The document provides a 2-week look ahead schedule for a PVC insert installation project with the following key details:
- MidongPhil Construction will be installing PVC inserts into concrete tracks from October 23rd to 28th between chainages 3+975 to 4+025.
- Steconfer will be pouring the concrete for the tracks in two sections - from October 25th to 25th from 3+934 to 3+970 and from October 30th to 30th from 3+970 to 4+020.
- Other tasks include rebar installation, formwork, cleaning and inspection work by Steconfer before the concrete pours.
The document provides a 2-week look ahead schedule for a PVC insert installation project with the following key details:
- MidongPhil Construction will be installing PVC inserts into concrete tracks from October 23rd to 28th between chainages 3+975 to 4+025.
- Steconfer will be pouring the concrete for the tracks in two sections - from October 25th to 25th from 3+934 to 3+970 and from October 30th to 30th from 3+970 to 4+020.
- Other tasks include rebar installation, formwork, cleaning and inspection work by Steconfer before the concrete pours.
The document provides a 2-week look ahead schedule for a PVC insert installation project with the following key details:
- MidongPhil Construction will be installing PVC inserts into concrete tracks from October 23rd to 28th between chainages 3+975 to 4+025.
- Steconfer will be pouring the concrete for the tracks in two sections - from October 25th to 25th from 3+934 to 3+970 and from October 30th to 30th from 3+970 to 4+020.
- Other tasks include rebar installation, formwork, cleaning and inspection work by Steconfer before the concrete pours.
Project Lead MIDONGPHIL Location: Stabling Area 21 Oct 2019 28 Oct 2019 21 22 23 24 25 26 27 28 29 30 31 1 2 3 P WBS TASK CHAINAGE LEAD START END DAYS % DONE WORK M T W T F S S M T W T F S S R 1 Trackworks - -