PVC INSERT INSTALLATION 2 WEEK LOOK AHEAD SCHEDULE

MIDONGPHIL CONSTRUCTION CORP,

Project Start Date 10/22/2019 (Tuesday) Display Week 1 Week 1 Week 2


Project Lead MIDONGPHIL Location: Stabling Area 21 Oct 2019 28 Oct 2019
21 22 23 24 25 26 27 28 29 30 31 1 2 3
P
WBS TASK CHAINAGE LEAD START END DAYS % DONE WORK M T W T F S S M T W T F S S
R
1 Trackworks - -

Rebar installation, Rail


1.1 Installation, Formworks, Steconfer Mon 9/30/19 Thu 10/24/19 25 95% 19
Fastener Installation
WB 3+934 - 3+970,
EB 3+944 - 3+975
1.2 Cleaning and Final Check Steconfer Thu 10/24/19 Thu 10/24/19 1 0% 1
Survey Pre-pour
1.3 Steconfer Thu 10/24/19 Thu 10/24/19 1 0% 1
Inspection
2 Trackworks - -

Rebar installation, Rail


2.1 Installation, Formworks, Steconfer Sat 10/26/19 Tue 10/29/19 4 0%
Fastener Installation
WB 3+970 - 4+020,
EB 3+975 - 4+025
2.2 Cleaning and Final Check Steconfer Tue 10/29/19 Tue 10/29/19 1 0%
Survey Pre-pour
2.3 Steconfer Tue 10/29/19 Tue 10/29/19 1 0%
Inspection
3 Third Rail Works - -
Layout of Insert Jig
3.1 3+975 - 4+025 MidongPhil Wed 10/23/19 Fri 10/25/19 3 0% 3
Locations
3.2 Installation of PVC Inserts 3+975 - 4+025 MidongPhil Wed 10/23/19 Mon 10/28/19 6 0% 4
PVC Insert Installation
WB 3+934 - 3+970,
3.3 Pre Concrete Pouring MidongPhil Thu 10/24/19 Thu 10/24/19 1 0%
EB 3+944 - 3+975
Inspection
PVC Insert Installation
WB 3+970 - 4+020,
3.4 Pre Concrete Pouring MidongPhil Tue 10/29/19 Tue 10/29/19 1 0% 1
EB 3+975 - 4+025
Inspection
4 Concrete Pouring
WB 3+934 - 3+970,
4.1 First Pour Steconfer Fri 10/25/19 Fri 10/25/19 1 0%
EB 3+944 - 3+975
WB 3+970 - 4+020,
4.2 Second Pour Steconfer Wed 10/30/19 Wed 10/30/19 1 0%
EB 3+975 - 4+025
-