You are on page 1of 1

ID WBS Task Name Duration Start Finish September 2019 October 2019 November 2019 December 2019

31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 02 05 08 11 14
1 1 Qiddya Cliff Infrastructure Installation 70.5 days Sun 08-09-19 Tue 03-12-19 Qiddya Cliff Infrastructure Installation

2 1.1 Preparations , Mobilization and roading 40.5 days Thu 12-09-19 Thu 31-10-19 Preparations , Mobilization and roading

3 1.1.1 ordering and delivery for Active components 40.5 days Thu 12-09-19 Thu 31-10-19 ordering and delivery for Active components

4 1.1.2 Mobilization 15 days Thu 12-09-19 Tue 01-10-19 Mobilization

5 1.1.3 soil inspection 5 days Thu 12-09-19 Wed 18-09-19 soil inspection

6 1.1.4 Road Grading 16.75 days Wed 18-09-19 Wed 09-10-19

7 1.1.4.1 Arc grading 15 days Wed 18-09-19 Mon 07-10-19

8 1.1.4.2 Slop road grading 15 days Sun 22-09-19 Wed 09-10-19

9 1.2 Civil works 48.75 days Sun 08-09-19 Wed 06-11-19 Civil works

10 1.2.1 Civil Trenching 29 days Sun 08-09-19 Sun 13-10-19 Civil Trenching

11 1.2.2 piping and conduting 15 days Sun 22-09-19 Wed 09-10-19 piping and conduting

12 1.2.3 Fiber cabling works 15 days Sun 29-09-19 Wed 16-10-19 Fiber cabling works

13 1.2.4 Concrete Basing and Rafting ( Including Dry outs ) 25 days Sun 15-09-19 Tue 15-10-19 Concrete Basing and Rafting ( Including Dry outs )

14 1.2.5 Fencing and Steel works 15 days Sun 20-10-19 Wed 06-11-19

15 1.2.5.1 Fencing Generators locations 15 days Sun 20-10-19 Wed 06-11-19

16 1.2.5.2 Generators Steel Structural Covering 10 days Tue 22-10-19 Sun 03-11-19

17 1.3 Electrical Panels installations 25.5 days Sun 13-10-19 Tue 12-11-19 Electrical Panels installations

18 1.3.1 Electrical Panels installations 16 days Sun 13-10-19 Thu 31-10-19 Electrical Panels installations

19 1.3.2 electrical Terminations 5 days Sun 03-11-19 Thu 07-11-19 electrical Terminations

20 1.3.3 Testing and project inspection 3 days Sun 10-11-19 Tue 12-11-19 Testing and project inspection

21 1.4 Active Works 15 days Sun 10-11-19 Wed 27-11-19 Active Works

22 1.4.1 installation and Configuration 15 days Sun 10-11-19 Wed 27-11-19 installation and Configuration

23 1.5 Project Documentation 30 days Mon 28-10-19 Tue 03-12-19 Project Documentation

24 1.5.1 Documentation 30 days Mon 28-10-19 Tue 03-12-19 Documentation

25 1.5.2 Review and Approve Docmuentation 15 days Sun 10-11-19 Wed 27-11-19 Review and Approve Docmuentation

26 1.5.3 Documentation handover 13 days Sun 10-11-19 Mon 25-11-19 Documentation handover

Task Critical Task Progress Rolled Up Task Rolled Up Progress Project Summary
Project: Qiddya_TP_Martin_Update10
Date: Tue 10-09-19 Task Progress Milestone Rolled Up Critical Task Split Group By Summary
Prepa: Essam Abdelaziz
Critical Task Summary Rolled Up Milestone External Tasks Deadline

Page 1

You might also like