PT Pionirbeton Industri
Project Start Date 4/7/2019 (Thursday) Display Week 1 Week 1 Week 2 Week 3 Week 4
Project Lead Heri Purnadi 1 Jul 2019 8 Jul 2019 15 Jul 2019 22 Jul 2019
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
% WORK
WBS TASK LEAD START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE DAYS
1 Penurunan Mixer Tank - -
1.1 Menurunkan mixer Riski Thu 04/7/19 Fri 05/7/19 2 0% 2
1.2 Kirim truck ke workshop Pionir Fri 05/7/19 Fri 05/7/19 1 0% 1
2 Repair Chasis - -
2.1 Cleaning chasis Iskandar Sat 06/7/19 Tue 09/7/19 4 0% 2
2.2 Pengukuran area korosi Iskandar Wed 10/7/19 Wed 10/7/19 1 0% 1
2.3 Pemotongan plat Iskandar Wed 10/7/19 Thu 11/7/19 2 0% 2
2.4 Pengelasan Iskandar Thu 11/7/19 Wed 17/7/19 7 0% 5
2.5 Painting dan Finishing Iskandar Thu 18/7/19 Mon 22/7/19 5 0% 3
3 Repair Cabin - -
3.1 Cleaning Cabin Iskandar Sat 06/7/19 Tue 09/7/19 4 0% 2
3.2 Pengukuran area korosi Iskandar Wed 10/7/19 Wed 10/7/19 1 0% 1
3.3 Pemotongan plat Iskandar Wed 10/7/19 Wed 10/7/19 1 0% 1
3.4 Pengelasan Iskandar Thu 11/7/19 Wed 17/7/19 7 0% 5
3.5 Painting dan Finishing Iskandar Thu 18/7/19 Tue 23/7/19 6 0% 4