August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
Appendix 2 -
INSPECTION TEST PLAN FOR CS and Non- CS Welding Work No :
This ITP is applicable for CS and non-CS Welding Job No : Maintenance-PU1-STRING -1
Dwg. / Line no :
E-7054 TUBE BLOCKAGE & BAFFLE PLATE CRACK
(DISCOVERY 036)
SKT-20090153
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Disposition
Initial / Date
1.2 For filler rods, sampling PMI to be done per box/tube. H R/W
WPS / PQR
2 H R
3 Welder Qualification H R
Electrode Storage /
4 M R
Baking Condition
5 FABRICATION
6 INSTALLATION
Page 1 of 23
Page 36 of 42 The controlled copy of this document is in electronic format on the Shell Singapore Web.This hardcopy is Issued by: Dept QSC Approved
uncontrolled and was printed on 13 September 201913 August 2018 by: DMA/122
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
6.9. Reinstatement H R
6.12.Insulation By Other
Page 2 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
Appendix 2 -
INSPECTION TEST PLAN FOR CS and Non- CS Welding Work No :
This ITP is applicable for CS and non-CS Welding Job No : Maintenance-PU1-HCU
SKT-20090152
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Disposition
Initial / Date
1.2 For filler rods, sampling PMI to be done per box/tube. H R/W
WPS / PQR
2 H R
3 Welder Qualification H R
Electrode Storage /
4 M R
Baking Condition
5 FABRICATION
6 INSTALLATION
Page 3 of 23
Page 36 of 42 The controlled copy of this document is in electronic format on the Shell Singapore Web.This hardcopy is Issued by: Dept QSC Approved
uncontrolled and was printed on 13 September 201913 August 2018 by: DMA/122
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
6.9. Reinstatement H R
6.12.Insulation By Other
Page 4 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
Appendix 2 -
INSPECTION TEST PLAN FOR CS and Non- CS Welding Work No :
This ITP is applicable for CS and non-CS Welding Job No : Maintenance-PU1-HV-4
SKT-20090150
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Disposition
Initial / Date
1.2 For filler rods, sampling PMI to be done per box/tube. H R/W
WPS / PQR
2 H R ER70S-G
PEC-TD-WPS-0045 Rev.5
3 Welder Qualification H R
Electrode Storage /
4 M R
Baking Condition
5 FABRICATION
6 INSTALLATION
Page 5 of 23
Page 36 of 42 The controlled copy of this document is in electronic format on the Shell Singapore Web.This hardcopy is Issued by: Dept QSC Approved
uncontrolled and was printed on 13 September 201913 August 2018 by: DMA/122
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
6.9. Reinstatement H R
6.12.Insulation By Other
Page 6 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
Appendix 2 -
INSPECTION TEST PLAN FOR CS and Non- CS Welding Work No :
This ITP is applicable for CS and non-CS Welding Job No : Maintenance-PU1-HV-4
SKT-20090149
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Disposition
Initial / Date
1.2 For filler rods, sampling PMI to be done per box/tube. H R/W
WPS / PQR
2 H R ER70S-G
PEC-TD-WPS-0045 Rev.5
3 Welder Qualification H R
Electrode Storage /
4 M R
Baking Condition
5 FABRICATION
6 INSTALLATION
Page 7 of 23
Page 36 of 42 The controlled copy of this document is in electronic format on the Shell Singapore Web.This hardcopy is Issued by: Dept QSC Approved
uncontrolled and was printed on 13 September 201913 August 2018 by: DMA/122
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
6.9. Reinstatement H R
6.12.Insulation By Other
Page 8 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
Appendix 2 -
INSPECTION TEST PLAN FOR CS and Non- CS Welding Work No :
This ITP is applicable for CS and non-CS Welding Job No : Maintenance-PU1-HV-4
SKT-20090148
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Disposition
Initial / Date
1.2 For filler rods, sampling PMI to be done per box/tube. H R/W
WPS / PQR
2 H R ER70S-G
PEC-TD-WPS-0045 Rev.5
3 Welder Qualification H R
Electrode Storage /
4 M R
Baking Condition
5 FABRICATION
6 INSTALLATION
Page 9 of 23
Page 36 of 42 The controlled copy of this document is in electronic format on the Shell Singapore Web.This hardcopy is Issued by: Dept QSC Approved
uncontrolled and was printed on 13 September 201913 August 2018 by: DMA/122
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
6.9. Reinstatement H R
6.12.Insulation By Other
Page 10 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
Appendix 2 -
INSPECTION TEST PLAN FOR CS and Non- CS Welding Work No :
This ITP is applicable for CS and non-CS Welding Job No : Maintenance-PU1-HV-4
SKT-20090146
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Disposition
Initial / Date
1.2 For filler rods, sampling PMI to be done per box/tube. H R/W
WPS / PQR
2 H R ER70S-G
PEC-TD-WPS-0045 Rev.5
3 Welder Qualification H R
Electrode Storage /
4 M R
Baking Condition
5 FABRICATION
6 INSTALLATION
Page 36 of 42 The controlled copy of this document is in electronic format on the Shell Singapore Web.This hardcopy is Issued by: Dept QSC Approved
uncontrolled and was printed on 13 September 201913 August 2018 by: DMA/122
Page 11 of 23
Page 36 of 42 The controlled copy of this document is in electronic format on the Shell Singapore Web.This hardcopy is Issued by: Dept QSC Approved
uncontrolled and was printed on 13 September 201913 August 2018 by: DMA/122
Page 12 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
6.9. Reinstatement H R
6.12.Insulation By Other
Page 37 of 42 The controlled copy of this document is in electronic format on the Shell Singapore Web.This hardcopy is Issued by: Dept QSC Approved
uncontrolled and was printed on 13 September 201913 August 2018 by: DMA/122
Page 13 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
Appendix 2 -
INSPECTION TEST PLAN FOR CS and Non- CS Welding Work No :
This ITP is applicable for CS and non-CS Welding Job No : Maintenance-PU1-HCU
SKT-20070135
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
1.2 For filler rods, sampling PMI to be done per box/tube. H R/W
WPS / PQR
2 H R E7016
PEC-TD-WPS-0085 Rev.6
3 Welder Qualification H R
Electrode Storage /
4 M R
Baking Condition
5 FABRICATION
6 INSTALLATION
Page 14 of 23
Page 36 of 42 The controlled copy of this document is in electronic format on the Shell Singapore Web.This hardcopy is Issued by: Dept QSC Approved
uncontrolled and was printed on 13 September 201913 August 2018 by: DMA/122
Page 15 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
6.9. Reinstatement H R
6.12.Insulation By Other
Page 37 of 42 The controlled copy of this document is in electronic format on the Shell Singapore Web.This hardcopy is Issued by: Dept QSC Approved
uncontrolled and was printed on 13 September 201913 August 2018 by: DMA/122
Page 16 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
Appendix 2 -
INSPECTION TEST PLAN FOR CS and Non- CS Welding Work No :
This ITP is applicable for CS and non-CS Welding Job No : Maintenance-PU1
SKT-20070136
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
1.2 For filler rods, sampling PMI to be done per box/tube. H R/W
3 Welder Qualification H R
Electrode Storage /
4 M R
Baking Condition
5 FABRICATION
5.4 PWHT / HARDNESS / BASE LINE UTG R/W N/A R/W N/A
6 INSTALLATION
Page 17 of 23
Page 36 of 42 The controlled copy of this document is in electronic format on the Shell Singapore Web.This hardcopy is Issued by: Dept QSC Approved
uncontrolled and was printed on 13 September 201913 August 2018 by: DMA/122
Page 18 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
6.9. Reinstatement H R
6.12.Insulation By Other
Page 37 of 42 The controlled copy of this document is in electronic format on the Shell Singapore Web.This hardcopy is Issued by: Dept QSC Approved
uncontrolled and was printed on 13 September 201913 August 2018 by: DMA/122
Page 19 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
APPENDIX 3
INSPECTION TEST PLAN ( HFA PIPING ) Work No :
This ITP only applicable for Piping Class 31310, 31311, 36081 Job No :
TEST PACKAGE NO :
Dwg. / Line no :
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
1 Material Verification (PMI) H R/W Raw material
Cr+Cu+Ni<0.15%.
CS PEC-TD-WPS-0034
2 WPS / PQR H R
MONEL PEC-TD-WPS-4020
3 Welder Qualification H R
Electrode Storage /
4 M R
Baking Condition
5 FABRICATION
Page 20 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
5.3.1 RT ### R/W R/W Before and After PWHT
6 INSTALLATION
Proposed Disposition
Legend: Approved Disposition endorsed by SEPL
endorsed by PEC
Remarks: Piping Class 31310, 31311, 36081equivalent to old DEP piping class 3131 and 3608
Page 21 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
Appendix 2 -
INSPECTION TEST PLAN FOR CS and Non- CS Welding Work No : 83973569
This ITP is applicable for CS and non-CS Welding Job No : Maintenance-PU4
Dwg. / Line no : CAIR 00013032 - RENEW THE 16" CORRODED PIPE -TM3
SKT-20080144
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
1.2 For filler rods, sampling PMI to be done per box/tube. H R/W
3 Welder Qualification H R
Electrode Storage /
4 M R
Baking Condition
5 FABRICATION
6 INSTALLATION
Page 22 of 23
Shell Eastern Petroleum - Pulau Bukom Oil Refinery - Refinery Management System
August 2018
MNT_INTG-2007OP Welding Inspection
Revision: 10
CONTRACTOR SEPL
S/N ITEM Completion Remark(s)
Disposition Initial / Date Disposition
Initial / Date
6.9. Reinstatement H R
6.12.Insulation By Other