Pagsibol Village

Brgy Timalan, Naic Cavite


Contractor ALPHACONSTRUCT CORPORATION

Billing Date Location Descrition Payment Date Amount Retention Net Payment
1 Feb 4, 2019 Blk 9 Lot 1-6 Steel reinforcement for ground floor wall including cr Feb 12, 2019 35,261.11 3,526.11 31,735.00
Blk 10 Lot 10-14 Foundation
2 Feb 11, 2019 Blk 9 Lot 7-8 SOG Steel Fabrication and installation Feb 19, 2019 79,872.19 7,987.22 71,884.97
Blk 10 Lot 10-14 SOG works and Steel reinforcement for ground floor wall including
cr
3 Mar 11, 2019 Blk 3 Lot 24-25 First Lift installation of forms Feb 19, 2019 11,916.67 1,191.67 10,725.00
4 Mar 18, 2019 Blk 3 Lot 24-25 First Lift Rebar Installation and Concreting (30% retention on Feb 26, 2019 16,133.34 2,310.00 13,823.34
concreting)
Blk 7 Lot 12-13 First Lift installation of forms
5 Mar 25, 2019 Blk 7 Lot 12-13 CR Zocallo, First Lift Rebar Installation and Concreting 27,072.23
Blk 7 Lot 4-5 First Lift installation of forms
6 Apr 1, 2019 Blk 7 Lot 4-5 CR Wall Footing, CR Zocallo, First Lift installation of forms, Rebar 17,905.56
Installation and Concreting
188,161.10 15,015.00 128,168.31