PVC INSERT INSTALLATION 2 WEEK LOOK AHEAD SCHEDULE

MIDONGPHIL CONSTRUCTION CORP,

Project Start Date 11/6/2019 (Wednesday) Display Week 2 Week 2 Week 3


Project Lead MIDONGPHIL Location: Stabling Area 11 Nov 2019 18 Nov 2019
11 12 13 14 15 16 17 18 19 20 21 22 23 24
P
WBS TASK CHAINAGE LEAD START END DAYS % DONE WORK M T W T F S S M T W T F S S
R
1 Trackworks - -

Rebar installation, Rail


1.1 Installation, Formworks, Steconfer Mon 10/28/19 Sun 11/10/19 14 75% 10
Fastener Installation
GW 4+030 - 4+097
1.2 Cleaning and Final Check Steconfer Mon 11/11/19 Mon 11/11/19 1 0% 1
Survey Pre-pour
1.3 Steconfer Mon 11/11/19 Mon 11/11/19 1 0% 1
Inspection
2 Trackworks - -

Rebar installation, Rail


2.1 Installation, Formworks, Steconfer Mon 11/11/19 Sun 11/17/19 7 0% 5
Fastener Installation
GW 4+097 - 4+160
2.2 Cleaning and Final Check Steconfer Mon 11/18/19 Mon 11/18/19 1 0% 1
Survey Pre-pour
2.3 Steconfer Mon 11/18/19 Mon 11/18/19 1 0% 1
Inspection
3 Third Rail Works - -
Layout of Insert Jig
3.1 GW 4+030 - 4+160 MidongPhil Wed 11/06/19 Fri 11/15/19 10 10% 8
Locations
3.2 Installation of PVC Inserts GW 4+030 - 4+160 MidongPhil Wed 11/06/19 Sun 11/17/19 12 5% 8
PVC Insert Installation
3.3 Pre Concrete Pouring GW 4+030 - 4+097 MidongPhil Mon 11/11/19 Mon 11/11/19 1 0% 1
Inspection
PVC Insert Installation
3.4 Pre Concrete Pouring GW 4+097 - 4+160 MidongPhil Mon 11/18/19 Mon 11/18/19 1 0% 1
Inspection
4 Concrete Pouring -

4.1 First Pour GW 4+030 - 4+097 Steconfer Tue 11/12/19 Tue 11/12/19 1 0% 1

4.2 Second Pour GW 4+097 - 4+160 Steconfer Tue 11/19/19 Tue 11/19/19 1 0% 1