2nd Half 1st Half 2nd Half

ID Task Name Duration Start Finish Predecessors Q4 Q3 Q2 Q1 Q4


1
2 WORK SCHEDULE FOR THE CONSTRUCTION OF 495 days Thu 25-10-18 Mon 24-08-20
PS2GS2 STAGE INTEGRATION BUILDING
INCLUDING CIVIL, INTERNAL ELECTRICAL, FIRE
ALARM, EOT CRANES, AIR CONDITIONING
WORKS & COMPRESSED AIR PIPELINE WORKS

3 Work commenced 87 days Thu 25-10-18 Sat 16-02-19


4 Finalization of the Agencies 32 days Thu 25-10-18 Fri 07-12-18
5 Finalization of the GA drawings 32 days Sat 08-12-18 Sat 19-01-19 4
6 Structural drawings vetting from IIT 11 days Mon 21-01-19 Thu 31-01-19 5
7 Finalization of the foundation drawings from HAL 12 days Fri 01-02-19 Sat 16-02-19 6

8 Site Mobilzation 26 days Tue 01-01-19 Thu 31-01-19


9 Clearing of Site 26 days Tue 01-01-19 Thu 31-01-19
10 Civil Works 402 days Fri 01-02-19 Thu 30-07-20
11 Main Building /PEB Building 253 days Fri 01-02-19 Thu 09-01-20
12 Excavation of Footing 60 days Fri 01-02-19 Wed 24-04-19
13 Casting Of Footing 45 days Mon 25-02-19 Fri 26-04-19
14 Casting of Column 60 days Fri 01-03-19 Wed 22-05-19
15 Casting of Colum Second Lift 30 days Mon 25-03-19 Fri 03-05-19
16 Casting of Plinth Beam 30 days Sat 15-06-19 Wed 24-07-19
17 Casting of Pedestal 30 days Thu 22-08-19 Wed 02-10-19
18 Fixing of Base plate for MS Column ( PEB ) 20 days Thu 19-09-19 Wed 16-10-19
19 Fabrication Of PEB Structure 60 days Fri 01-02-19 Wed 24-04-19
20 Supply of PEB Structure 30 days Fri 27-09-19 Thu 07-11-19
21 Erection of PEB structure 60 days Tue 22-10-19 Thu 09-01-20
22 Construction of Annex Buildings - 02 nos 222 days Thu 03-10-19 Thu 30-07-20

23 Annex Building - 1 / Office Block 184 days Thu 03-10-19 Tue 09-06-20
24 Footing of Annex Block - 1 45 days Thu 03-10-19 Mon 02-12-19
25 Columns up to Plinth 30 days Wed 16-10-19 Mon 25-11-19
26 Casting of Plinth Beam 20 days Fri 01-11-19 Wed 27-11-19
27 Casting of Base Slab 25 days Fri 15-11-19 Tue 17-12-19
28 Column up to GF Lintel 25 days Mon 02-12-19 Fri 03-01-20
29 Castiing of Lintel 22 days Mon 16-12-19 Tue 14-01-20
30 Column above Lintel 25 days Wed 01-01-20 Mon 03-02-20
31 Stare case at GF Roof Level 30 days Mon 13-01-20 Wed 19-02-20
32 Casting of Gf Slab 20 days Mon 03-02-20 Wed 26-02-20
33 Column up to FF Lintel 25 days Wed 12-02-20 Fri 13-03-20
34 Castiing of Lintel 22 days Sat 22-02-20 Mon 23-03-20
35 Column above Lintel 25 days Mon 02-03-20 Fri 03-04-20
36 Stare case up to FF Roof Level 30 days Fri 13-03-20 Thu 23-04-20
37 Castiing of FF Slab 25 days Fri 20-03-20 Thu 23-04-20
38 Column up to Second F Lintel 20 days Wed 01-04-20 Tue 28-04-20
39 Castiing of Lintel 22 days Tue 14-04-20 Wed 13-05-20
40 Column above Lintel 25 days Wed 22-04-20 Tue 26-05-20
41 Stare case up to Roof Level 25 days Fri 01-05-20 Thu 04-06-20
42 Casting of Second Roof Slab 20 days Wed 13-05-20 Tue 09-06-20
43 Annex Building - 2 / AHU Block 161 days Thu 03-10-19 Thu 07-05-20
44 Footing of Annex Block - 2 45 days Thu 03-10-19 Mon 02-12-19
45 Columns up to Plinth 30 days Wed 16-10-19 Mon 25-11-19
46 Casting of Plinth Beam 20 days Fri 01-11-19 Wed 27-11-19
47 Casting of Base Slab 25 days Fri 15-11-19 Tue 17-12-19
48 Casting of Columns First Lift 20 days Mon 02-12-19 Fri 27-12-19
49 Casting of Columns Second Lift 20 days Mon 16-12-19 Fri 10-01-20
50 Casting of Columns Third Lift 25 days Wed 01-01-20 Mon 03-02-20
51 Casting of Columns Forth Lift 25 days Mon 13-01-20 Thu 13-02-20
52 Castiing of Lintel 22 days Mon 03-02-20 Fri 28-02-20
53 Column above Lintel 25 days Wed 12-02-20 Fri 13-03-20
54 Stare case at 10.39 Level 22 days Sat 22-02-20 Mon 23-03-20
55 Casting Roof Slab at 10.39 M 25 days Mon 02-03-20 Fri 03-04-20
56 Casting of Columns First Lift 30 days Fri 13-03-20 Thu 23-04-20
57 Casting of Columns Second Lift 25 days Fri 20-03-20 Thu 23-04-20
58 Casting of Columns Third Lift 20 days Wed 01-04-20 Tue 28-04-20
59 Castiing of Lintel 22 days Wed 08-04-20 Thu 07-05-20
60 Stare case at 17.82 M Level 25 days Fri 03-04-20 Thu 07-05-20
61 Casting Roof Slab at 11.82 M 25 days Fri 03-04-20 Thu 07-05-20
62 Construction of Security Cabin 45 days Mon 13-05-19 Tue 09-07-19
63 Excavation for footing 7 days Mon 13-05-19 Mon 20-05-19
64 Casting of footing 3 days Mon 20-05-19 Wed 22-05-19
65 Casting of pedestal upto the plinth beam 6 days Sat 18-05-19 Fri 24-05-19
66 Casting of Plinth Beam 15 days Tue 21-05-19 Fri 07-06-19
67 Super Structure 15 days Wed 29-05-19 Sat 15-06-19
68 Balance civil works 353 days Wed 30-01-19 Thu 21-05-20

Task Inactive Task Manual Summary


Split Inactive Task Start-only
Milestone Inactive Milestone Finish-only
Project: PS2GS2.mpp
Summary Inactive Summary Progress
Date: Thu 17-01-19
Project Summary Manual Task Deadline
External Tasks Duration-only
External Milestone Manual Summary Rollup

Page 1
2nd Half 1st Half 2nd Half
ID Task Name Duration Start Finish Predecessors Q4 Q3 Q2 Q1 Q4
69 Brick work 115 days Sat 30-11-19 Mon 04-05-20
70 Fixing Of Doors & Windows 50 days Mon 16-12-19 Wed 19-02-20
71 Fixing of Steel & Aluminium Work 90 days Fri 20-12-19 Mon 20-04-20
72 Plastering 100 days Thu 05-12-19 Fri 17-04-20
73 Roofing/Ceiling 50 days Fri 13-03-20 Thu 21-05-20
74 Roof Sheeting 50 days Sat 18-01-20 Tue 24-03-20
75 Wall Sheet Cladding 50 days Fri 10-01-20 Mon 16-03-20
76 Flooring, Pavings & Road Work 100 days Fri 03-01-20 Mon 18-05-20
77 Water Supply and Sanitary 120 days Wed 30-01-19 Wed 10-07-19
78 HVAC Works 210 days Thu 27-12-18 Thu 03-10-19
79 Supply of SA GI ducting and sheets 12 days Sat 27-04-19 Sat 11-05-19
80 Supply of SA Duct Line Acoustic 12 days Sat 27-04-19 Sat 11-05-19
81 Supply of SA Thermal Insulation 7 days Mon 15-04-19 Tue 23-04-19
82 Supply of RA GI ducting and sheets 7 days Mon 15-04-19 Tue 23-04-19
83 Supply of RA Duct Line Acoustic 12 days Mon 15-04-19 Tue 30-04-19
84 Supply of RA Thermal Insulation 21 days Tue 16-04-19 Tue 14-05-19
85 Supply of Aluminium supply air grilles with damper. 21 days Tue 16-04-19 Tue 14-05-19

86 Supply of Aluminium return air grilles without 21 days Tue 16-04-19 Tue 14-05-19
damper.
87 Supply of Aluminium supply air square diffuser with 21 days Tue 16-04-19 Tue 14-05-19
damper
88 Supply of Aluminium return/exhaust air square 21 days Tue 16-04-19 Tue 14-05-19
diffuser without damper.
89 Supply of Al Volume control dampers for Slot 21 days Tue 16-04-19 Tue 14-05-19
Diffusers & supply air collar of Linear Grill
90 Supply of GI Volume control dampers for ducts 21 days Tue 16-04-19 Tue 14-05-19

91 Supply of AHU 11 days Mon 01-07-19 Mon 15-07-19


92 AHU Placement & Fittings 50 days Sat 20-07-19 Wed 25-09-19
93 Installation of SA GI duct 50 days Mon 22-07-19 Thu 26-09-19
94 Installation of RA GI duct 50 days Mon 29-07-19 Thu 03-10-19
95 Supply of Chillers 14 days Thu 01-08-19 Mon 19-08-19
96 SA duct line acoustic 41 days Fri 09-08-19 Thu 03-10-19
97 Placement of Chillers 20 days Mon 02-09-19 Fri 27-09-19
98 RA duct line acoustic 41 days Fri 09-08-19 Thu 03-10-19
99 HVAC Panel with laying of cables 30 days Fri 23-08-19 Thu 03-10-19
100 SA thermal insulation 41 days Fri 09-08-19 Thu 03-10-19
101 RA thermal insulation 41 days Fri 09-08-19 Thu 03-10-19
102 Al SA sqr diffuser with damper 26 days Thu 29-08-19 Thu 03-10-19
103 VCD for slot diffusers & air collar linear grill 35 days Fri 16-08-19 Thu 03-10-19
104 Al RA sqr diffuser with damper 26 days Thu 29-08-19 Thu 03-10-19
105 HVAC Piping 25 days Sat 10-08-19 Thu 12-09-19
106 EOT Works 65 days Fri 01-03-19 Wed 29-05-19
107 Supply of EOT Crane 45 days Fri 01-03-19 Thu 02-05-19
108 EOT Crane 20 days Fri 03-05-19 Wed 29-05-19 107
109 Electrical Works 180 days Thu 30-05-19 Mon 27-01-20
110 Supply of Electrical Fittings & Accessories 14 days Thu 30-05-19 Sat 15-06-19
111 Internal Electrical Works 30 days Mon 08-07-19 Wed 14-08-19
112 LT cables (Aluminium) 30 days Mon 01-07-19 Thu 08-08-19
113 Copper wires laying 25 days Tue 27-08-19 Mon 30-09-19
114 Sockets & Switch Board 35 days Thu 14-11-19 Mon 30-12-19
115 Placing and fixing LT Panel at PS2/GS2 10 days Tue 31-12-19 Mon 13-01-20
116 Cables laying upto Distribution Boards 30 days Fri 30-08-19 Thu 10-10-19
117 Point wiring from DB 40 days Mon 02-09-19 Fri 25-10-19
118 Building Light Control Box 45 days Sat 16-11-19 Wed 15-01-20
119 Earthing 30 days Fri 22-11-19 Wed 01-01-20
120 Cable End Terminations 30 days Mon 02-12-19 Fri 10-01-20
121 Telephone cables 30 days Mon 16-12-19 Thu 23-01-20
122 Fire Alarm Works 22 days Fri 27-12-19 Fri 24-01-20
123 Compressed Airline Works 118 days Fri 27-12-19 Thu 04-06-20
124 Supply of Pipeline and accessories 45 days Fri 27-12-19 Mon 24-02-20
125 Compressed Airline 75 days Sat 22-02-20 Thu 04-06-20
126 Miscellaneous Works 43 days Fri 05-06-20 Sat 01-08-20
127 Balance works 21 days Fri 05-06-20 Fri 03-07-20
128 Painting & Finishing 21 days Mon 06-07-20 Sat 01-08-20
129 Commissioning Trials/Handover to HAL 15 days Mon 03-08-20 Fri 21-08-20

Task Inactive Task Manual Summary


Split Inactive Task Start-only
Milestone Inactive Milestone Finish-only
Project: PS2GS2.mpp
Summary Inactive Summary Progress
Date: Thu 17-01-19
Project Summary Manual Task Deadline
External Tasks Duration-only
External Milestone Manual Summary Rollup