Issue Date: 29/04/2019

Rev No: C09


CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
1 2nd Stage Tender Period 44w 09/07/18 31/05/19 100%

2 Statutory Authorities Application etc. 6w 18/06/19 29/07/19 100%


START ON SITE - 9TH SEPTEMBER 2019
PRACTICAL COMPLETION - 19th APRIL
2021

3 Planning Determination / CPO Process 8w 4d 25/06/19 26/08/19 100%

4 Sub-contractor Appointment / Lead-in 16w 24/06/19 14/10/19 100%


+

5 PURPLE PHASE - 82Nr FLATS / 10Nr TOWNHOUSES 89w 1d 01/07/19 19/04/21 11% 7%

6 Purple Phase - Site Establishment 20w 01/07/19 15/11/19 100% 100%

7 Secure site / erect hoarding 3w 01/07/19 19/07/19 100% 100%


8 Construction date of possession 09/09/19 09/09/19 100% 100%
9 Site accommodation / welfare 3w 09/09/19 27/09/19 100% 100% 9
10 Site surveys / investigations 2w 09/09/19 20/09/19 100% 100% 10
11 Soft strip demolition 2w 09/09/19 20/09/19 100% 100% 11
12 Demolition (approx 20Nr Dwellings) 8w 23/09/19 15/11/19 100% 100% 12
13 Site clearance / R.L Dig 4w 23/09/19 18/10/19 100% 100% 13
14 Piling mat 3w 07/10/19 25/10/19 100% 100% 14

15 P1 - Apartment Block - 82Nr Apartments 70w 2d 28/10/19 06/04/21 9% 7% 15


16 P1 - Substructures 11w 28/10/19 24/01/20 100% 100% 16
17 P1 piling - approx. 200Nr 5w 28/10/19 29/11/19 100% 100% 17
18 P1 pile caps / ground beams 7w 11/11/19 10/01/20 100% 100% 18
19 P1 Below slab drainage / services 6w 2d 18/11/19 14/01/20 100% 100% 19
20 Tower Crane Base 1w 18/11/19 22/11/19 100% 100% 20
21 Tower Crane Install 13/12/19 13/12/19 100% 100% 21
22 P1 Level 00 slab 5w 09/12/19 24/01/20 100% 100% 22
23 P1 - Superstructure - 82Nr Apartments 23w 3d 06/01/20 22/06/20 95% 85% 23
24 Columns / walls level 00 to 01 3w 06/01/20 24/01/20 100% 100% 24
25 Level 01 floor slab 6w 15/01/20 25/02/20 100% 100% 25
26 Columns / walls level 01 to 02 3d 11/03/20 13/03/20 100% 100% 26
27 Level 02 floor slab 1w 16/03/20 20/03/20 100% 100% 27
28 Columns / walls level 02 to 03 1w 3d 17/03/20 26/03/20 100% 100% 28
29 Level 03 floor slab 2w 19/03/20 01/04/20 100% 100% 29
30 Columns / walls level 03 to 04 2w 26/03/20 08/04/20 100% 100% 30
31 Level 04 floor slab 2w 05/05/20 18/05/20 100% 100% 31
32 Columns / walls level 04 to 05 2w 08/05/20 21/05/20 100% 100% 32
33 Level 05 floor slab 2w 12/05/20 25/05/20 100% 100% 33
34 Columns / walls level 05 to 06 2w 15/05/20 28/05/20 100% 100% 34
35 Install stairs 3w 28/04/20 19/05/20 100% 100% 35
36 Level 06 core roof slab 2w 19/05/20 01/06/20 100% 70% 36
37 Upstands 2w 22/05/20 04/06/20 100% 50% 37
38 Strike clear & Clearout 2w 02/06/20 15/06/20 80% 40% 38
39 Podium Re-Visit works 3w 02/06/20 22/06/20 53% 39
40 P1 - Envelope 38w 3d 27/04/20 04/02/21 13% 5% 40
41 Seal Balconies 9w 1d 05/05/20 07/07/20 62% 32% 41
42 Ground Floor Water proofing 2w 05/05/20 18/05/20 100% 100% 42
43 L01 Seal Balconies 2w 19/05/20 01/06/20 100% 85% 43
44 L02 Seal Balconies 2w 22/05/20 04/06/20 100% 5% 44
45 L03 Seal Balconies 2w 03/06/20 16/06/20 70% 45

1 5
9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 2020
Revision No : C09
2021 Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
46 L04 Seal Balconies 2w 12/06/20 25/06/20 46
47 L05 Seal Balconies 2w 24/06/20 07/07/20 47
48 P1 - Metsec infill 12w 2d 11/05/20 04/08/20 40% 33% 48
49 Metsec infill level 00 to 01 3w 11/05/20 29/05/20 100% 100% 49
50 Metsec infill level 01 to 02 3w 22/05/20 11/06/20 100% 85% 50
51 Metsec infill level 02 to 03 3w 04/06/20 24/06/20 40% 13% 51
52 Metsec infill level 03 to 04 3w 17/06/20 07/07/20 52
53 Metsec infill level 04 to 05 3w 02/07/20 22/07/20 53
54 Metsec infill level 05 to 06 3w 15/07/20 04/08/20 54
55 P1 - Windows / External doors 15w 22/05/20 03/09/20 17% 11% 55
56 Level 00 windows / external doors 4w 22/05/20 18/06/20 75% 55% 56
57 Level 01 windows / external doors 4w 05/06/20 02/07/20 25% 10% 57
58 Level 02 windows / external doors 4w 19/06/20 16/07/20 58
59 Level 03 windows / external doors 4w 10/07/20 06/08/20 59
60 Level 04 windows / external doors 4w 22/07/20 18/08/20 60
61 Level 05 windows / external doors 4w 07/08/20 03/09/20 61
62 P1 - Masonry 22w 4d 27/04/20 02/10/20 19% 17% 62
63 Internal Block work level 00 to 01 3w 27/04/20 18/05/20 100% 95% 63
64 Ext.Masonry level 00 to 01 4w 29/05/20 25/06/20 50% 5% 64
65 Ext. Masonry level 01 to 02 5w 29/06/20 31/07/20 65
66 Ext. Masonry level 02 to 03 5w 20/07/20 21/08/20 66
67 Ext, Masonry level 03 to 04 5w 10/08/20 11/09/20 67
68 Ext. Masonry level 04 to 05 5w 31/08/20 02/10/20 68
69 P1 - Roof finishes 13w 22/06/20 18/09/20 69
70 Roof finishes 13w 22/06/20 18/09/20 70
71 Roof Substaintially watertight 27/07/20 27/07/20 71
72 PV Installation Roof 4w 3d 28/09/20 28/10/20 72
73 Installation of PV Panels 2w 28/09/20 09/10/20 73
74 Installation of PV DC Wiring Invertor 1w 12/10/20 16/10/20 74
75 Installation of AC supply to Invertor 1w 19/10/20 23/10/20 75
76 Commissioning of PV installation 3d 26/10/20 28/10/20 76
77 P1 - Metal balustrading 33w 4d 01/06/20 04/02/21 9% 77
78 Ground Level Metal Balustrading 1st Fix 2w 11/01/21 22/01/21 78
79 Ground Level Metal Balustrading 2nd Fix 2w 22/01/21 04/02/21 79
80 Level 01 Metal balustrading 1st fix 2w 01/06/20 12/06/20 90% 80
81 Level 01 Metal balustrading 2nd fix 2w 16/10/20 29/10/20 81
82 Level 02 Metal balustrading 1st Fix 2w 15/06/20 26/06/20 82
83 Level 02 Metal balustrading 2nd Fix 2w 05/10/20 16/10/20 83
84 Level 03 Metal balustrading 1st Fix 2w 29/06/20 10/07/20 84
85 Level 03 Metal balustrading 2nd Fix 2w 22/09/20 05/10/20 85
86 Level 04 Metal balustrading 1st Fix 2w 13/07/20 24/07/20 86
87 Level 04 Metal balustrading 2nd Fix 2w 09/09/20 22/09/20 87
88 P1 - Parapets / copings 7w 11/09/20 29/10/20 88
89 Parapets / copings 7w 11/09/20 29/10/20 89
90 Lighting Protection 17w 2d 08/06/20 06/10/20 14% 90
91 Connection to rebar in concrete Columns - CONTINUING 3w 2d 08/06/20 30/06/20 24% 91
92 Roof Net work 2w 21/09/20 02/10/20 92
93 Testing of Lightning Protection System 2d 05/10/20 06/10/20 93

94 P1 - Final flashings / seals 8w 21/09/20 13/11/20 94


95 Final flashings / seals 8w 21/09/20 13/11/20 95

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021 Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
96 Ground to Level 5 Composite Panels 16w 29/06/20 16/10/20 96
97 Ground Floor (All Elevations) 1w 3d 29/06/20 08/07/20 97
98 Galv, top Hats (128x50mm/128x100mm) & Fire Barriers 4d 29/06/20 02/07/20 98
99 Composite Panels (150mm) 4d 03/07/20 08/07/20 99
100 Level 1 (All Elevations) 2w 09/07/20 22/07/20 100
101 Galv, top Hats (128x50mm/128x100mm) & Fire Barriers 4d 09/07/20 14/07/20 101
102 Composite Panels (150mm) 1w 1d 15/07/20 22/07/20 102
103 Level 2 (All Elevations) 1w 3d 23/07/20 03/08/20 103
104 Galv, top Hats (128x50mm/128x100mm) & Fire Barriers 4d 23/07/20 28/07/20 104
105 Composite Panels (150mm) 4d 29/07/20 03/08/20 105
106 Level 3 (All Elevations) 1w 3d 04/08/20 13/08/20 106
107 Galv, top Hats (128x50mm/128x100mm) & Fire Barriers 4d 04/08/20 07/08/20 107
108 Composite Panels (150mm) 4d 10/08/20 13/08/20 108
109 Level 4 (All Elevations) 1w 3d 14/08/20 25/08/20 109
110 Galv, top Hats (128x50mm/128x100mm) & Fire Barriers 4d 14/08/20 19/08/20 110
111 Composite Panels (150mm) 4d 20/08/20 25/08/20 111
112 Level 5 Substarte 10w 10/08/20 16/10/20 112
113 South Elevation (Level 5) 1w 3d 10/08/20 19/08/20 113
114 Galvs, Top Hats (128x50mm) & Fire Barriers 3d 10/08/20 12/08/20 114
115 Composite Panel (150mm) 1w 11/08/20 17/08/20 115
116 Capping Bracket & Support 2d 18/08/20 19/08/20 116
117 East Elevation (Level 5) 2w 3d 20/08/20 07/09/20 117
118 Galvs, Top Hats (128x50mm) & Fire Barriers 4d 20/08/20 25/08/20 118
119 Composite Panel (150mm) 1w 4d 21/08/20 02/09/20 119
120 Capping Bracket & Support 3d 03/09/20 07/09/20 120
121 North Elevation (Level 5) 1w 3d 08/09/20 17/09/20 121
122 Galvs, Top Hats (128x50mm) & Fire Barriers 3d 08/09/20 10/09/20 122
123 Composite Panel (150mm) 1w 09/09/20 15/09/20 123
124 Capping Bracket & Support 2d 16/09/20 17/09/20 124
125 West Elevation (Level 5) 2w 3d 16/09/20 02/10/20 125
126 Galvs, Top Hats (128x50mm) & Fire Barriers 4d 16/09/20 21/09/20 126
127 Composite Panel (150mm) 1w 4d 17/09/20 29/09/20 127
128 Capping Bracket & Support 3d 30/09/20 02/10/20 128

129 North Podium (Level 5) 1w 05/10/20 09/10/20 129


130 Galvs, Top Hats (128x50mm) & Fire Barriers 2d 05/10/20 06/10/20 130
131 Composite Panel (150mm) 2d 07/10/20 08/10/20 131
132 Capping Bracket & Support 1d 09/10/20 09/10/20 132
133 South Podium (Level 5) 1w 12/10/20 16/10/20 133
134 Galvs, Top Hats (128x50mm) & Fire Barriers 2d 12/10/20 13/10/20 134
135 Composite Panel (150mm) 2d 14/10/20 15/10/20 135
136 Capping Bracket & Support 1d 16/10/20 16/10/20 136
Level 5 Terrace Aluminium Capping

137 Level 5 to Ground Zinc & Aluminium Soffits 17w 1d 09/07/20 05/11/20 137
138 Level 5 (All Elevations) 11w 3.5d 09/07/20 29/09/20 138
139 South Elevation (Level 5) 2w 4d 09/07/20 28/07/20 139
140 Tyvek Breather Memebrane 1d 09/07/20 09/07/20 140
141 Zinc standing Seam (430mm Centres) 2w 10/07/20 23/07/20 141
142 Zinc Capping Installtion 3d 24/07/20 28/07/20 142
143 East Elevation (Level 5) 3w 4d 29/07/20 24/08/20 143

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021
Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
144 Tyvek Breather Memebrane 2d 29/07/20 30/07/20 144
145 Zinc standing Seam (430mm Centres) 2w 4d 31/07/20 19/08/20 145
146 Zinc Capping Installtion 3d 20/08/20 24/08/20 146
147 North Elevation (Level 5) 2w 4d 25/08/20 11/09/20 147
148 Tyvek Breather Memebrane 1d 25/08/20 25/08/20 148
149 Zinc standing Seam (430mm Centres) 2w 26/08/20 08/09/20 149
150 Zinc Capping Installtion 3d 09/09/20 11/09/20 150
151 West Elevation (Level 5) 4w 1d 21/08/20 18/09/20 151
152 Tyvek Breather Memebrane 2d 21/08/20 24/08/20 152
153 Zinc standing Seam (430mm Centres) 3w 1d 25/08/20 15/09/20 153
154 Zinc Capping Installtion 3d 16/09/20 18/09/20 154

155 North Podium (Level 5) 2d 4h 21/09/20 23/09/20 155


156 Zinc standing Seam (430mm Centres) 2d 4h 21/09/20 23/09/20 156
157 Tyvek Breather Memebrane 4h 21/09/20 21/09/20 157
158 Zinc Capping Installtion 1d 21/09/20 21/09/20 158
159 South Podium (Level 5) 2d 4h 25/09/20 29/09/20 159
160 Zinc standing Seam (430mm Centres) 2d 4h 25/09/20 29/09/20 160
161 Tyvek Breather Memebrane 4h 25/09/20 25/09/20 161
162 Zinc Capping Installtion 1d 25/09/20 25/09/20 162
163 Level 4 (All Elevations) 7w 3d 29/07/20 18/09/20 163
164 Tyvek & Flashings 2d 31/08/20 01/09/20 164
165 Zinc standing Seam (430mm Centres) 1w 3d 02/09/20 11/09/20 165
166 Aluminium Soffits 1w 14/09/20 18/09/20 166
167 Level 3 Town house Parapet Capping 2w 29/07/20 11/08/20 167
168 Level 1 Houses Parapet Capping 1w 3d 12/08/20 21/08/20 168
169 Level 3 (All Elevations) 2w 19/08/20 01/09/20 169
170 Tyvek & Flashings 2d 19/08/20 20/08/20 170
171 Zinc standing Seam (430mm Centres) 2w 19/08/20 01/09/20 171
172 Level 2 (All Elevations) 3w 04/09/20 24/09/20 172
173 Tyvek & Flashings 2d 04/09/20 07/09/20 173
174 Zinc standing Seam (430mm Centres) 2w 08/09/20 21/09/20 174
175 Aluminium Soffits 1w 18/09/20 24/09/20 175
176 Level 1 (All Elevations) 3w 25/09/20 15/10/20 176
177 Tyvek & Flashings 2d 25/09/20 28/09/20 177
178 Zinc standing Seam (430mm Centres) 1w 3d 29/09/20 08/10/20 178
179 Aluminium Soffits 1w 09/10/20 15/10/20 179
180 Ground Floor (All Elevations) 3w 16/10/20 05/11/20 180
181 Tyvek & Flashings 2d 16/10/20 19/10/20 181
182 Zinc standing Seam (430mm Centres) 1w 3d 20/10/20 29/10/20 182
183 Aluminium Soffits 1w 30/10/20 05/11/20 183

184 P1 - Dismantle scaffold 6w 02/11/20 11/12/20 184


185 Dismantle scaffold 6w 02/11/20 11/12/20 185
186 P1 - Internal Fit-out (82 Apartments) 43w 3d 13/05/20 26/03/21 2% 3% 186
187 P1 - Fit-out - Level 00 - Plantrooms & BOH Areas 14w 2d 17/08/20 24/11/20 187
188 Plantroom 5w 2d 07/09/20 13/10/20 188
189 Delivery & Install of pre-fab skids 2d 07/09/20 08/09/20 189
190 Install of pipework from skid to car park 1w 09/09/20 15/09/20 190
191 Flue install 3d 16/09/20 18/09/20 191

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021
Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
192 Pressure testing 3d 21/09/20 23/09/20 192
193 Flushing & Water treatment of LTHW system 1w 24/09/20 30/09/20 193
194 Electrical 1st Fix Containment & wiring 1w 16/09/20 22/09/20 194
195 Electrical 2nd Fix 2d 23/09/20 24/09/20 195
196 Electrical Testing & Commissioning 2d 25/09/20 28/09/20 196
197 Commissioning of plant 1w 01/10/20 07/10/20 197
198 Pipework Insulation 4d 08/10/20 13/10/20 198
199 Tank Room 5w 3d 09/09/20 16/10/20 199
200 Delivery & Install of pre-fab skid 1d 09/09/20 09/09/20 200
201 Install of BCWS tank 1w 10/09/20 16/09/20 201
202 Install remaining pipework 1w 17/09/20 23/09/20 202
203 Pressure testing 3d 24/09/20 28/09/20 203
204 Filling tank & Water treatment 3d 29/09/20 01/10/20 204
205 Electrical 1st Fix Containment & wiring 1w 24/09/20 30/09/20 205
206 Electrical 2nd Fix 2d 01/10/20 02/10/20 206
207 Electrical Testing & Commissioning 2d 05/10/20 06/10/20 207
208 Commissioning of plant 1w 07/10/20 13/10/20 208
209 Pipework Insulation 3d 14/10/20 16/10/20 209
210 Electrical Switchroom 8w 4d 14/09/20 12/11/20 210
211 Installation of Main Switchboards 3d 14/09/20 16/09/20 211
212 Termination Submains Cabling 1w 17/09/20 23/09/20 212
213 Electrical 1st Fix - Containment & Wiring 1w 24/09/20 30/09/20 213
214 Electrical 2nd Fix 2d 01/10/20 02/10/20 214
215 Power On 2d 05/10/20 06/10/20 215
216 Electrical Testing & Commission Main Switchboard 2d 07/10/20 08/10/20 216
217 Electrical Testing & Commissioning 5w 09/10/20 12/11/20 217
Testing & commissioning L1 COMMENCE (from above
218
sequence)
11/11/20 11/11/20 218
219 OFFICE FITOUT 14w 2d 17/08/20 24/11/20 219
220 Fan inc associated ductwork 3d 17/08/20 19/08/20 220
221 AC cassette units inc associated pipework 4d 20/08/20 25/08/20 221
222 SVPs 2d 26/08/20 27/08/20 222
223 UFH Install 3d 28/08/20 01/09/20 223
224 Plumbing Copper first fix pipework inc HIU 3d 02/09/20 04/09/20 224
225 Electrical 1st Fix - Containment & wiring 2w 14/09/20 25/09/20 225
226 IT Cable Installation 2w 21/09/20 02/10/20 226
227 Mechanical 2nd fix 1w 26/10/20 30/10/20 227
228 Electrical 2nd Fix 1w 02/11/20 06/11/20 228
229 Test & Commission 2d 09/11/20 10/11/20 229
230 IT Comms Cabinets 1w 11/11/20 17/11/20 230
231 Commissioning of plant 1w 11/11/20 17/11/20 231
232 Testing of IT Systems 1w 18/11/20 24/11/20 232

233 P1 - Fit-out - Level 00 - 4Nr Apartments 32w 2d 13/05/20 07/01/21 20% 18% 233
234 Advanced works 3w 1d 13/05/20 03/06/20 100% 75% 234

235 Point survey to be carried out for setting out of all M&E services 3d 13/05/20 15/05/20 100% 100% 235

236 Duct work to be installed into UC and throughout apartment 2w 1d 14/05/20 28/05/20 100% 100% 236
Install soils & waste running from floor to floor & leave
237
connections where required
2w 1d 15/05/20 29/05/20 100% 100% 237
238 Insulate SVP's 3d 01/06/20 03/06/20 100% 238
239 1st fix corridor/Riser M&E 14w 2d 27/05/20 03/09/20 21% 15% 239
240 Install Electrical Riser Brackets & Containment 1w 29/05/20 04/06/20 100% 60% 240

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021
Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Install Submains cabling for IDNO boards in Risers ** SEE CAR
241
PARK SECTION
2w 14/08/20 27/08/20 241
242 Install electrical switchgear 1w 28/08/20 03/09/20 242
243 Install Electrical Corridor Containment 1w 05/06/20 11/06/20 100% 100% 243
244 Install Mechanical Brackets & Pipe work 1w 09/06/20 15/06/20 60% 80% 244
245 Testing and insualtion of corridor pipework 1w 18/06/20 24/06/20 245
246 Install Submains Cabling to Apartments 3d 18/06/20 22/06/20 246
247 Install Lighting & Power Cabling 2d 23/06/20 24/06/20 247
248 ELV & IT Cable installation 1w 25/06/20 01/07/20 248
249 Fire Alarm and smoke extract wiring 1w 25/06/20 01/07/20 249
250 Sprinkler 1st fix corridor pipework 3w 17/07/20 06/08/20 250
Install party walls for apartment & corridor including utility
251
cupboard
3w 27/05/20 16/06/20 80% 70% 251
252 Tape & joint utility cupboard and paint to allow fixing to wall 2w 03/06/20 16/06/20 70% 252
253 Install sole plate for stud wall & board both sides to 150mm high 2w 08/06/20 19/06/20 40% 253
Delivery, load out and install HIU POD inc. low level waste
254
pipework to POD & LTHW riser
1w 1d 12/06/20 19/06/20 254
255 Install UFH insulation 2w 3d 17/06/20 03/07/20 255
256 UFH installation throughout apartment & test 3w 1d 18/06/20 09/07/20 256
257 Screed floor throughout apartment 1w 01/07/20 07/07/20 257
258 Install wireway for Screed Temperature sensor 1w 08/07/20 14/07/20 258
259 Installation of internal stud walls & board 1 side 3w 01/07/20 21/07/20 259
260 Installation of bathroom boxings 2w 2d 15/07/20 30/07/20 260
261 Corridor Second Fix M&E 2w 1d 23/10/20 06/11/20 261
262 Install Lighting & Power 1w 23/10/20 29/10/20 262
263 CCTV, Access Control 1w 27/10/20 02/11/20 263
264 Fire Alarm 1w 29/10/20 04/11/20 264
265 Smoke Extract System 1w 02/11/20 06/11/20 265
266 Commissioning Landlords Systems 8w 30/10/20 07/01/21 266
267 Testing & Commission Lighting & Power 5w 30/10/20 03/12/20 267
268 Testing & Commission CCTV & Access Control 5w 06/11/20 10/12/20 268
269 Testing & Commission Fire Alarm 5w 13/11/20 17/12/20 269
270 Testing & Commission Smoke Extract System 5w 20/11/20 07/01/21 270
271 Remaining 1st fix M&E in ceiling & all drops in walls 18w 2d 22/07/20 26/11/20 271
272 Install domestic copper pipework, pressure test and insulate 3w 22/07/20 11/08/20 272
273 Sprinkler 1st fix pipework 3w 24/07/20 13/08/20 273
274 Electrical first fix (Cabling) 3w 28/07/20 17/08/20 274
Issue sign off & test certs to allow WIR to be issued for WALL
275
CLOSURES
2w 4d 31/07/20 19/08/20 275
276 Inspection of baffle boxes 2w 4d 31/07/20 19/08/20 276
277 Close walls / Install ceiling metal / Install ceiling pattresses 1w 4d 06/08/20 18/08/20 277
278 Firestopping 1w 2d 10/08/20 18/08/20 278
279 Sprinkler head install & pressure test 1w 13/08/20 19/08/20 279
Pull cables through wooden pattresses (smoke detectors / lighting
280
pendants)
1w 13/08/20 19/08/20 280
Issue sign off & test certs to allow WIR to be issued for CEILING
281
CLOSURES
4d 17/08/20 20/08/20 281
282 Finishes 14w 2d 19/08/20 26/11/20 282
283 1st fix Joinery 3w 19/08/20 08/09/20 283
284 Plasterboard ceilings 2w 19/08/20 01/09/20 284
285 Plastering 3w 21/08/20 10/09/20 285
286 Drying 3w 28/08/20 17/09/20 286
287 Mist coat decoration 2w 11/09/20 24/09/20 287
288 2nd Fix Mechanical (bath, shower trays, kitchen) 3w 18/09/20 08/10/20 288
Drill holes for light fittings and pull cables through ceiling, install
289 blue plugs, fit sockets and lights, Install and terminate consumer 3w 18/09/20 08/10/20 289
unit)

290 2nd fix Joinery 3w 18/09/20 08/10/20 290


291 Floor tiling 2w 18/09/20 01/10/20 291

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021 Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
292 Install Kitchen 2w 25/09/20 08/10/20 292
293 Wall tiling 2w 25/09/20 08/10/20 293
294 Final fix Mechanical (sanitaryware / kitchen sink taps) 3w 4d 02/10/20 28/10/20 294
Final fix Electrical (IT, IRS, Door Entry, wiring kitchen
295
accessories)
2w 09/10/20 22/10/20 295
296 Floor finishes 3w 09/10/20 29/10/20 296
297 Final Decoration 3w 05/10/20 23/10/20 297
298 Final snagging 3w 23/10/20 12/11/20 298
299 M&E Accessories (toilet seat, Shower hoses, head etc) 3w 23/10/20 12/11/20 299
300 Testing & commissioning 4w 30/10/20 26/11/20 300
301 Electrical Testing & Certification 2w 30/10/20 12/11/20 301

302 P1 - Fit-Out - Level 01 -16 Apartments 34w 25/05/20 29/01/21 8% 12% 302
303 Advanced works 3w 1d 25/05/20 15/06/20 93% 70% 303

304 Point survey to be carried out for setting out of all M&E services 3d 25/05/20 27/05/20 100% 100% 304

305 Duct work to be installed into UC and throughout apartment 2w 1d 26/05/20 09/06/20 100% 100% 305
Install soils & waste running from floor to floor & leave
306
connections where required
2w 1d 27/05/20 10/06/20 100% 80% 306
307 Insulate SVP's 3d 11/06/20 15/06/20 33% 307
308 1st fix corridor/Riser M&E 14w 2d 15/06/20 22/09/20 7% 308
309 Install Electrical Riser Brackets & Containment 1w 17/06/20 23/06/20 309
310 Install electrical switchgear 1w 16/09/20 22/09/20 310
311 Install Electrical Corridor Containment 1w 24/06/20 30/06/20 100% 311
312 Install Mechanical Brackets & Pipe work 1w 26/06/20 02/07/20 30% 312
313 Testing and insualtion of corridor pipework 1w 07/07/20 13/07/20 313
314 Install Submains Cabling to Apartments 3d 07/07/20 09/07/20 314
315 Install Lighting & Power Cabling 2d 10/07/20 13/07/20 315
316 ELV & IT Cable installation 1w 14/07/20 20/07/20 316
317 Fire Alarm and smoke extract wiring 1w 14/07/20 20/07/20 317
318 Sprinkler 1st fix corridor pipework 3w 05/08/20 25/08/20 318
Install party walls for apartment & corridor including utility
319
cupboard
3w 15/06/20 03/07/20 319
320 Tape & joint utility cupboard and paint to allow fixing to wall 2w 22/06/20 03/07/20 320
321 Install sole plate for stud wall & board both sides to 150mm high 2w 25/06/20 08/07/20 321
Delivery, load out and install HIU POD inc. low level waste
322
pipework to POD & LTHW riser
1w 1d 01/07/20 08/07/20 322
323 Install UFH insulation 2w 3d 06/07/20 22/07/20 323
324 UFH installation throughout apartment & test 3w 1d 07/07/20 28/07/20 324
325 Screed floor throughout apartment 2w 20/07/20 31/07/20 325
326 Install wireway for Screed Temperature sensor 1w 03/08/20 07/08/20 326
327 Installation of internal stud walls & board 1 side 3w 27/07/20 14/08/20 327
328 Installation of bathroom boxings 2w 2d 03/08/20 18/08/20 328
329 Corridor Second Fix M&E 2w 1d 04/11/20 18/11/20 329
330 Install Lighting & Power 1w 04/11/20 10/11/20 330
331 CCTV, Access Control 1w 06/11/20 12/11/20 331
332 Fire Alarm 1w 10/11/20 16/11/20 332
333 Smoke Extract System 1w 12/11/20 18/11/20 333
334 Commissioning Landlords Systems 9w 3d 11/11/20 29/01/21 334
335 Testing & Commission Lighting & Power 5w 11/11/20 15/12/20 335
336 Testing & Commission CCTV & Access Control 5w 18/11/20 05/01/21 336
337 Testing & Commission Fire Alarm 5w 25/11/20 12/01/21 337
338 Testing & Commission Smoke Extract System 5w 02/12/20 19/01/21 338
339 Final clean 4w 04/01/21 29/01/21 339
340 Remaining 1st fix M&E in ceiling & all drops in walls 18w 2d 03/08/20 08/12/20 340
341 Install domestic copper pipework, pressure test and insulate 3w 03/08/20 21/08/20 341

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021
Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
342 Sprinkler 1st fix pipework 3w 05/08/20 25/08/20 342
343 Electrical first fix (Cabling) 3w 07/08/20 27/08/20 343
Issue sign off & test certs to allow WIR to be issued for WALL
344
CLOSURES
2w 4d 12/08/20 31/08/20 344
345 Inspection of baffle boxes 2w 4d 12/08/20 31/08/20 345
346 Close walls / Install ceiling metal / Install ceiling pattresses 1w 4d 18/08/20 28/08/20 346
347 Firestopping 1w 2d 20/08/20 28/08/20 347
348 Sprinkler head install & pressure test 1w 25/08/20 31/08/20 348
Pull cables through wooden pattresses (smoke detectors / lighting
349
pendants)
1w 25/08/20 31/08/20 349
Issue sign off & test certs to allow WIR to be issued for CEILING
350
CLOSURES
4d 27/08/20 01/09/20 350
351 Finishes 14w 2d 31/08/20 08/12/20 351
352 1st fix Joinery 3w 31/08/20 18/09/20 352
353 Plasterboard ceilings 2w 31/08/20 11/09/20 353
354 Plastering 3w 02/09/20 22/09/20 354
355 Drying 3w 09/09/20 29/09/20 355
356 Mist coat decoration 2w 23/09/20 06/10/20 356
357 2nd Fix Mechanical (bath, shower trays, kitchen) 3w 30/09/20 20/10/20 357
Drill holes for light fittings and pull cables through ceiling, install
358 blue plugs, fit sockets and lights, Install and terminate consumer 3w 30/09/20 20/10/20 358
unit)

359 2nd fix Joinery 3w 30/09/20 20/10/20 359


360 Floor tiling 2w 30/09/20 13/10/20 360
361 Install Kitchen 2w 07/10/20 20/10/20 361
362 Wall tiling 2w 07/10/20 20/10/20 362
363 Final fix Mechanical (sanitaryware / kitchen sink taps) 3w 4d 14/10/20 09/11/20 363
Final fix Electrical (IT, IRS, Door Entry, wiring kitchen
364
accessories)
2w 21/10/20 03/11/20 364
365 Floor finishes 3w 21/10/20 10/11/20 365
366 Final Decoration 3w 15/10/20 04/11/20 366
367 Final snagging 3w 04/11/20 24/11/20 367
368 M&E Accessories (toilet seat, Shower hoses, head etc) 3w 04/11/20 24/11/20 368
369 Testing & commissioning 4w 11/11/20 08/12/20 369
370 Electrical Testing & Certification 2w 11/11/20 24/11/20 370
371 Podium Garden Area 5w 25/01/21 26/02/21 371
372 Electrical 1st Fix 1w 25/01/21 29/01/21 372
373 Electrical 2nd Fix 1w 01/02/21 05/02/21 373
374 Irrigation System 2w 08/02/21 19/02/21 374
375 Commission Irriagation System 1w 22/02/21 26/02/21 375

376 P1 - Fit-Out - Level 02 -16 Apartments 34w 08/06/20 12/02/21 2% 8% 376


377 Advanced works 3w 1d 08/06/20 29/06/20 29% 40% 377

378 Point survey to be carried out for setting out of all M&E services 3d 08/06/20 10/06/20 100% 100% 378

379 Duct work to be installed into UC and throughout apartment 2w 1d 09/06/20 23/06/20 27% 20% 379
Install soils & waste running from floor to floor & leave
380
connections where required
2w 1d 10/06/20 24/06/20 18% 40% 380
381 Insulate SVP's 3d 25/06/20 29/06/20 381
382 1st fix corridor/Riser M&E 14w 2d 22/06/20 29/09/20 6% 382
383 Install Electrical Riser Brackets & Containment 1w 24/06/20 30/06/20 383
384 Install electrical switchgear 1w 23/09/20 29/09/20 384
385 Install Electrical Corridor Containment 1w 01/07/20 07/07/20 95% 385
386 Install Mechanical Brackets & Pipe work 1w 03/07/20 09/07/20 20% 386
387 Testing and insualtion of corridor pipework 1w 14/07/20 20/07/20 387
388 Install Submains Cabling to Apartments 3d 14/07/20 16/07/20 388
389 Install Lighting & Power Cabling 2d 17/07/20 20/07/20 389
390 ELV & IT Cable installation 1w 21/07/20 27/07/20 390

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021 Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
391 Fire Alarm and smoke extract wiring 1w 21/07/20 27/07/20 391
392 Sprinkler 1st fix corridor pipework 3w 12/08/20 01/09/20 392
Install party walls for apartment & corridor including utility
393
cupboard
3w 22/06/20 10/07/20 393
394 Tape & joint utility cupboard and paint to allow fixing to wall 2w 29/06/20 10/07/20 394
395 Install sole plate for stud wall & board both sides to 150mm high 2w 02/07/20 15/07/20 395
Delivery, load out and install HIU POD inc. low level waste
396
pipework to POD & LTHW riser
1w 1d 08/07/20 15/07/20 396
397 Install UFH insulation 2w 3d 13/07/20 29/07/20 397
398 UFH installation throughout apartment & test 3w 1d 14/07/20 04/08/20 398
399 Screed floor throughout apartment 2w 27/07/20 07/08/20 399
400 Install wireway for Screed Temperature sensor 1w 10/08/20 14/08/20 400
401 Installation of internal stud walls & board 1 side 3w 03/08/20 21/08/20 401
402 Installation of bathroom boxings 2w 2d 10/08/20 25/08/20 402
403 Corridor Second Fix M&E 2w 1d 18/11/20 02/12/20 403
404 Install Lighting & Power 1w 18/11/20 24/11/20 404
405 CCTV, Access Control 1w 20/11/20 26/11/20 405
406 Fire Alarm 1w 24/11/20 30/11/20 406
407 Smoke Extract System 1w 26/11/20 02/12/20 407
408 Commissioning Landlords Systems 9w 3d 25/11/20 12/02/21 408
409 Testing & Commission Lighting & Power 5w 25/11/20 12/01/21 409
410 Testing & Commission CCTV & Access Control 5w 02/12/20 19/01/21 410
411 Testing & Commission Fire Alarm 5w 09/12/20 26/01/21 411
412 Testing & Commission Smoke Extract System 5w 16/12/20 02/02/21 412
413 Final clean 4w 18/01/21 12/02/21 413
414 Remaining 1st fix M&E in ceiling & all drops in walls 18w 2d 17/08/20 05/01/21 414
415 Install domestic copper pipework, pressure test and insulate 3w 17/08/20 04/09/20 415
416 Sprinkler 1st fix pipework 3w 19/08/20 08/09/20 416
417 Electrical first fix (Cabling) 3w 21/08/20 10/09/20 417
Issue sign off & test certs to allow WIR to be issued for WALL
418
CLOSURES
2w 4d 26/08/20 14/09/20 418
419 Inspection of baffle boxes 2w 4d 26/08/20 14/09/20 419
420 Close walls / Install ceiling metal / Install ceiling pattresses 1w 4d 01/09/20 11/09/20 420
421 Firestopping 1w 2d 03/09/20 11/09/20 421
422 Sprinkler head install & pressure test 1w 08/09/20 14/09/20 422
Pull cables through wooden pattresses (smoke detectors / lighting
423
pendants)
1w 08/09/20 14/09/20 423
Issue sign off & test certs to allow WIR to be issued for CEILING
424
CLOSURES
4d 10/09/20 15/09/20 424
425 Finishes 14w 2d 14/09/20 05/01/21 425
426 1st fix Joinery 3w 14/09/20 02/10/20 426
427 Plasterboard ceilings 2w 14/09/20 25/09/20 427
428 Plastering 3w 16/09/20 06/10/20 428
429 Drying 3w 23/09/20 13/10/20 429
430 Mist coat decoration 2w 07/10/20 20/10/20 430
431 2nd Fix Mechanical (bath, shower trays, kitchen) 3w 14/10/20 03/11/20 431
Drill holes for light fittings and pull cables through ceiling, install
432 blue plugs, fit sockets and lights, Install and terminate consumer 3w 14/10/20 03/11/20 432
unit)

433 2nd fix Joinery 3w 14/10/20 03/11/20 433


434 Floor tiling 2w 14/10/20 27/10/20 434
435 Install Kitchen 2w 21/10/20 03/11/20 435
436 Wall tiling 2w 21/10/20 03/11/20 436
437 Final fix Mechanical (sanitaryware / kitchen sink taps) 3w 4d 28/10/20 23/11/20 437
Final fix Electrical (IT, IRS, Door Entry, wiring kitchen
438
accessories)
2w 04/11/20 17/11/20 438
439 Floor finishes 3w 04/11/20 24/11/20 439
440 Final Decoration 3w 29/10/20 18/11/20 440
441 Final snagging 3w 18/11/20 08/12/20 441

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
442 M&E Accessories (toilet seat, Shower hoses, head etc) 3w 18/11/20 08/12/20 442
443 Testing & commissioning 4w 25/11/20 05/01/21 443
444 Electrical Testing & Certification 2w 25/11/20 08/12/20 444

445 P1 - Fit-Out - Level 03 -16 Apartments 32w 2d 22/06/20 16/02/21 445


446 Advanced works 3w 1d 22/06/20 13/07/20 446

447 Point survey to be carried out for setting out of all M&E services 3d 22/06/20 24/06/20 447

448 Duct work to be installed into UC and throughout apartment 2w 1d 23/06/20 07/07/20 448
Install soils & waste running from floor to floor & leave
449
connections where required
2w 1d 24/06/20 08/07/20 449
450 Insulate SVP's 3d 09/07/20 13/07/20 450
451 1st fix corridor/Riser M&E 14w 2d 06/07/20 13/10/20 451
452 Install Electrical Riser Brackets & Containment 1w 08/07/20 14/07/20 452
Install Submains cabling for IDNO boards in Risers ** SEE CAR
453
PARK SECTION
2w 23/09/20 06/10/20 453
454 Install electrical switchgear 1w 07/10/20 13/10/20 454
455 Install Electrical Corridor Containment 1w 15/07/20 21/07/20 455
456 Install Mechanical Brackets & Pipe work 1w 17/07/20 23/07/20 456
457 Testing and insualtion of corridor pipework 1w 28/07/20 03/08/20 457
458 Install Submains Cabling to Apartments 3d 28/07/20 30/07/20 458
459 Install Lighting & Power Cabling 2d 31/07/20 03/08/20 459
460 ELV & IT Cable installation 1w 04/08/20 10/08/20 460
461 Fire Alarm and smoke extract wiring 1w 04/08/20 10/08/20 461
462 Sprinkler 1st fix corridor pipework 3w 26/08/20 15/09/20 462
Install party walls for apartment & corridor including utility
463
cupboard
3w 06/07/20 24/07/20 463
464 Tape & joint utility cupboard and paint to allow fixing to wall 2w 13/07/20 24/07/20 464
465 Install sole plate for stud wall & board both sides to 150mm high 2w 16/07/20 29/07/20 465
Delivery, load out and install HIU POD inc. low level waste
466
pipework to POD & LTHW riser
1w 1d 22/07/20 29/07/20 466
467 Install UFH insulation 2w 3d 27/07/20 12/08/20 467
468 UFH installation throughout apartment & test 3w 1d 28/07/20 18/08/20 468
469 Screed floor throughout apartment 2w 10/08/20 21/08/20 469
470 Install wireway for Screed Temperature sensor 1w 24/08/20 28/08/20 470
471 Installation of internal stud walls & board 1 side 3w 17/08/20 04/09/20 471
472 Installation of bathroom boxings 2w 2d 24/08/20 08/09/20 472
473 Corridor Second Fix M&E 2w 1d 02/12/20 16/12/20 473
474 Install Lighting & Power 1w 02/12/20 08/12/20 474
475 CCTV, Access Control 1w 04/12/20 10/12/20 475
476 Fire Alarm 1w 08/12/20 14/12/20 476
477 Smoke Extract System 1w 10/12/20 16/12/20 477
478 Commissioning Landlords Systems 8w 09/12/20 16/02/21 478
479 Testing & Commission Lighting & Power 5w 09/12/20 26/01/21 479
480 Testing & Commission CCTV & Access Control 5w 16/12/20 02/02/21 480
481 Testing & Commission Fire Alarm 5w 06/01/21 09/02/21 481
482 Testing & Commission Smoke Extract System 5w 13/01/21 16/02/21 482
483 Remaining 1st fix M&E in ceiling & all drops in walls 18w 2d 31/08/20 19/01/21 483
484 Install domestic copper pipework, pressure test and insulate 3w 31/08/20 18/09/20 484
485 Sprinkler 1st fix pipework 3w 02/09/20 22/09/20 485
486 Electrical first fix (Cabling) 3w 04/09/20 24/09/20 486
Issue sign off & test certs to allow WIR to be issued for WALL
487
CLOSURES
2w 4d 09/09/20 28/09/20 487
488 Inspection of baffle boxes 2w 4d 09/09/20 28/09/20 488
489 Close walls / Install ceiling metal / Install ceiling pattresses 1w 4d 15/09/20 25/09/20 489
490 Firestopping 1w 2d 17/09/20 25/09/20 490
491 Sprinkler head install & pressure test 1w 22/09/20 28/09/20 491

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Pull cables through wooden pattresses (smoke detectors / lighting
492
pendants)
1w 22/09/20 28/09/20 492
Issue sign off & test certs to allow WIR to be issued for CEILING
493
CLOSURES
4d 24/09/20 29/09/20 493
494 Finishes 14w 2d 28/09/20 19/01/21 494
495 1st fix Joinery 3w 28/09/20 16/10/20 495
496 Plasterboard ceilings 2w 28/09/20 09/10/20 496
497 Plastering 3w 30/09/20 20/10/20 497
498 Drying 3w 07/10/20 27/10/20 498
499 Mist coat decoration 2w 21/10/20 03/11/20 499
500 2nd Fix Mechanical (bath, shower trays, kitchen) 3w 28/10/20 17/11/20 500
Drill holes for light fittings and pull cables through ceiling, install
501 blue plugs, fit sockets and lights, Install and terminate consumer 3w 28/10/20 17/11/20 501
unit)

502 2nd fix Joinery 3w 28/10/20 17/11/20 502


503 Floor tiling 2w 28/10/20 10/11/20 503
504 Install Kitchen 2w 04/11/20 17/11/20 504
505 Wall tiling 2w 04/11/20 17/11/20 505
506 Final fix Mechanical (sanitaryware / kitchen sink taps) 3w 4d 11/11/20 07/12/20 506
Final fix Electrical (IT, IRS, Door Entry, wiring kitchen
507
accessories)
2w 18/11/20 01/12/20 507
508 Floor finishes 3w 18/11/20 08/12/20 508
509 Final Decoration 3w 12/11/20 02/12/20 509
510 Final snagging 3w 02/12/20 05/01/21 510
511 M&E Accessories (toilet seat, Shower hoses, head etc) 3w 02/12/20 05/01/21 511
512 Testing & commissioning 4w 09/12/20 19/01/21 512
513 Electrical Testing & Certification 2w 09/12/20 05/01/21 513

514 P1 - Fit-Out - Level 04 -16 Apartments 34w 06/07/20 12/03/21 514


515 Advanced works 3w 1d 06/07/20 27/07/20 515

516 Point survey to be carried out for setting out of all M&E services 3d 06/07/20 08/07/20 516

517 Duct work to be installed into UC and throughout apartment 2w 1d 07/07/20 21/07/20 517
Install soils & waste running from floor to floor & leave
518
connections where required
2w 1d 08/07/20 22/07/20 518
519 Insulate SVP's 3d 23/07/20 27/07/20 519
520 1st fix corridor/Riser M&E 14w 2d 20/07/20 27/10/20 520
521 Install Electrical Riser Brackets & Containment 1w 22/07/20 28/07/20 521
522 Install electrical switchgear 1w 21/10/20 27/10/20 522
523 Install Electrical Corridor Containment 1w 29/07/20 04/08/20 523
524 Install Mechanical Brackets & Pipe work 1w 31/07/20 06/08/20 524
525 Testing and insualtion of corridor pipework 1w 11/08/20 17/08/20 525
526 Install Submains Cabling to Apartments 3d 11/08/20 13/08/20 526
527 Install Lighting & Power Cabling 2d 14/08/20 17/08/20 527
528 ELV & IT Cable installation 1w 18/08/20 24/08/20 528
529 Fire Alarm and smoke extract wiring 1w 18/08/20 24/08/20 529
530 Sprinkler 1st fix corridor pipework 3w 09/09/20 29/09/20 530
Install party walls for apartment & corridor including utility
531
cupboard
3w 20/07/20 07/08/20 531
532 Tape & joint utility cupboard and paint to allow fixing to wall 2w 27/07/20 07/08/20 532
533 Install sole plate for stud wall & board both sides to 150mm high 2w 30/07/20 12/08/20 533
Delivery, load out and install HIU POD inc. low level waste
534
pipework to POD & LTHW riser
1w 1d 05/08/20 12/08/20 534
535 Install UFH insulation 2w 3d 10/08/20 26/08/20 535
536 UFH installation throughout apartment & test 3w 1d 11/08/20 01/09/20 536
537 Screed floor throughout apartment 2w 24/08/20 04/09/20 537
538 Install wireway for Screed Temperature sensor 1w 07/09/20 11/09/20 538
539 Installation of internal stud walls & board 1 side 3w 31/08/20 18/09/20 539
540 Installation of bathroom boxings 2w 2d 07/09/20 22/09/20 540

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021
Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
541 Corridor Second Fix M&E 2w 1d 16/12/20 13/01/21 541
542 Install Lighting & Power 1w 16/12/20 05/01/21 542
543 CCTV, Access Control 1w 18/12/20 07/01/21 543
544 Fire Alarm 1w 05/01/21 11/01/21 544
545 Smoke Extract System 1w 07/01/21 13/01/21 545
546 Commissioning Landlords Systems 9w 3d 06/01/21 12/03/21 546
547 Testing & Commission Lighting & Power 5w 06/01/21 09/02/21 547
548 Testing & Commission CCTV & Access Control 5w 13/01/21 16/02/21 548
549 Testing & Commission Fire Alarm 5w 20/01/21 23/02/21 549
550 Testing & Commission Smoke Extract System 5w 27/01/21 02/03/21 550
551 Final clean 4w 15/02/21 12/03/21 551
552 Remaining 1st fix M&E in ceiling & all drops in walls 4w 2d 14/09/20 13/10/20 552
553 Install domestic copper pipework, pressure test and insulate 3w 14/09/20 02/10/20 553
554 Sprinkler 1st fix pipework 3w 16/09/20 06/10/20 554
555 Electrical first fix (Cabling) 3w 18/09/20 08/10/20 555
Issue sign off & test certs to allow WIR to be issued for WALL
556
CLOSURES
2w 4d 23/09/20 12/10/20 556
557 Inspection of baffle boxes 2w 4d 23/09/20 12/10/20 557
558 Close walls / Install ceiling metal / Install ceiling pattresses 1w 4d 29/09/20 09/10/20 558
559 Firestopping 1w 2d 01/10/20 09/10/20 559
560 Sprinkler head install & pressure test 1w 06/10/20 12/10/20 560
Pull cables through wooden pattresses (smoke detectors / lighting
561
pendants)
1w 06/10/20 12/10/20 561
Issue sign off & test certs to allow WIR to be issued for CEILING
562
CLOSURES
4d 08/10/20 13/10/20 562
563 Finishes 14w 2d 12/10/20 02/02/21 563
564 1st fix Joinery 3w 12/10/20 30/10/20 564
565 Plasterboard ceilings 2w 12/10/20 23/10/20 565
566 Plastering 3w 14/10/20 03/11/20 566
567 Drying 3w 21/10/20 10/11/20 567
568 Mist coat decoration 2w 04/11/20 17/11/20 568
569 2nd Fix Mechanical (bath, shower trays, kitchen) 3w 11/11/20 01/12/20 569
Drill holes for light fittings and pull cables through ceiling, install
570 blue plugs, fit sockets and lights, Install and terminate consumer 3w 11/11/20 01/12/20 570
unit)

571 2nd fix Joinery 3w 11/11/20 01/12/20 571


572 Floor tiling 2w 11/11/20 24/11/20 572
573 Install Kitchen 2w 18/11/20 01/12/20 573
574 Wall tiling 2w 18/11/20 01/12/20 574
575 Final fix Mechanical (sanitaryware / kitchen sink taps) 3w 4d 25/11/20 04/01/21 575
Final fix Electrical (IT, IRS, Door Entry, wiring kitchen
576
accessories)
2w 02/12/20 15/12/20 576
577 Floor finishes 3w 02/12/20 05/01/21 577
578 Final Decoration 3w 26/11/20 16/12/20 578
579 Final snagging 3w 16/12/20 19/01/21 579
580 M&E Accessories (toilet seat, Shower hoses, head etc) 3w 16/12/20 19/01/21 580
581 Testing & commissioning 4w 06/01/21 02/02/21 581
582 Electrical Testing & Certification 2w 06/01/21 19/01/21 582

583 P1 - Fit-Out - Level 05 -16 Apartments 34w 20/07/20 26/03/21 583


584 Advanced works 3w 1d 20/07/20 10/08/20 584

585 Point survey to be carried out for setting out of all M&E services 3d 20/07/20 22/07/20 585

586 Duct work to be installed into UC and throughout apartment 2w 1d 21/07/20 04/08/20 586
Install soils & waste running from floor to floor & leave
587
connections where required
2w 1d 22/07/20 05/08/20 587
588 Insulate SVP's 3d 06/08/20 10/08/20 588
589 1st fix corridor/Riser M&E 14w 2d 03/08/20 10/11/20 589

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021
Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
590 Install Electrical Riser Brackets & Containment 1w 05/08/20 11/08/20 590
591 Install electrical switchgear 1w 04/11/20 10/11/20 591
592 Install Electrical Corridor Containment 1w 12/08/20 18/08/20 592
593 Install Mechanical Brackets & Pipe work 1w 14/08/20 20/08/20 593
594 Testing and insualtion of corridor pipework 1w 25/08/20 31/08/20 594
595 Install Submains Cabling to Apartments 3d 25/08/20 27/08/20 595
596 Install Lighting & Power Cabling 2d 28/08/20 31/08/20 596
597 ELV & IT Cable installation 1w 01/09/20 07/09/20 597
598 Fire Alarm and smoke extract wiring 1w 01/09/20 07/09/20 598
599 Sprinkler 1st fix corridor pipework 3w 23/09/20 13/10/20 599
Install party walls for apartment & corridor including utility
600
cupboard
3w 03/08/20 21/08/20 600
601 Tape & joint utility cupboard and paint to allow fixing to wall 2w 10/08/20 21/08/20 601
602 Install sole plate for stud wall & board both sides to 150mm high 2w 13/08/20 26/08/20 602
Delivery, load out and install HIU POD inc. low level waste
603
pipework to POD & LTHW riser
1w 1d 19/08/20 26/08/20 603
604 Install UFH insulation 2w 3d 24/08/20 09/09/20 604
605 UFH installation throughout apartment & test 3w 1d 25/08/20 15/09/20 605
606 Screed floor throughout apartment 2w 07/09/20 18/09/20 606
607 Install wireway for Screed Temperature sensor 1w 21/09/20 25/09/20 607
608 Installation of internal stud walls & board 1 side 3w 14/09/20 02/10/20 608
609 Installation of bathroom boxings 2w 2d 21/09/20 06/10/20 609
610 Corridor Second Fix M&E 2w 1d 13/01/21 27/01/21 610
611 Install Lighting & Power 1w 13/01/21 19/01/21 611
612 CCTV, Access Control 1w 15/01/21 21/01/21 612
613 Fire Alarm 1w 19/01/21 25/01/21 613
614 Smoke Extract System 1w 21/01/21 27/01/21 614
615 Commissioning Landlords Systems 9w 3d 20/01/21 26/03/21 615
616 Testing & Commission Lighting & Power 5w 20/01/21 23/02/21 616
617 Testing & Commission CCTV & Access Control 5w 27/01/21 02/03/21 617
618 Testing & Commission Fire Alarm 5w 03/02/21 09/03/21 618
619 Testing & Commission Smoke Extract System 5w 10/02/21 16/03/21 619
620 Final clean 4w 01/03/21 26/03/21 620
621 Remaining 1st fix M&E in ceiling & all drops in walls 4w 2d 28/09/20 27/10/20 621
622 Install domestic copper pipework, pressure test and insulate 3w 28/09/20 16/10/20 622
623 Sprinkler 1st fix pipework 3w 30/09/20 20/10/20 623
624 Electrical first fix (Cabling) 3w 02/10/20 22/10/20 624
Issue sign off & test certs to allow WIR to be issued for WALL
625
CLOSURES
2w 4d 07/10/20 26/10/20 625
626 Inspection of baffle boxes 2w 4d 07/10/20 26/10/20 626
627 Close walls / Install ceiling metal / Install ceiling pattresses 1w 4d 13/10/20 23/10/20 627
628 Firestopping 1w 2d 15/10/20 23/10/20 628
629 Sprinkler head install & pressure test 1w 20/10/20 26/10/20 629
Pull cables through wooden pattresses (smoke detectors / lighting
630
pendants)
1w 20/10/20 26/10/20 630
Issue sign off & test certs to allow WIR to be issued for CEILING
631
CLOSURES
4d 22/10/20 27/10/20 631
632 Finishes 14w 2d 26/10/20 16/02/21 632
633 1st fix Joinery 3w 26/10/20 13/11/20 633
634 Plasterboard ceilings 2w 26/10/20 06/11/20 634
635 Plastering 3w 28/10/20 17/11/20 635
636 Drying 3w 04/11/20 24/11/20 636
637 Mist coat decoration 2w 18/11/20 01/12/20 637
638 2nd Fix Mechanical (bath, shower trays, kitchen) 3w 25/11/20 15/12/20 638
Drill holes for light fittings and pull cables through ceiling, install
639 blue plugs, fit sockets and lights, Install and terminate consumer 3w 25/11/20 15/12/20 639
unit)

640 2nd fix Joinery 3w 25/11/20 15/12/20 640

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021
Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
641 Floor tiling 2w 25/11/20 08/12/20 641
642 Install Kitchen 2w 02/12/20 15/12/20 642
643 Wall tiling 2w 02/12/20 15/12/20 643
644 Final fix Mechanical (sanitaryware / kitchen sink taps) 3w 4d 09/12/20 18/01/21 644
Final fix Electrical (IT, IRS, Door Entry, wiring kitchen
645
accessories)
2w 16/12/20 12/01/21 645
646 Floor finishes 3w 16/12/20 19/01/21 646
647 Final Decoration 3w 10/12/20 13/01/21 647
648 Final snagging 3w 13/01/21 02/02/21 648
649 M&E Accessories (toilet seat, Shower hoses, head etc) 3w 13/01/21 02/02/21 649
650 Testing & commissioning 4w 20/01/21 16/02/21 650
651 Electrical Testing & Certification 2w 20/01/21 02/02/21 651

652 P1 - Fit-out - Level 00 - Management Suite 16w 2d 17/08/20 08/12/20 652


653 Fit-out - Level 00 - Management Suite 16w 2d 17/08/20 08/12/20 653

654 P1 - Install 4 Nr lifts 24w 08/09/20 08/03/21 654


655 Lift 1A Inc Testing & Commissioning 10w 08/09/20 16/11/20 655
656 Lift 1B Inc Testing & Commissioning 10w 08/09/20 16/11/20 656
657 Lift 2A Inc Testing & Commissioning 10w 17/11/20 08/02/21 657
658 Lift 2B Inc Testing & Commissioning 10w 17/11/20 08/02/21 658
659 Test period 4w 09/02/21 08/03/21 659

660 P1 - Staircore Finishes 7w 23/11/20 22/01/21 660


661 Staircore 01 7w 23/11/20 22/01/21 661
662 Staircore 02 7w 23/11/20 22/01/21 662

663 Fit-Out - Car park 28w 11/05/20 20/11/20 31% 9% 663


664 SVPs & RWPs 4w 11/05/20 05/06/20 100% 70% 664
665 LTHW & BCWS horizontal distribution 5w 13/05/20 16/06/20 88% 5% 665
666 Ventilation Ductwork to lobby areas & bin store 2w 17/06/20 30/06/20 666
667 Pressure testing 1w 01/07/20 07/07/20 667
668 Pipework Insulation Inc Trace heating 4w 08/07/20 04/08/20 668
669 Install Brackets & Main Containment 4w 18/05/20 12/06/20 95% 75% 669
670 Install Secondary Containment for Lighting & Power 3w 01/06/20 19/06/20 60% 33% 670
671 Install Secondary Containment for - CCTV & Access Control 2w 22/06/20 03/07/20 671
672 Install cabling for Lighting & Power 2w 06/07/20 17/07/20 672
673 Install cabling for CCTV & Access Control Cabling 1w 20/07/20 24/07/20 673
674 Install cabling to Car Chargers 2w 27/07/20 07/08/20 674
675 Install Cabling for Fire Alarm System 3w 10/08/20 28/08/20 675
676 Install Submains cabling to Distribution boards & Lifts 2w 31/08/20 11/09/20 676
677 Install Submains cabling for IDNO boards in Risers 2w 14/09/20 25/09/20 677
678 Install lighting & Power Outlets 2w 28/09/20 09/10/20 678
679 Testing of 400/230V Cabling 2w 12/10/20 23/10/20 679
680 Testing & Commissioning CCTV & Access Control 1w 26/10/20 30/10/20 680
681 Testing & Commissioning of Fire Alarm 1w 02/11/20 06/11/20 681
682 Install CCTV & Access Control equipment 1w 09/11/20 13/11/20 682
683 Commissioning of CCTV & Access Conrol equipment 1w 16/11/20 20/11/20 683
684 Sprinkler Mist 7w 2d 05/08/20 24/09/20 684
685 Tank Room Install 1w 05/08/20 11/08/20 685
686 Car Park pipework install 3w 12/08/20 01/09/20 686
687 Pressure testing 3d 02/09/20 04/09/20 687

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021 Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
688 Electrical 1st Fix Containment & wiring 1w 02/09/20 08/09/20 688
689 Electrical 2nd Fix 2d 09/09/20 10/09/20 689
690 Electrical Testing & Commissioning 2d 11/09/20 14/09/20 690
691 Commissioning of plant 1w 18/09/20 24/09/20 691
692 Generator Room 2w 4d 31/08/20 17/09/20 692
693 Install Generator , Fuel Tank etc 3d 31/08/20 02/09/20 693
694 Electrical 1st Fix - Containment & Wiring 1w 03/09/20 09/09/20 694
695 Electrical 2nd Fix 2d 10/09/20 11/09/20 695
696 Electrical Testing & Commissioning 2d 14/09/20 15/09/20 696
697 Test & Commission Generator 2d 16/09/20 17/09/20 697

698 P1 - Building Finals 22w 19/10/20 06/04/21 698


699 Water On 19/10/20 19/10/20 699
700 Power On 19/10/20 19/10/20 700
701 Gas On 19/10/20 19/10/20 701
702 Pre-commissioning 9w 19/10/20 18/12/20 702
703 Final snagging 12w 04/01/21 26/03/21 703
704 Final commissioning 8w 11/01/21 05/03/21 704
705 Final Clean 3w 08/03/21 26/03/21 705
706 Client Demonstrations 1w 29/03/21 06/04/21 706

707 Final clean 4w 04/01/21 29/01/21 707


708 P3 Podium - Level 00 Carpark Podium Infill Level 01 Slab 61w 2d 02/12/19 05/03/21 47% 47% 708
709 P3 - Substructures 14w 02/12/19 20/03/20 100% 95% 709
710 P3 - piling - approx. 98Nr 1w 02/12/19 06/12/19 100% 100% 710
711 P3 - pile caps / ground beams 4w 16/12/19 24/01/20 100% 100% 711
712 P3 - Below slab drainage / services 1w 10/01/20 16/01/20 100% 100% 712
713 P3 - Make up levels to below basecoat asphalt 8w 27/01/20 20/03/20 100% 80% 713
714 P3 - Superstructure 16w 2d 24/02/20 19/06/20 93% 85% 714
715 Columns -GL H-K level 00 to 01 2w 24/02/20 06/03/20 100% 100% 715
716 Courtyard Floor Slab -GL H-K level 01 3w 09/03/20 27/03/20 100% 95% 716
717 Basecoat car-park 2w 09/03/20 20/03/20 100% 95% 717
718 Columns - level 00 to 01 8w 09/03/20 06/05/20 100% 100% 718
719 Courtyard Infill floor slab - level 01 3w 01/06/20 19/06/20 60% 33% 719
720 P3 - Envelope 6w 06/07/20 14/08/20 720
721 External walls 6w 06/07/20 14/08/20 721
722 P3 - Fit-out 15w 09/11/20 05/03/21 722
723 Landscaping / planting 6w 07/12/20 29/01/21 723
724 Fit-out car-park 10w 09/11/20 29/01/21 724
725 Final snagging 4w 04/01/21 29/01/21 725
726 Final commissioning 4w 01/02/21 26/02/21 726
727 Top-coat car-park 1w 15/02/21 19/02/21 727
728 Final Clean 2w 22/02/21 05/03/21 728
729 Client Demonstrations 1w 01/03/21 05/03/21 729

730 P2 Town Houses - 10Nr Town Houses 55w 4d 27/01/20 09/03/21 7% 2% 730
731 P2 - Substructures 31w 2d 27/01/20 04/09/20 83% 80% 731
732 Strip foundations 3w 27/01/20 14/02/20 100% 100% 732
733 P2 - Below slab drainage / services 3w 03/02/20 21/02/20 100% 100% 733
734 Foundation Block work 2w 18/02/20 02/03/20 100% 100% 734
735 Block beam flooring install 2w 27/04/20 11/05/20 100% 100% 735

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 2020
Revision No : C09
2021 Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
736 Ground Floor Screed 2w 24/08/20 04/09/20 736
737 P2 - Superstructure 14w 4d 11/05/20 20/08/20 37% 17% 737
738 Blockwork 4w 11/05/20 05/06/20 100% 100% 738
739 Level 01 Joist 2w 25/05/20 05/06/20 100% 739
740 Install L01-02 Brickwork 4w 05/06/20 02/07/20 25% 740
741 Level 02 Joist 2w 19/06/20 02/07/20 741
742 Install Blockwork L02-03 5w 03/07/20 06/08/20 742
743 Roof Joist 2w 07/08/20 20/08/20 743
744 P2 - Envelope 27w 2d 19/05/20 25/11/20 9% 4% 744
745 Brickwork 14w 2d 19/05/20 26/08/20 25% 19% 745
746 Windows 9w 09/07/20 09/09/20 746
747 Roof finishes 8w 24/08/20 16/10/20 747
748 Final flashings / seals 6w 17/09/20 28/10/20 748
749 Dismantle Ext. scaffold 4w 29/10/20 25/11/20 749
750 P2 - Internal Fit-out (10Nr Townhouse) 21w 3d 21/07/20 17/12/20 750
751 P2 - Fit-Out Townhouse Nr1 14w 1d 21/07/20 27/10/20 751
752 Install Stairs 3d 21/07/20 23/07/20 752
753 Install Floor Decking 3d 24/07/20 28/07/20 753
754 Partition walls incl board 1 side 1w 28/07/20 03/08/20 754
755 1st fix M&E 1w 05/08/20 11/08/20 755
756 1st fix Joinery 1w 05/08/20 11/08/20 756
757 Close walls / Plasterboard ceilings 1w 12/08/20 18/08/20 757
758 Plastering 2w 19/08/20 01/09/20 758
759 Drying 1w 02/09/20 08/09/20 759
760 Mist coat decoration 3d 10/09/20 14/09/20 760
761 2nd fix M&E 1w 10/09/20 16/09/20 761
762 2nd fix Joinery 1w 10/09/20 16/09/20 762
763 Floor tiling 3d 17/09/20 21/09/20 763
764 Install Kitchen 1w 15/09/20 21/09/20 764
765 Wall tiling 3d 17/09/20 21/09/20 765
766 Final fix M&E 1w 21/09/20 25/09/20 766
767 Floor finishes 1w 28/09/20 02/10/20 767
768 Final snagging 1w 05/10/20 09/10/20 768
769 Final Decoration 1w 09/10/20 15/10/20 769
770 Final clean 2d 16/10/20 19/10/20 770
771 Testing & commissioning 2w 14/10/20 27/10/20 771
772 P2 - Fit-Out Townhouse Nr 2 14w 1d 27/07/20 02/11/20 772
773 Install Stairs 3d 27/07/20 29/07/20 773
774 Install Floor Decking 3d 29/07/20 31/07/20 774
775 Partition walls incl board 1 side 1w 04/08/20 10/08/20 775
776 fix M&E 1w 11/08/20 17/08/20 776
777 1st fix Joinery 1w 11/08/20 17/08/20 777
778 Close walls / Plasterboard ceilings 1w 18/08/20 24/08/20 778
779 Plastering 2w 25/08/20 07/09/20 779
780 Drying 1w 09/09/20 15/09/20 780
781 Mist coat decoration 3d 16/09/20 18/09/20 781
782 2nd fix M&E 1w 16/09/20 22/09/20 782
783 2nd fix Joinery 1w 16/09/20 22/09/20 783
784 Floor tiling 3d 23/09/20 25/09/20 784
785 Install Kitchen 1w 21/09/20 25/09/20 785
786 Wall tiling 3d 23/09/20 25/09/20 786

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021 Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
787 Final fix M&E 1w 25/09/20 01/10/20 787
788 Floor finishes 1w 02/10/20 08/10/20 788
789 Final snagging 1w 09/10/20 15/10/20 789
790 Final Decoration 1w 15/10/20 21/10/20 790
791 Final clean 2d 22/10/20 23/10/20 791
792 Testing & commissioning 2w 20/10/20 02/11/20 792
793 P3 - Fit-Out Townhouse Nr 3 13w 2d 30/07/20 30/10/20 793
794 Install Stairs 3d 30/07/20 03/08/20 794
795 Install Floor Decking 3d 03/08/20 05/08/20 795
796 Partition walls incl board 1 side 1w 03/08/20 07/08/20 796
797 fix M&E 1w 10/08/20 14/08/20 797
798 1st fix Joinery 1w 10/08/20 14/08/20 798
799 Close walls / Plasterboard ceilings 1w 17/08/20 21/08/20 799
800 Plastering 2w 24/08/20 04/09/20 800
801 Drying 1w 08/09/20 14/09/20 801
802 Mist coat decoration 3d 15/09/20 17/09/20 802
803 2nd fix M&E 1w 15/09/20 21/09/20 803
804 2nd fix Joinery 1w 15/09/20 21/09/20 804
805 Floor tiling 3d 22/09/20 24/09/20 805
806 Install Kitchen 1w 18/09/20 24/09/20 806
807 Wall tiling 3d 22/09/20 24/09/20 807
808 Final fix M&E 1w 24/09/20 30/09/20 808
809 Floor finishes 1w 01/10/20 07/10/20 809
810 Final snagging 1w 08/10/20 14/10/20 810
811 Final Decoration 1w 14/10/20 20/10/20 811
812 Final clean 2d 21/10/20 22/10/20 812
813 Testing & commissioning 2w 19/10/20 30/10/20 813
814 P3 - Fit-Out Townhouse Nr 4 13w 4d 04/08/20 06/11/20 814
815 Install Stairs 3d 04/08/20 06/08/20 815
816 Install Floor Decking 3d 05/08/20 07/08/20 816
817 Partition walls incl board 1 side 1w 10/08/20 14/08/20 817
818 fix M&E 1w 17/08/20 21/08/20 818
819 1st fix Joinery 1w 17/08/20 21/08/20 819
820 Close walls / Plasterboard ceilings 1w 24/08/20 28/08/20 820
821 Plastering 2w 01/09/20 14/09/20 821
822 Drying 1w 15/09/20 21/09/20 822
823 Mist coat decoration 3d 22/09/20 24/09/20 823
824 2nd fix M&E 1w 22/09/20 28/09/20 824
825 2nd fix Joinery 1w 22/09/20 28/09/20 825
826 Floor tiling 3d 29/09/20 01/10/20 826
827 Install Kitchen 1w 25/09/20 01/10/20 827
828 Wall tiling 3d 29/09/20 01/10/20 828
829 Final fix M&E 1w 01/10/20 07/10/20 829
830 Floor finishes 1w 08/10/20 14/10/20 830
831 Final snagging 1w 15/10/20 21/10/20 831
832 Final Decoration 1w 21/10/20 27/10/20 832
833 Final clean 2d 28/10/20 29/10/20 833
834 Testing & commissioning 2w 26/10/20 06/11/20 834
835 P3 - Fit-Out Townhouse Nr 5 14w 1d 07/08/20 13/11/20 835
836 Install Stairs 3d 07/08/20 11/08/20 836
837 Install Floor Decking 3d 10/08/20 12/08/20 837

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021
Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
838 Partition walls incl board 1 side 1w 17/08/20 21/08/20 838
839 fix M&E 1w 24/08/20 28/08/20 839
840 1st fix Joinery 1w 24/08/20 28/08/20 840
841 Close walls / Plasterboard ceilings 1w 01/09/20 07/09/20 841
842 Plastering 2w 08/09/20 21/09/20 842
843 Drying 1w 22/09/20 28/09/20 843
844 Mist coat decoration 3d 29/09/20 01/10/20 844
845 2nd fix M&E 1w 29/09/20 05/10/20 845
846 2nd fix Joinery 1w 29/09/20 05/10/20 846
847 Floor tiling 3d 06/10/20 08/10/20 847
848 Install Kitchen 1w 02/10/20 08/10/20 848
849 Wall tiling 3d 06/10/20 08/10/20 849
850 Final fix M&E 1w 08/10/20 14/10/20 850
851 Floor finishes 1w 15/10/20 21/10/20 851
852 Final snagging 1w 22/10/20 28/10/20 852
853 Final Decoration 1w 28/10/20 03/11/20 853
854 Final clean 2d 04/11/20 05/11/20 854
855 Testing & commissioning 2w 02/11/20 13/11/20 855
856 P3 - Fit-Out Townhouse Nr 6 14w 3d 12/08/20 20/11/20 856
857 Install Stairs 3d 12/08/20 14/08/20 857
858 Install Floor Decking 3d 13/08/20 17/08/20 858
859 Partition walls incl board 1 side 1w 24/08/20 28/08/20 859
860 fix M&E 1w 01/09/20 07/09/20 860
861 1st fix Joinery 1w 01/09/20 07/09/20 861
862 Close walls / Plasterboard ceilings 1w 08/09/20 14/09/20 862
863 Plastering 2w 15/09/20 28/09/20 863
864 Drying 1w 29/09/20 05/10/20 864
865 Mist coat decoration 3d 06/10/20 08/10/20 865
866 2nd fix M&E 1w 06/10/20 12/10/20 866
867 2nd fix Joinery 1w 06/10/20 12/10/20 867
868 Floor tiling 3d 13/10/20 15/10/20 868
869 Install Kitchen 1w 09/10/20 15/10/20 869
870 Wall tiling 3d 13/10/20 15/10/20 870
871 Final fix M&E 1w 15/10/20 21/10/20 871
872 Floor finishes 1w 22/10/20 28/10/20 872
873 Final snagging 1w 29/10/20 04/11/20 873
874 Final Decoration 1w 04/11/20 10/11/20 874
875 Final clean 2d 11/11/20 12/11/20 875
876 Testing & commissioning 2w 09/11/20 20/11/20 876
877 P3 - Fit-Out Townhouse Nr 7 15w 17/08/20 27/11/20 877
878 Install Stairs 3d 17/08/20 19/08/20 878
879 Install Floor Decking 3d 18/08/20 20/08/20 879
880 Partition walls incl board 1 side 1w 01/09/20 07/09/20 880
881 fix M&E 1w 08/09/20 14/09/20 881
882 1st fix Joinery 1w 08/09/20 14/09/20 882
883 Close walls / Plasterboard ceilings 1w 15/09/20 21/09/20 883
884 Plastering 2w 22/09/20 05/10/20 884
885 Drying 1w 06/10/20 12/10/20 885
886 Mist coat decoration 3d 13/10/20 15/10/20 886
887 2nd fix M&E 1w 13/10/20 19/10/20 887
888 2nd fix Joinery 1w 13/10/20 19/10/20 888

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021
Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
889 Floor tiling 3d 20/10/20 22/10/20 889
890 Install Kitchen 1w 16/10/20 22/10/20 890
891 Wall tiling 3d 20/10/20 22/10/20 891
892 Final fix M&E 1w 22/10/20 28/10/20 892
893 Floor finishes 1w 29/10/20 04/11/20 893
894 Final snagging 1w 05/11/20 11/11/20 894
895 Final Decoration 1w 11/11/20 17/11/20 895
896 Final clean 2d 18/11/20 19/11/20 896
897 Testing & commissioning 2w 16/11/20 27/11/20 897
898 P3 - Fit-Out Townhouse Nr 8 15w 1d 20/08/20 03/12/20 898
899 Install Stairs 3d 20/08/20 24/08/20 899
900 Install Floor Decking 3d 24/08/20 26/08/20 900
901 Partition walls incl board 1 side 1w 07/09/20 11/09/20 901
902 fix M&E 1w 14/09/20 18/09/20 902
903 1st fix Joinery 1w 14/09/20 18/09/20 903
904 Close walls / Plasterboard ceilings 1w 21/09/20 25/09/20 904
905 Plastering 2w 28/09/20 09/10/20 905
906 Drying 1w 12/10/20 16/10/20 906
907 Mist coat decoration 3d 19/10/20 21/10/20 907
908 2nd fix M&E 1w 19/10/20 23/10/20 908
909 2nd fix Joinery 1w 19/10/20 23/10/20 909
910 Floor tiling 3d 26/10/20 28/10/20 910
911 Install Kitchen 1w 22/10/20 28/10/20 911
912 Wall tiling 3d 26/10/20 28/10/20 912
913 Final fix M&E 1w 28/10/20 03/11/20 913
914 Floor finishes 1w 04/11/20 10/11/20 914
915 Final snagging 1w 11/11/20 17/11/20 915
916 Final Decoration 1w 17/11/20 23/11/20 916
917 Final clean 2d 24/11/20 25/11/20 917
918 Testing & commissioning 2w 20/11/20 03/12/20 918
919 P3 - Fit-Out Townhouse Nr 9 15w 3d 25/08/20 10/12/20 919
920 Install Stairs 3d 25/08/20 27/08/20 920
921 Install Floor Decking 3d 28/08/20 01/09/20 921
922 Partition walls incl board 1 side 1w 14/09/20 18/09/20 922
923 fix M&E 1w 21/09/20 25/09/20 923
924 1st fix Joinery 1w 21/09/20 25/09/20 924
925 Close walls / Plasterboard ceilings 1w 28/09/20 02/10/20 925
926 Plastering 2w 05/10/20 16/10/20 926
927 Drying 1w 19/10/20 23/10/20 927
928 Mist coat decoration 3d 26/10/20 28/10/20 928
929 2nd fix M&E 1w 26/10/20 30/10/20 929
930 2nd fix Joinery 1w 26/10/20 30/10/20 930
931 Floor tiling 3d 02/11/20 04/11/20 931
932 Install Kitchen 1w 29/10/20 04/11/20 932
933 Wall tiling 3d 02/11/20 04/11/20 933
934 Final fix M&E 1w 04/11/20 10/11/20 934
935 Floor finishes 1w 11/11/20 17/11/20 935
936 Final snagging 1w 18/11/20 24/11/20 936
937 Final Decoration 1w 24/11/20 30/11/20 937
938 Final clean 2d 01/12/20 02/12/20 938
939 Testing & commissioning 2w 27/11/20 10/12/20 939

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Issue Date : 29/04/2019 Revision Date : 22/05/2020
2019 Revision No : C09
2020 2021
Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject
Issue Date: 29/04/2019
Rev No: C09
CANALSIDE - PURPLE PHASE
CONSTRUCTION PROGRAMME
Rev Date:22/05/2020
Progress 09

2019 2020 2021


Planned
Line Name Duration Start Finish
percent Percent Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
complete complete
(PPC) 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
940 P3 - Fit-Out Townhouse Nr 10 16w 28/08/20 17/12/20 940
941 Install Stairs 3d 28/08/20 01/09/20 941
942 Install Floor Decking 3d 02/09/20 04/09/20 942
943 Partition walls incl board 1 side 1w 21/09/20 25/09/20 943
944 fix M&E 1w 28/09/20 02/10/20 944
945 1st fix Joinery 1w 28/09/20 02/10/20 945
946 Close walls / Plasterboard ceilings 1w 05/10/20 09/10/20 946
947 Plastering 2w 12/10/20 23/10/20 947
948 Drying 1w 26/10/20 30/10/20 948
949 Mist coat decoration 3d 02/11/20 04/11/20 949
950 2nd fix M&E 1w 02/11/20 06/11/20 950
951 2nd fix Joinery 1w 02/11/20 06/11/20 951
952 Floor tiling 3d 09/11/20 11/11/20 952
953 Install Kitchen 1w 05/11/20 11/11/20 953
954 Wall tiling 3d 09/11/20 11/11/20 954
955 Final fix M&E 1w 11/11/20 17/11/20 955
956 Floor finishes 1w 18/11/20 24/11/20 956
957 Final snagging 1w 25/11/20 01/12/20 957
958 Final Decoration 1w 01/12/20 07/12/20 958
959 Final clean 2d 08/12/20 09/12/20 959
960 Testing & commissioning 2w 04/12/20 17/12/20 960

961 P2 - Building Finals 23w 4d 10/09/20 09/03/21 961


962 Water On 11/09/20 11/09/20 962
963 Power On 11/09/20 11/09/20 963
964 Gas On 11/09/20 11/09/20 964
965 Pre-commissioning 9w 10/09/20 11/11/20 965
966 Final snagging 12w 30/10/20 04/02/21 966
967 Final commissioning 10w 11/11/20 02/02/21 967
968 Final Clean 4w 02/02/21 01/03/21 968
969 Client Demonstrations 1w 03/03/21 09/03/21 969

970 Purple Phase - External Works / Landscaping 26w 1d 01/10/20 19/04/21 970
971 Footpath Possessions 01/10/20 01/10/20 971
972 External Works / Landscaping 21w 06/11/20 19/04/21 972

973 PHASE 3 COMPLETION 19/04/21 19/04/21 973

1 59 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85
Planned
Line Name Duration Start Finish
percent Percent 2 23 14 4 25 16 6 27 17 9 30 20 11 1 22 13 3 24 14 5 26 16 7 28 18 8 1 22 12
complete complete
(PPC) Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2019 2020 2021
Canalside Purple
Summary Site Establishment Milestone Demolition Substructure Superstructure Envelope Roofing Fit-Out
Building Finals Externals
Milestone Appearances
Diamond
Issue Date : 29/04/2019 Revision Date : 22/05/2020 Revision No : C09 Notes: Progress 09
Project Ref. C:\Users\kumard\OneDrive - Gilbert-Ash Ltd\Asta Powerproject\Projects\468 - Canalside\Progress Files\Cons progress files\Cons. P09.pp Planned by Asta Powerproject