Septic Tank GL C-D/7-8 0.03% 4-Apr 11-Apr 7days 100.00%
10 Construction of Cistern and Septic Tank GL C-D/2-3 0.04% 36cum 4-Apr 11-Apr 7days 5 50.00%
11 Straight Pipes Installation GL D-F/1-7 0.15% 4-Apr 11-Apr 7days 8 0.20%
12 Painting works GL D-F/1-7 0.14% 4-Apr 11-Apr 7days 4
13 Door & Door Jamb Installation 1-7 4-Apr 11-Apr 7days 3
14 Window Installation F/1-7 4-Apr 11-Apr 7days 5
15 Railing Installation on Stairs GL D-F/1-7 28-Mar 4-Apr 7days 5
TOTAL 2.38% 84

PROJECT LOOK AHEAD WK 31-32

ITEM DESCRIPTION LOCATION TARGET REL WT QTY START END DURATION MANPOWER ACCOMPLISHMENT
1 Ceiling Works GL D-F/4-5 0.08% 136sqm 11-Apr 18-Apr 7days 3
Formworks and Rebar Installation of Main
2 Ramp GL A-B/7-8 0.09% 11-Apr 18-Apr 7days 5
3 Earthfill and Compaction GL D-F/1-5 0.14% 300 cum 11-Apr 18-Apr 7days 5
4 Masonry (Ground to 3rd Floor) GL D-F/1-7 0.42% 400 sqm 11-Apr 18-Apr 7days 15
5 Electrical Roughing-ins & Wire Installation GL D-F/1-10 0.15% 11-Apr 18-Apr 7days 8
6 Sewer Pipe Line Roughing-ins GL D-F/1-7 0.15% 11-Apr 18-Apr 7days 5
7 Waterline Installation and Roughing-ins GL D-F/1-7 11-Apr 18-Apr 7days 5
8 Truss Installation GL D-F/1-7 0.91% 11-Apr 18-Apr 7days 8
9 Septic Tank GL C-D/7-8 11-Apr 18-Apr 7days
10 Construction of Cistern and Septic Tank GL C-D/2-3 11-Apr 18-Apr 7days 5
11 Straight Pipes Installation GL D-F/1-7 0.15% 11-Apr 18-Apr 7days 8
12 Painting works GL D-F/1-7 0.14% 11-Apr 18-Apr 7days 4
2nd & 3rd
13 Door & Door Jamb Installation Floor GL 1-7 11-Apr 18-Apr 7days 3
2nd Flr GL
14 Window Installation F/1-7 11-Apr 18-Apr 7days 5
15 Railing Installation on Stairs GL D-F/1-7 11-Apr 18-Apr 7days 5
TOTAL 2.23% 84